WBV -- HARVEY / WESTWEGO (69 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
WBV-14a.1
| Harvey Canal West Bank Levees - 2nd Englt Phase 1 | 8(a) - MATOC | Reeves Electrical Service (RES) | $1.77 | 04-15-2008 |
11-03-2008
|
WBV-14a.2
| Harvey Canal West Bank Levees - Phase 2 - Estelle PS to Vicinity of Lapalco Ove | HUBZONE - MATOC - Low Bid | Purnell Construction Co., Inc. | $13.06 | 11-12-2010 |
05-24-2012
|
WBV-14b.1
| Orleans Village to Hwy 45, Levee - Phase 1 | HZ-MATOC | Cycle Construction Co., LLC | $3.00 | 08-28-2007 |
05-21-2008
|
WBV-14b.2
| Orleans Village to Hwy 45 Levee - Phase 2 | Firm Fixed Price - MATOC | Creek Services, LLC | $11.06 | 09-25-2009 |
02-16-2011
|
WBV-14c.1
| New Westwego Pump Station to Orleans Village - 3rd Enlgt - Phase 1 | HZ-MATOC | Clark Construction Enterprises, LLC | $8.98 | 03-14-2008 |
09-03-2009
|
WBV-14c.2
| New Westwego Pump Station to Orleans Village - Phase 2 | HUBZONE - BV | Phylway Construction | $26.54 | 06-14-2010 |
12-09-2011
|
WBV-14d
| V-line Floodwall | HZ-MATOC | Shavers-Whittle Construction | $17.15 | 07-02-2009 |
03-31-2011
|
WBV-14e.1
| V-line Levee, East of Vertex - Phase 1 | HZ-MATOC | Bucktown Contractors and Company | $8.01 | 06-06-2008 |
05-22-2009
|
WBV-14e.2
| V-line levee, East of Vertex - Phase 2 | HZ-MATOC | Purnell Construction Co., Inc. | $15.81 | 03-26-2010 |
10-04-2010
|
WBV-14e.2a
| V-line levee, East of Vertex - Phase 2 | HZ-MATOC | Phylway Construction | $13.85 | 01-21-2011 |
10-20-2011
|
WBV-14f.2
| Hwy 45 levee - Phase 2 | Firm Fixed Price | Clark Construction Enterprises, LLC | $4.94 | 09-17-2009 |
10-22-2010
|
WBV-14g.1
| Old Estelle to New Estelle | HZ-MATOC | Shavers-Whittle Construction | $2.50 | 09-13-2007 |
06-19-2008
|
WBV-14g.2
| Estelle Pump Station Vicinity Floodwalls | HZ-MATOC | Creek Services, LLC | $20.57 | 08-21-2009 |
07-21-2011
|
WBV-14i
| V-Line Levee, LA 3134 Highway Crossing | Unrestricted - Best Value | Shavers-Whittle Construction | $13.07 | 03-24-2010 |
03-31-2012
|
WBV-14j
| Westwego to Harvey Utility Crossings and Miscellaneous Sector Gate Retrofits | HUBZONE - MATOC - Low Bid | Aquaterra-CAYO | $8.40 | 12-13-2010 |
12-02-2011
|
WBV-15a.1
| Lake Cataouatche Pump Station to Segnette State Park - Phase 1 | Unrestricted - Best Value | Odebrecht Construction | $44.72 | 07-27-2007 |
07-09-2009
|
WBV-15a.2
| Lake Cataouatche Pump Station to Segnette State Park - Phase 2 | HUBZONE - BV | Phylway Construction | $41.31 | 02-04-2010 |
11-22-2011
|
WBV-15a.2a
| Lake Cataouatche Pump Station to Segnettte State Park at Chevron Pipeline | SDV-MATOC | Conquistidor Dorado JV | $2.61 | 01-24-2012 |
|
WBV-15b.1
| Lake Cataouatche Pump Station Fronting Protection, Modifications | HZ-MATOC | Cycle Construction Co., LLC | $4.86 | 08-31-2007 |
05-28-2008
|
WBV-15b.2
| Lake Cataouatche Pump Station Fronting Protection, Modifications | HZ-MATOC | Merrick Construction Co. | $23.74 | 04-10-2009 |
|
WBV-15b.2a
| Lake Cataouatche Pump Station Fronting Protection, Modifications | HZ-MATOC | Healtheon | $1.37 | 09-12-2011 |
08-22-2012
|
WBV-16.1
| Segnette PS to New Westwego Pump Station Floodwall - Phase 1 | HZ-MATOC | Cajun Constructors | $14.75 | 05-23-2007 |
06-06-2008
|
WBV-16.1a
| Company Canal Barge Gate Modifications & Channel Dredging | HZ-MATOC | Creek Services, LLC | $1.52 | 06-04-2009 |
12-18-2009
|
WBV-16.2
| Bayou Segnette Complex | Unrestricted - Best Value | Cajun Constructors | $42.81 | 02-10-2010 |
|
WBV-16b
| Segnette Pump Station Fronting Protection & Modifications. | Unrestricted - Best Value | M.R. Pittman Group, LLC. | $19.57 | 01-25-2010 |
07-31-2012
|
WBV-17b.1
| Station 160+00 to Hwy 90 - Phase 1 | HUBZONE | Vistas Construction of Illinois, Inc. | $14.62 | 03-19-2008 |
08-16-2010
|
WBV-17b.2
| Hwy 90 to Lake Cataouatche Pumping Station Levee, Station 125 to 160 - Phase 2 | HUBZONE - MATOC - Low Bid | Healtheon | $5.30 | 11-02-2010 |
11-16-2011
|
WBV-18.1
| Hwy 90 to Lake Cataouatche Pump Station - Phase 1 | Unrestricted | Manson Gulf | $16.85 | 10-24-2006 |
12-23-2008
|
WBV-18.2
| Hwy 90 to Lake Cataouatche Pump Station - Phase 2 | Unrestricted - Best Value | Circle Inc. | $12.31 | 08-21-2009 |
10-10-2011
|
WBV-20
| New Westwego Pump Station Fronting Protection and Modifications | Firm Fixed Price - MATOC | Shavers-Whittle Construction | $14.68 | 10-02-2009 |
09-01-2011
|
WBV-21
| Old Westwego Pump Station Fronting Protection & Modifications | HUBZONE - MATOC - Low Bid | Reeves Electrical Service (RES) | $3.56 | 04-15-2010 |
08-10-2011
|
WBV-22
| Westwego Floodwall | Unrestricted - IFB | W, G, Yates & Sons Construction Company | $7.49 | 10-22-2009 |
12-16-2010
|
WBV-23
| New Estelle Pump Station Fronting Protection & Modifications | HUBZONE - MATOC - Low Bid | Reeves Electrical Service (RES) | $8.00 | 04-19-2010 |
09-21-2011
|
WBV-24
| Segnette State Park Floodwall | Firm Fixed Price | David Boland, Inc. | $20.87 | 12-23-2009 |
|
WBV-30
| Westminster Pump Station Fronting Protection and Modifications | Firm Fixed Price - MATOC | Bucktown Contractors and Company | $13.69 | 09-18-2009 |
08-25-2011
|
WBV-33
| Old Estelle Pump Station Fronting Protection and Modifications | Firm Fixed Price - MATOC | Purnell Construction Co., Inc. | $22.57 | 09-16-2009 |
08-16-2011
|
WBV-37
| Ames/Mt. Kennedy P.S. Fronting Protection & Modifications. | Unrestricted - Best Value | Merrick Construction Co. | $22.50 | 06-23-2010 |
|
WBV-38.1
| Cousins Pump Station - Phase 1 | Unrestricted | C.R. Pittman | $18.78 | 09-16-2006 |
03-01-2008
|
WBV-38.2
| Cousins Pump Station and Discharge Channel Floodwalls - Phase 2 | HUBZONE - Low Bid | Creek Services, LLC | $11.17 | 10-26-2010 |
|
WBV-39b.1
| Cousins Discharge Channel Floodwalls - Phase 1 | Unrestricted | Hired Labor | $0.92 | 06-17-2007 |
08-29-2008
|
WBV-46.1
| Sector gate Complex - Phase 1 | Unrestricted | Boh Bros. | $35.69 | 12-16-2003 |
07-14-2008
|
WBV-46.1a
| Harvey Canal Floodgate (Sector Gate)- Permanent Pumps | | | $5-20M | Q-1-2013 |
|
WBV-46.1a1
| Harvey Canal Floodgate (Sector Gate) - Repair of Temporary Pumps | | | $0-5M | Q-4-2013 |
|
WBV-46.2
| Cousins Canal Walls - Destrehan Bridge to Sector Gate | HUBZONE - Low Bid | Aquaterra-CAYO | $3.50 | 05-18-2010 |
09-30-2011
|
WBV-53
| Priority Interim - Contract 2 | Hired Labor | Hired Labor | $0.63 | 09-19-2006 |
09-27-2007
|
WBV-54
| Priority Interim - Contract 3 | Hired Labor | Hired Labor | $0.40 | 09-19-2006 |
09-27-2007
|
WBV-55
| Priority Interim - Contract 4 | Hired Labor | Hired Labor | $1.00 | 09-19-2006 |
09-27-2007
|
WBV-56
| Priority Interim - Contract 5 | Hired Labor | Hired Labor | $0.41 | 09-19-2006 |
09-27-2007
|
WBV-58
| '07 Priority Interim - Contract 1: V-line floodwall | 8(a) - MATOC | Allen Wright Enterprises / Hamps Construction | $1.34 | 04-05-2007 |
02-04-2008
|
WBV-59
| '07 Priority Interim - Contract 2: Estelle PS to Lapalco | HUBZONE | Shavers-Whittle Construction | $2.08 | 07-13-2007 |
11-29-2007
|
WBV-60
| '07 Priority Interim - Contract 3: Weswego Floodwall | 8(a) | Southern Services & Equipment, Inc. | $7.69 | 12-07-2007 |
12-12-2008
|
WBV-61
| '07 Priority Interim - Contract 4: Segnette Park Floodwall | 8(a) | Creek Services, LLC | $7.17 | 11-20-2007 |
11-17-2008
|
WBV-62
| '07 Priority Interim - Contract 5: Old and New Estelle PS and PS #13 | 8(a) - MATOC | Allen Wright Enterprises / Hamps Construction | $2.69 | 04-27-2007 |
02-15-2008
|
WBV-63a
| '07 Priority Interim - Contract 6: Misc West Bank Pump Stations and Utility Crossings | 8(a) - MATOC | Progressive Construction | $0.99 | 04-26-2007 |
11-29-2007
|
WBV-63b
| '07 Priority Interm - Contract 7: Misc West Bank Pump Stations and Utility Crossings | 8(a) - MATOC | Bucktown Contractors and Company | $0.67 | 06-21-2007 |
10-04-2007
|
WBV-63b.1
| '07 Priority Interim - Contract 7b: Misc West Bank Pump Stations and Utility Crossings | 8(a) - MATOC | Allen Wright Enterprises / Hamps Construction | $3.50 | 07-03-2007 |
11-18-2008
|
WBV-70
| Western Tie-In Levees (Dewatering Cells) | HUBZONE | Phylway Construction | $10.90 | 09-25-2009 |
07-08-2010
|
WBV-71
| Western Tie-In Levees (North-South) | 8(a) - MATOC | DQSI | $5.33 | 09-25-2009 |
08-15-2012
|
WBV-72
| Western Tie-In Levees (East-West) | Unrestricted - Best Value | WRS Infrastructure & Environment, Inc.
WRS Infrastructure & Environment, Inc. | $30.22 | 03-22-2010 |
|
WBV-73
| Western Tie-In Highway Crossing | Unrestricted - Best Value | James Construction Group | $38.48 | 07-06-2010 |
|
WBV-74
| Western Tie-In Closure Structure | Unrestricted - Best Value | Tetra Tech EC Inc | $28.95 | 04-30-2010 |
06-18-2012
|
WBV-75
| Western Tie-In BNSF Railroad Crossing | Unrestricted - Best Value | Boh Bros. | $4.42 | 06-24-2011 |
04-10-2012
|
WBV-76
| Western Tie-In Hwy 90 Pump Station | HUBZONE - BV | Healtheon | $6.99 | 01-10-2011 |
|
WBV-77
| Western Tie-In UP Railroad and LA-18 Crossing | Unrestricted - Best Value | Cajun Constructors | $8.37 | 07-18-2011 |
|
WBV-80
| Algiers Canal Clearing and Grubbing | | | | 05-29-2012 |
|
WBV-81
| Chevron 30-inch pipeline relocation along Algiers Canal | | | $0-5M | Q-4-2012 |
|
WBV-82
| Gulf South 12-inch pipeline relocation along Algiers Canal | | | $0-5M | Q-4-2012 |
|
WBV-83
| S&WB pipeline relocations along Algiers Canal | | | $0-5M | Q-4-2012 |
|
WBV-84
| AT&T submarine lines relocation along Algiers Canal (Hired Labor) | | | | Q-4-2012 |
|
LPV -- JEFFERSON EAST BANK / ST.CHARLES (42 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
LPV-00.1
| Reach 1 Lakefront Levee - Phase 1 | 8(a) - MATOC | DQSI | $4.57 | 08-31-2006 |
05-14-2008
|
LPV-00.2
| Reach 1 Lakefront Levee - Phase 2 | 8(a) - MATOC | Phylway Construction | $3.16 | 08-18-2009 |
09-10-2010
|
LPV-01.1
| Reach 2 Lakefront Levee - Phase 1 & 2 | 8(a) - MATOC | Southern Services & Equipment, Inc. | $3.55 | 07-14-2009 |
01-05-2011
|
LPV-01.2
| Foreshore Protection A - Phase 2 | Unrestricted | B.I.S Services L.L.C | $22.57 | 09-17-2010 |
|
LPV-02.1
| Reach 3 Lakefront Levee (3rd Lift) - Phase 1 | 8(a) - MATOC | Creek Services, LLC | $5.52 | 10-06-2006 |
07-28-2008
|
LPV-02.2
| Reach 3 Lakefront Levee - Phase 2 | 8(a) - MATOC | Southern Services & Equipment, Inc. | $3.56 | 07-14-2009 |
09-10-2010
|
LPV-03.2A
| West Return Floodwall (Southern Segment) - Phase 2 | Unrestricted - Best Value | Cajun Constructors | $36.87 | 07-30-2010 |
04-30-2012
|
LPV-03.2B
| West Return Floodwall (Northern Segment) - Phase 2 | Unrestricted - Best Value | Odebrecht / Johnson Bros Joint Venture | $82.64 | 07-15-2010 |
05-22-2012
|
LPV-03a.1
| West Return Floodwall - Vintage-Phase 1 | 8(a) | Purnell Construction Co., Inc. | $1.68 | 05-13-2006 |
07-01-2006
|
LPV-03b.1
| West Return Floodwall, Airport I-wall - Phase 1 | | Purnell Construction Co., Inc. | | 09-16-2006 |
11-22-2006
|
LPV-03c.1
| West Return Floodwall- I-wall @ I-10 - Phase 1 | HZ-MATOC | Purnell Construction Co., Inc. | $0.09 | 04-24-2007 |
07-27-2007
|
LPV-03d.2
| Airport Runway10 Levee - Phase 2 | 8(a) - MATOC | Progressive Construction | $1.85 | 09-28-2010 |
12-30-2011
|
LPV-04.1
| Levee - Reach 1A, 1B & 2A - Phase 1 & 2 | HZ-MATOC | Clark Construction Enterprises, LLC | $12.93 | 06-28-2007 |
06-30-2010
|
LPV-04.2A
| Levee - Reach 1A from Cross Bayou to St. Rose and Gulf South Floodwall - Phase 2 | HUBZONE - MATOC - Low Bid | Bucktown Contractors and Company | $9.05 | 09-28-2009 |
06-01-2011
|
LPV-04.2B
| Levee - Reach 1B from I-310 to Walker Drainage Structure - Phase 2 | HUBZONE - MATOC - Low Bid | Creek Services, LLC | $7.97 | 12-17-2009 |
06-01-2011
|
LPV-05.1
| Levee - Reach 2B (2nd Lift) - Phase 1 | 8(a) - MATOC | Bucktown Contractors and Company | $4.66 | 09-14-2006 |
12-03-2007
|
LPV-05.2A
| Levee - Reach 2A Shell Pipeline to Goodhope and Shell Pipeline Floodwall Replacement - Phase 2 | HUBZONE - MATOC - Low Bid | Bucktown Contractors and Company | $6.64 | 12-17-2009 |
01-22-2011
|
LPV-05.2B
| Levee - Reach 2B - from Good Hope to Cross Bayou - Phase 2 | HZ-MATOC | Phylway Construction | $12.19 | 11-24-2009 |
12-23-2010
|
LPV-06a.2
| Bayou Trepagnier Complex Floodwall - Phase 2 | Firm Fixed Price - MATOC | Healtheon | $5.90 | 12-23-2009 |
01-14-2011
|
LPV-06b.2
| Shell Pipeline Floodwall - Phase 2 | 8(a) - MATOC | Bucktown Contractors and Company | $1.62 | 12-09-2010 |
05-16-2011
|
LPV-06c.2
| Goodhope Floodwall - Phase 2 | SDV-MATOC | Integrated Pro Services, LLC | $2.40 | 12-18-2009 |
09-17-2010
|
LPV-06e.1
| Floodwall Under I-310 - Phase 1 | 8(a) - MATOC | Purnell Construction Co., Inc. | $0.47 | 04-27-2007 |
11-09-2007
|
LPV-06e.2
| Floodwall Under I-310 - Phase 2 | Unrestricted - Best Value | Cajun Constructors | $11.18 | 04-23-2010 |
05-31-2011
|
LPV-06f.2
| Illinois Central Railroad Gate - Phase 2 | SDV-MATOC - Low Bid | Garner Services LLC | $4.29 | 06-24-2010 |
07-01-2011
|
LPV-07.1
| St. Charles Drainage Structure Tie-ins - Phase 1 | 8(a) - MATOC | Purnell Construction Co., Inc. | $0.85 | 09-26-2007 |
05-30-2008
|
LPV-07b.2
| Cross Bayou Drainage Structure - Phase 2 | Unrestricted - Low Bid | Lakeshore Engineering | $9.51 | 03-02-2010 |
06-07-2011
|
LPV-07b.2a
| Cross Bayou Access Bridge and Pile Load Test | 8(a) - MATOC | DQSI | $1.04 | 10-15-2009 |
03-22-2010
|
LPV-07c.2
| St. Rose Drainage Structure & Levee - Phase 2 | Unrestricted - Low Bid | Quality Enterprises USA | $6.42 | 12-30-2009 |
05-19-2011
|
LPV-07d.2
| Almedia / Walker Drainage Structures - Phase 2 | HZ-MATOC | Cycle Construction Co., LLC | $2.63 | 08-14-2009 |
09-09-2010
|
LPV-09.1
| PS#1 (Bonnabel) Floodwall Tie ins & Floodwall/Gate at Boat Launch - Phase 1 | HZ-MATOC | Cycle Construction Co., LLC | $0.29 | 05-16-2007 |
11-09-2007
|
LPV-09.2
| Pumping Stations #1 (Bonnabel), #2 (Suburban), #3 (Elmwood) and #4 (Duncan) Modifications, Fronting Protection, Positive Cutoff and Floodwall Tie-ins - Phase 2 | Unrestricted | Odebrecht Construction | $174.15 | 04-15-2010 |
|
LPV-09a.2
| Pumping Station #1 (Bonnabel) Breakwater - Phase 2 | Unrestricted | Boh Bros. | $9.15 | 05-07-2009 |
04-30-2010
|
LPV-10.1
| Pumping Station #2 (Suburban) Floodwall Tie-ins-Phase 1 | 8(a) - MATOC | Bucktown Contractors and Company | $1.19 | 09-22-2006 |
11-09-2007
|
LPV-11.1
| Pumping Station #3 (Elmwood) Floodwall tie-ins- Phase 1 | 8(a) | Progressive Construction | $1.39 | 09-22-2006 |
11-09-2007
|
LPV-12a.2
| Pumping Station #4 (Duncan) Breakwater - Phase 2 | Unrestricted | Boh Bros. | $7.99 | 08-21-2009 |
|
LPV-13.1
| Pump Station #4, Re-Curve I-Wall in Northwest Kenner, tie-ins at Causeway, Bonnabel Blvd., and Williams Blvd.- Phase 1 | HUBZONE | Bucktown Contractors and Company | $1.01 | 05-02-2007 |
10-15-2007
|
LPV-16.2
| Floodwall and Gate at Bonnabel Boat Launch - Phase 2 | HZ-MATOC | Cooley Constructors, Inc. | $3.02 | 12-15-2009 |
10-15-2010
|
LPV-17.2
| Bridge abutment and Floodwall Tie-ins at Causeway Bridge -Phase 2 | Unrestricted - Best Value | Boh Bros. | $43.19 | 08-24-2010 |
|
LPV-18.2
| Floodwall and Gate at Williams Blvd. Boat Launch-Phase 2 | HZ-MATOC | Phylway Construction | $3.33 | 09-10-2009 |
10-11-2010
|
LPV-19.2
| Reach 4 Lakefront Levee - Phase 2 | HZ-MATOC | Phylway Construction | $2.62 | 09-03-2009 |
09-08-2010
|
LPV-20.1
| Reach 5 Lakefront Levee - Phase 1 & 2 | 8(a) - MATOC | L&S/CKY JOINT VENTURE | $2.91 | 10-27-2008 |
10-13-2010
|
LPV-20.2
| Foreshore Protection B - Phase 2 | HZ-MATOC | Phylway Construction | $18.33 | 08-19-2010 |
|
LPV -- NEW ORLEANS METRO (26 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
LPV-101.02
| Lakefront Levee OEB - 17th St. Canal to Topaz St. | Unrestricted - Best Value | Tetra Tech EC Inc | $33.25 | 07-31-2009 |
05-14-2012
|
LPV-101.02A
| Advanced Measures | HUBZONE | Bucktown Contractors and Company | $0.38 | 09-18-2008 |
11-17-2008
|
LPV-102.01
| Lakefront Levee OEB - Topaz to Orleans Canal | HZ-MATOC | Merrick Construction Co. | $1.09 | 10-03-2007 |
05-03-2008
|
LPV-103.01
| Lakefront Levee OEB - Orleans Canal to London Ave | HZ-MATOC | Merrick Construction Co. | $5.20 | 12-03-2007 |
07-24-2008
|
LPV-103.1A1
| Lakefront Levee OEB - 17th St. Canal to London Av. Canal - Phase 1A | HZ-MATOC | Aquaterra-CAYO | $10.17 | 08-07-2009 |
11-08-2010
|
LPV-103.1A2
| Gate Structure Lakefront OEB - Orleans Canal to London Ave. | HUBZONE | Aquaterra-CAYO | $5.42 | 07-22-2010 |
08-01-2011
|
LPV-104.01
| Lakefront Levee OEB - London Avenue Canal to IHNC | HZ-MATOC | Bucktown Contractors and Company | $1.29 | 07-13-2007 |
05-01-2008
|
LPV-104.01a
| Lakefront Levee OEB - London Ave. Canal to IHNC - Phase 1A | HZ-MATOC | Cycle Construction Co., LLC | $14.07 | 10-21-2009 |
|
LPV-104.02
| Lakefront Levee OEB - London Ave Canal to IHNC | Unrestricted - Best Value | Quality Enterprises USA | $5.13 | 01-19-2010 |
|
LPV-104.02b
| Lakefront Levee OEB-London Avenue Canal to IHNC Seepage Cutoff | | | $0-5M | Q-4-2012 |
|
LPV-120.01
| Westbank IHNC - Almonaster to Lakefront Floodwall | HZ-MATOC | Cycle Construction Co., LLC | $4.61 | 02-27-2009 |
10-09-2009
|
LPV-201
| IHNC - GIWW to Almonaster. Completed by Hired Labor | Hired Labor | Hired Labor | $0.10 | 12-30-2006 |
05-31-2007
|
OEB-02
| Lake Pontchartrain - 17th St Canal Floodwall Repair, Phase II | | Boh Bros. | $14.82 | 02-15-2006 |
09-09-2007
|
OEB-04
| Lake Pontchartrain - London Ave Canal Breach at Mirabeau, Phase II | | Odebrecht Construction | $12.02 | 02-10-2006 |
11-26-2006
|
OEB-06
| Lake Pontchartrain - London Ave Canal Breach at Robert E Lee, Phase II | | James Construction Group | $9.78 | 02-24-2006 |
03-09-2007
|
OEB-09
| Lake Pontchartrain - Interim Closure Structure at 17th St. Canal | | Boh Bros. | $27.81 | 01-27-2006 |
04-29-2007
|
OEB-10
| Lake Pontchartrain - Interim Closure Structure at London Ave Canal | | M.R. Pittman Group, LLC. | $25.50 | 01-27-2006 |
07-15-2007
|
OEB-11
| Lake Pontchartrain - Interim Closure Structure at Orleans Ave Canal | | Gilbert Southern Group | $31.45 | 02-03-2006 |
07-03-2007
|
OEB-12
| Temporary Pump Supply 07 - 17th St. Canal | Supply | B&K Construction Co. LLC. | $6.28 | 12-22-2006 |
05-18-2006
|
OEB-13
| Temporary Pump Supply 07 - London Ave. Canal | Supply | Hill Brothers Construction Co. | $10.99 | 12-22-2006 |
01-31-2007
|
OEB-14
| Temporary Pump Installation 07 - 17th St. Canal | Firm Fixed Price | Weston Solutions | $84.96 | 01-31-2007 |
09-15-2007
|
OEB-15
| Temporary Pump Installation 07 - London Ave. Canal | Firm Fixed Price | Weston Solutions | $26.81 | 01-31-2007 |
09-15-2007
|
OEB-16
| ICS Coating System for Interim Control Structures | HUBZONE | Creek Services, LLC | $1.97 | 10-02-2008 |
03-04-2009
|
OEB-17
| Enhancement Work at 17th St, London, and Orleans Ave. Temporary Pump Stations | | Weston Solutions | $5.00 | 01-20-2008 |
03-16-2009
|
OEB-18
| Condominium Purchase and Demolition at 17th St Canal | 8(a) | Garner Services LLC | $0.50 | 09-14-2009 |
04-05-2010
|
SCADA-01
| SCADA system for 17th Street, London and Orleans Avenue Canals | Unrestricted | Prime Controls | $5.43 | 04-19-2006 |
06-15-2007
|
WBV -- BELLE CHASE (23 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
WBV-09a
| Hero Canal to Oakville - Levees | Unrestricted - Best Value | Kiewit Louisiana Company | $33.41 | 06-21-2010 |
11-01-2011
|
WBV-09b
| Hero Canal to Oakville - Structures | Unrestricted - Best Value | Conti Federal Services, Inc. | $26.47 | 05-14-2010 |
|
WBV-09c
| Hero Canal to Oakville - Highway Structures | Unrestricted - Best Value | Conti Federal Services, Inc. | $7.03 | 07-09-2010 |
|
WBV-10
| Belle Chasse Pump Station #1 (Plaquemines Pump Station) Fronting Protection and Modifications-Phase 1 | Firm Fixed Price | Boh Bros. | $31.71 | 09-24-2009 |
|
WBV-11
| Belle Chasse Pump Station #2 Fronting Protection and Modifications | Unrestricted - Best Value | F. Miller Construction, LLC, | $11.39 | 11-05-2010 |
|
WBV-12
| Hero Canal Reach 1, 2nd Enlgt | | Gulf Intracoastal Constructors | $5-20M | 04-29-2010 |
|
WBV-13
| S&WB PS #11 Fronting Protection and Modifications | Firm Fixed Price | Boh Bros. | $21.40 | 09-25-2009 |
06-26-2012
|
WBV-48.1
| Belle Chasse Hwy to Algiers Lock (East) - Phase 1 | Unrestricted | Circle Inc. | $4.99 | 08-08-2005 |
02-01-2007
|
WBV-48.2
| Belle Chasse Hwy to Algiers Lock (East) - Phase 2 | 8(a) - MATOC | Allen Wright Enterprises / Hamps Construction | $1.58 | 11-19-2010 |
03-31-2011
|
WBV-49.1
| Hero Levee to Belle Chasse Hwy (East) - Phase 1 | 8(a) - MATOC | Allen Wright Enterprises / Hamps Construction | $1.31 | 10-22-2010 |
06-03-2011
|
WBV-63c
| '07 Priority Interim - Contract 8: Misc West Bank Pump Stations and Utility Crossings | 8(a) - MATOC | Southern Services & Equipment, Inc. | $2.46 | 05-23-2007 |
12-17-2007
|
WBV-90
| GIWW - West Closure Complex | ECI | Gulf Intracoastal Constructors | $6.97 | 04-17-2009 |
|
WBV-MRL 01.1
| Oak Point to Oakville | HZ-MATOC | Cycle Construction Co., LLC | $15.55 | 04-02-2011 |
10-23-2011
|
WBV-MRL 01.2A
| Augusta to Oakville (A) | | | $20-50M | Q-4-2013 |
|
WBV-MRL 01.2B
| Augusta to Oakville (B) | | | $5-20M | Q-3-2013 |
|
WBV-MRL 02.2
| Oak Point to Augusta | | | $20-50M | Q-3-2013 |
|
WBV-MRL 03.1
| Belle Chasse to Oak Point | HZ-MATOC | Merrick Construction Co. | $10.22 | 04-02-2011 |
11-10-2011
|
WBV-MRL 03.2
| Belle Chasse to Oak Point | | | $20-50M | Q-3-2013 |
|
WBV-MRL 04.1
| English Turn Bend to Belle Chasse | HZ-MATOC | Shavers-Whittle Construction | $6.24 | 04-02-2011 |
01-18-2012
|
WBV-MRL 04.2
| English Turn Bend to Belle Chasse | | | $20-50M | Q-4-2013 |
|
WBV-MRL 05.2
| English Turn Bend | | | $5-20M | Q-3-2013 |
|
WBV-MRL 06.1
| Parish Line to English Turn Bend | 8(a) | Allen Wright Enterprises / Hamps Construction | $4.44 | 04-02-2011 |
10-26-2011
|
WBV-MRL 07.1
| West Crossover Pt. to Parish Line | 8(a) | Southern Services & Equipment, Inc. | $2.41 | 02-17-2011 |
03-05-2012
|
LPV -- NEW ORLEANS EAST (19 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
LPV-105.01
| Lakefront Airport Floodwalls - West | SDV | RCG Enterprises, Inc. | $12.49 | 04-09-2010 |
06-29-2011
|
LPV-105.02
| T-Wall Existing Alignment- Lakefront Airport - East | Unrestricted - Best Value | David Boland, Inc. | $19.47 | 05-13-2010 |
08-22-2012
|
LPV-105.03
| Interim Measures at Lakefront Airport Floodwall. Completed by Hired Labor | Hired Labor | Hired Labor | $0.75 | 07-18-2007 |
09-15-2007
|
LPV-106
| Replace Levee W/T - Citrus Lakefront Levee (West of Paris Road) | Unrestricted | L&A Contracting Co | $15.99 | 05-13-2010 |
06-29-2012
|
LPV-107
| Lincoln Beach Levee and Gate Replacement | HZ-MATOC | Shavers-Whittle Construction | $7.33 | 05-12-2010 |
07-28-2011
|
LPV-108
| Raise Levee - Paris Rd. to South Point | HUBZONE | Hamps Construction | $10.55 | 11-21-2008 |
05-26-2010
|
LPV-109.02a
| New Orleans East Levee - South Point to CSX RR (100 YR) | Unrestricted - IFB | Archer Western Contractors Inc. | $112.25 | 03-30-2010 |
08-31-2011
|
LPV-109.02A1
| Wick Drain Test Section | HZ-MATOC | Cycle Construction Co., LLC | $0.84 | 08-14-2009 |
11-06-2009
|
LPV-109.02A-BS
| New Orleans East Levee - South Point to CSX RR (100 YR) | Supply | Chapel Hill, LLC | $0-5M | 12-03-2009 |
|
LPV-109.02b
| I-10 Floodwall & Crossing | Unrestricted - Best Value | Barriere Bros | $16.43 | 04-08-2010 |
07-15-2011
|
LPV-110
| New Orleans East Levee - Modify CSX Railroad Gate | SDV | Garner Services LLC | $3.38 | 04-16-2010 |
07-27-2011
|
LPV-111.01
| New Orleans East Back Levee - CSX RR to Michoud Canal | ECI | Archer Western Alberici / Joint Venture | $3.12 | Q-- |
08-31-2011
|
LPV-111.01-BS
| New Orleans East Back Levee - CSX RR to Michoud Canal | Supply | Chapel Hill, LLC | $5-20M | 12-03-2009 |
|
LPV-113
| Citrus Back Levee - Michoud Canal to Michoud Slip to Auth. Elevation | HZ-MATOC | Purnell Construction Co., Inc. | $6.67 | 07-29-2009 |
09-15-2010
|
LPV-115
| Citrus Back Levee - Michoud Slip to IHNC Completed by Hired Labor | Hired Labor | Hired Labor | $1.10 | 12-21-2006 |
05-30-2007
|
LPV-116
| EB IHNC-GIWW/MRGO to Almonaste. Completed by Hired Labor | Hired Labor | Hired Labor | $1.50 | 12-30-2006 |
05-31-2007
|
LPV-117.01
| Eastbank IHNC - Almonaster to Lakefront Floodwall | 8(a) - MATOC | Progressive Construction | $2.19 | 05-06-2009 |
09-21-2009
|
LPV-117.02
| IHNC Reach II Emergency Interim Repair | HZ-MATOC | Shavers-Whittle Construction | $2.41 | 12-11-2009 |
04-17-2010
|
NOE-09
| Michoud Slip to Michoud Canal, Floodwall Scour Repair | | Boh Bros. | $8.66 | 02-03-2006 |
11-10-2006
|
NOV -- PLAQUEMINES (16 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
NOV-01
| East Bank Back Levee Reach C (Phoenix to Bohemia) | Unrestricted - Best Value | | $0-5M | Q-- |
|
NOV-02
| East Bank Back Levee Two Pump Structure Frontage Repair Reach C (Phoenix to Bohemia) | Unrestricted | | $5-20M | Q-1-2013 |
|
NOV-09
| West Bank MRL Levee Repair (St. Jude to City Price) | HZ-MATOC | | $5-20M | Q-- |
|
NOV-10
| West Bank MRL Levee Repair (City Price to Port Sulphur) including the fronting protection for Pt. Michel Pump Station | Unrestricted | | $0-5M | Q-- |
|
NOV-11
| West Bank MRL Levee Repair(Buras to Fort Jackson) | Unrestricted - Best Value | | $0-5M | Q-- |
|
NOV-12
| West Bank MRL Levee Repair (Fort Jackson to Venice) | Unrestricted - Best Value | | $0-5M | Q-- |
|
NOV-13
| Empire Floodgate | Unrestricted - Best Value | | $20-50M | Q-3-2013 |
|
NOV-14
| Empire Lock | Unrestricted - Best Value | | $20-50M | Q-4-2013 |
|
NOV-15
| I-Wall replacement at Childress and Venice | HUBZONE | | $0-5M | Q-- |
|
NOV-15.01
| West Bank Floodwall Interim Measure Repair Duvic and Grand Liard Pump Stations Constructed by Hired Labor | Hired Labor | Hired Labor | $3.88 | 08-08-2007 |
11-17-2007
|
NOV-16
| West Bank MRL Levee Enlargement Buras Area | 8(a) | | $20-50M | Q-- |
|
P-13
| Plaquemines - Landside Levee Enlargement Port Sulphur Area | Firm Fixed Price | Barriere Bros | $9.37 | 02-10-2006 |
07-01-2007
|
P-14
| Plaquemines - Landside Levee Enlargement Empire/Buras Area | Firm Fixed Price | Shaw Environmental | $18.25 | 01-26-2006 |
08-12-2007
|
P-15.02
| Plaquemines - Empire Floodgate Repair | Firm Fixed Price | M.R. Pittman Group, LLC. | $4.62 | 01-20-2006 |
04-17-2007
|
P-17
| Plaquemines - Landside Levee Enlargement Buras Area | Firm Fixed Price | Ronald Adams | $8.99 | 02-03-2006 |
03-15-2007
|
P-24
| Plaquemines - Landside Levee Enlargement Port Sulphur Area | Firm Fixed Price | Shaw Environmental | $28.05 | 01-30-2006 |
07-01-2007
|
WBV -- GRETNA / ALGIERS (14 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
WBV-01
| Contract 1, Sectorgate to Boomtown Floodwall | Unrestricted | Cajun Constructors | $132.13 | 02-01-2008 |
05-11-2010
|
WBV-02a
| Contract 2a, Boomtown Floodwalls | Unrestricted | Cajun Constructors | $48.45 | 07-17-2008 |
06-17-2010
|
WBV-02b
| Contract 2b, Boomtown to Hero Pump Station Floodwalls | Unrestricted | Cajun Constructors | $56.10 | 03-26-2007 |
08-28-2008
|
WBV-03a
| Contract 3a, Hero PS to Algiers Canal Floodwall | Unrestricted | Boh Bros. | $62.28 | 07-11-2008 |
06-08-2011
|
WBV-03b
| Contract 3b, Hero PS to Algiers Canal Floodwall | Unrestricted - Best Value | Shavers-Whittle Construction | $32.01 | 12-08-2008 |
07-15-2010
|
WBV-04.2
| Belle Chasse Hwy to Hero Cutoff-Reach1-Phase 2 | 8(a) - MATOC | DQSI | $4.21 | 09-30-2010 |
01-12-2012
|
WBV-05.2
| Belle Chasse Hwy to Hero Cutoff-Reach 2 - Phase 2 | 8(a) - MATOC | DQSI | $3.94 | 09-30-2010 |
12-09-2011
|
WBV-06.2
| Belle Chasse Hwy to Hero Cutoff-Reach 3 & 4-Phase 2 | Unrestricted - Best Value | Conti Federal Services, Inc. | $21.73 | 12-14-2010 |
|
WBV-06a.1
| Belle Chasse Hwy to Hero Cutoff (West) | HZ-MATOC | Merrick Construction Co. | $9.62 | 01-04-2008 |
01-26-2010
|
WBV-07
| Planters Pump Station Fronting Protection and Modifications | Firm Fixed Price | Kiewit Louisiana Company | $33.07 | 09-28-2009 |
12-21-2011
|
WBV-08
| Sewerage & Water Board Pump Station #13 Fronting Protection and Modifications | Firm Fixed Price | Boh Bros. | $29.98 | 09-24-2009 |
|
WBV-44
| Whitney Barataria Pump Station Floodwall Modifications | HUBZONE - MATOC - Low Bid | Cycle Construction Co., LLC | $7.35 | 08-17-2010 |
10-06-2011
|
WBV-47.1
| Algiers Lock to Belle Chasse Hwy (West) - Phase 1 | 8(a) - MATOC | Allen Wright Enterprises / Hamps Construction | $5.84 | 11-18-2010 |
08-16-2011
|
WBV-52
| Priority Interim - Contract 1 | Hired Labor | Hired Labor | $0.17 | 09-19-2006 |
09-27-2007
|
SELA -- JEFFERSON EAST BANK / ST.CHARLES (13 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
SELA-01
| Soniat Canal - Veterans to Canal #3 & gap below Veterans | Unrestricted - Best Value | B&K Construction Co. LLC. | $23.99 | 11-16-2006 |
11-03-2009
|
SELA-01A
| Soniat Canal - West Napoleon to Lynette | HUBZONE - MATOC - Low Bid | Bucktown Contractors and Company | $10.73 | 09-15-2009 |
10-21-2011
|
SELA-04
| Elmwood Canal Bridge @ Kawanee | 8(a) - MATOC | Allen Wright Enterprises / Hamps Construction | $5.84 | 01-30-2007 |
12-31-2008
|
SELA-04A
| Elmwood Canal Bridge @ W. Esplanade | HZ-MATOC | Shavers-Whittle Construction | $13.08 | 02-26-2007 |
10-19-2010
|
SELA-07
| Pump to the River Disc. Tubes (750' Segment) | SDV | Babcock Construction | $8.45 | 08-14-2007 |
11-21-2008
|
SELA-07A
| Pump to the River North Discharge Tubes | Unrestricted - Low Bid | | $20-50M | Q-1-2013 |
|
SELA-07B
| Pump to the River South Discharge Tubes | Unrestricted - Low Bid | | $50-100M | Q-2-2013 |
|
SELA-07C
| Pump to the River Discharge Structure | Unrestricted - Best Value | | $20-50M | Q-1-2013 |
|
SELA-08
| Soniat Canal - Lynette to Lester | Best Value - Set Aside | Bucktown Contractors and Company | $26.74 | 04-18-2011 |
|
SELA-08A
| Soniat Canal - Lester to W. Metairie | Unrestricted - Low Bid | | $5-20M | Q-2-2013 |
|
SELA-09
| Pump to the River Pump Station | Unrestricted - Low Bid | M.R. Pittman Group, LLC. | $29.39 | 09-21-2011 |
|
SELA-09A
| Pump to the River Intake Basin | SDV-MATOC - Low Bid | | $5-20M | Q-2-2013 |
|
SELA-OG-1
| Soniat Canal - West Napoleon to Veterans | Firm Fixed Price | C.R. Pittman | $14.43 | 07-25-2000 |
09-30-2006
|
NFPS -- NEW ORLEANS METRO (10 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
OPS-01
| Orleans Pump Stations - Roofing Repairs | 8(a) | Crown Roofing | $1.89 | 08-22-2006 |
04-21-2007
|
OPS-03
| Orleans Pump Stations - Motors Rewinds Pump Stations #1 and #6 | Unrestricted | Evans Enterprises | $3.31 | 05-15-2006 |
08-29-2006
|
OPS-05
| Orleans Pump Stations - Horizontal Pump Bearings | Unrestricted | IPS | $0.96 | 09-20-2006 |
04-26-2007
|
OPS-06B
| Orleans Pump Stations - Bearings - Pump Stations #4, #6, #10, #12, #19 | 8(a) | IPS | $2.96 | 12-01-2006 |
03-31-2008
|
OPS-07A
| Orleans Pump Stations - Frequency Changers Carrollton Building | 8(a) | Reeves Electrical Service (RES) | $3.34 | 11-22-2006 |
08-11-2007
|
OPS-07B
| Orleans Pump Stations - Frequency Changers Station 17 (D) | 8(a) | Reeves Electrical Service (RES) | $3.42 | 11-22-2006 |
04-01-2008
|
OPS-08
| Orleans Pump Stations - Electrical - Mechanical Repairs | 8(a) | Healtheon | $3.25 | 06-19-2007 |
01-11-2008
|
OPS-09
| Orleans Pump Stations - Building and Structural Repairs | 8(a) | Creek Services, LLC | $1.55 | 10-12-2007 |
07-03-2008
|
OPS-10
| Orleans Pump Stations - Discharge Line | 8(a) | Garner Services LLC | $1.85 | 08-01-2007 |
06-09-2008
|
SBPS-03
| Saint Bernard Pump Stations - Generators for Pump Station #1 and #4 | 8(a) | Reeves Electrical Service (RES) | $0.07 | 07-27-2006 |
09-05-2006
|
SELA -- NEW ORLEANS METRO (10 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
SELA-19
| Florida Avenue - Phase 1 | Unrestricted - Best Value | B&K Construction Co. LLC. | $49.17 | 01-29-2010 |
|
SELA-20
| Florida Avenue - Phase 2 and Phase 3 | Unrestricted - Best Value | | $50-100M | Q-1-2014 |
|
SELA-21
| Uptown Jeff Avenue - Phase 1 - Claiborne to Dryades | Unrestricted - Best Value | | $20-50M | Q-3-2013 |
|
SELA-22
| Uptown Jeff Avenue - Phase 2 - Dryades to Constance | Unrestricted - Best Value | | $20-50M | Q-1-2013 |
|
SELA-23
| Uptown Napoleon Avenue - Phase 2 - Claiborne to Carondelet | Unrestricted - Best Value | Boh Bros. | $54.16 | 09-14-2011 |
|
SELA-23A
| Uptown Napoleon Avenue - Phase 3 - Carondelet to Constance | Unrestricted - Best Value | | $20-50M | Q-3-2013 |
|
SELA-24A
| Uptown South Claiborne - Phase 1 - Monticello to Leonidas | Unrestricted - Best Value | Cajun Constructors | $25.97 | 09-30-2011 |
|
SELA-24B
| Uptown South Claiborne - Phase 2 - Leonidas to Lowerline | Unrestricted - Best Value | B&K Construction Co. LLC. | $27.82 | 06-20-2012 |
|
SELA-26
| Florida Avenue - Phase 4 | Unrestricted - Best Value | | $50-100M | Q-1-2014 |
|
SELA-27
| Uptown Louisiana Avenue - Claiborne to Constance | Unrestricted - Best Value | | $50-100M | Q-1-2014 |
|
LPV -- ST BERNARD (8 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
LPV-142
| Interim Measure - South Side of GIWW | | Hired Labor | $1.15 | 06-10-2007 |
04-15-2008
|
LPV-144
| Chalmette Loop Levee - Bayou Dupre Floodgate | Unrestricted - IFB | Tetra Tech EC Inc | $36.37 | 01-22-2010 |
02-23-2012
|
LPV-145
| Chalmette Loop Levee - Bayou Bienvenue to Bayou Dupre. | ECI | Chalmette Levee Constructors | $0.74 | 07-14-2009 |
07-26-2011
|
LPV-146
| Chalmette Loop Levee - Bayou Dupre to Hwy 46 Floodwall | ECI | St. Bernard Levee Partners LLC | $0.54 | 08-06-2009 |
05-24-2011
|
LPV-147
| Chalmette Loop Levee - Highway 46 Floodgates | SDV-MATOC | Integrated Pro Services, LLC | $5.32 | 03-19-2010 |
04-05-2011
|
LPV-148.01
| Chalmette Loop Levee - Hwy 46 to River (Verret to Caernarvon) - raise to authorized grade | Unrestricted - Best Value | Odebrecht Construction | $41.82 | 10-31-2007 |
05-14-2009
|
LPV-148.02
| Chalmette Loop Levee - Hwy 46 to River (Verret to Caernarvon) | ECI | Cajun Constructors | $0.27 | 02-23-2010 |
12-13-2011
|
LPV-149
| Caernarvon Canal at LA 39/Railroad Replace Floodgates | Unrestricted - IFB | Conti Federal Services, Inc. | $46.44 | 06-15-2010 |
12-20-2011
|
SP -- HARVEY / WESTWEGO (8 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
JSP-02
| Jefferson Storm Proofing - Mount Kennedy Generator | HZ-MATOC | Cycle Construction Co., LLC | $2.96 | 10-14-2009 |
04-06-2011
|
JSP-03
| Jefferson Storm Proofing - Five Safe Rooms | HZ-MATOC | Cycle Construction Co., LLC | $17.16 | 12-18-2007 |
06-25-2008
|
JSP-04
| Jefferson Storm Proofing - Seven Pump Station Automation | HZ-MATOC | Healtheon | $9.74 | 09-22-2008 |
04-09-2009
|
JSP-05
| Jefferson Storm Proofing - Storm Proofing Pump Stations | SDV | Benetech, LLC. | $17.30 | 12-24-2009 |
04-19-2012
|
JSP-08
| Jefferson Storm Proofing - Storm Proofing Two Pump Stations | 8(a) | DQSI | $7.21 | 07-23-2010 |
|
JSP-09
| Jefferson Storm Proofing - Storm Proofing Three Pump Stations | HZ-MATOC | Healtheon | $5.78 | 10-19-2010 |
|
JSP-13
| Jefferson Storm Proofing - DPS Estelle No 1 Storm-Proofing | SDV-MATOC | Garner Services LLC | $3.23 | 04-04-2011 |
04-20-2012
|
JSP-14
| Jefferson Storm Proofing - DPS Harvey Storm-Proofing | HZ-MATOC | Allen Wright Enterprises / Hamps Construction | $2.20 | 03-04-2011 |
01-10-2012
|
SELA -- HARVEY / WESTWEGO (7 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
SELA-02
| Westwego Pump Station Diesel Engine | 8(a) - MATOC | Reeves Electrical Service (RES) | $1.49 | 12-18-2006 |
04-10-2009
|
SELA-03
| Westminster/Lincolnshire Pump Station Backup Generator | 8(a) - MATOC | Allen Wright Enterprises / Hamps Construction | $8.85 | 12-29-2006 |
09-23-2008
|
SELA-05
| Grand Cross Canal @ Lapalco | HZ-MATOC | Cycle Construction Co., LLC | $8.66 | 06-18-2007 |
07-13-2009
|
SELA-10
| Mayronne Canal | 8(a) - MATOC - Low Bid | Fleming Construction Company, LLC. | $3.35 | 08-29-2011 |
|
SELA-11
| Cousins Canal - Phase 2 | 8(a) - MATOC | Bucktown Contractors and Company | $9.00 | 09-27-2007 |
10-07-2009
|
SELA-12
| Two Mile Canal Phase 2 | Best Value - Set Aside | Bucktown Contractors and Company | $19.81 | 03-07-2011 |
|
SELA-13
| Justice and Oil Company Canals | HUBZONE - MATOC - Low Bid | Merrick Construction Co. | $13.64 | 06-21-2011 |
|
SP -- NEW ORLEANS METRO (6 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
OSP-01
| Orleans Storm Proofing - 15 MW 60 HZ Generator | SDV | DV & Associates | $31.19 | 11-18-2009 |
|
OSP-04
| Orleans Storm Proofing - CWT & PP - Old River - New River Storm Proofing | 8(a) | Keiland Construction | $16.86 | 06-28-2010 |
06-06-2011
|
OSP-04A
| Orleans Storm Proofing - Old River - New River Intake Structures Storm Proofing | | Healtheon | $4.51 | 03-10-2011 |
|
OSP-06
| Orleans Storm Proofing - Storm Proofing Three Pump Stations | SDV | Benetech, LLC. | $10.96 | 07-14-2010 |
|
OSP-07
| Orleans Storm Proofing - Storm Proofing One Pump Station | HZ-MATOC | Shavers-Whittle Construction | $16.04 | 07-29-2010 |
04-25-2012
|
OSP-08
| Orleans Storm Proofing - Storm-Proof at DPS No. 1, 2, 4, 12, 19, & I-10 | 8(a) | Benetech, LLC. | $8.35 | 12-02-2010 |
|
LGM -- LAROSE TO GOLDEN MEADOWS (5 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
LGM-000
| Section D; South Berm and Mitigation Levee | 8(a) - MATOC | Purnell Construction Co., Inc. | $1.73 | 11-21-2006 |
09-27-2007
|
LGM-001
| C North 3rd Lift-Phase 1, Hwy 1 to Larose Floodgate | 8(a) - MATOC | | $0-5M | Q-4-2013 |
|
LGM-001A
| Section C North 3rd Lift-Phase 2, Hwy 1 to Larose Floodgate | 8(a) - MATOC | Hired Labor | $0-5M | 07-17-2009 |
11-13-2009
|
LGM-002
| D North 3rd Lift | 8(a) - MATOC | DQSI | $2.88 | 11-21-2006 |
02-08-2008
|
LGM-028A
| S. L. Crawfish Farm Pump Station Discharge | HZ-MATOC | Reeves Electrical Service (RES) | $4.42 | 10-04-2009 |
04-12-2010
|
NFPS -- HARVEY / WESTWEGO (5 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
JPS-03A
| Jefferson Pump Stations - Roofing Siding Repairs | 8(a) | Crown Roofing | $0.10 | 07-17-2006 |
09-04-2006
|
JPS-03B
| Jefferson Pump Stations - Roofing Siding Repairs | 8(a) | Crown Roofing | $0.07 | 07-17-2006 |
09-04-2006
|
JPS-03C
| Jefferson Pump Stations - Roofing Siding Repairs | 8(a) | Crown Roofing | $0.10 | 07-17-2006 |
09-04-2006
|
JPS-05
| Jefferson Pump Stations - Misc Repairs #2 | 8(a) | Crown Roofing | $0.08 | 10-30-2006 |
02-27-2007
|
JPS-06
| Jefferson Pump Stations - Misc Repairs #3 | 8(a) | Crown Roofing | $0.07 | 11-02-2006 |
12-08-2006
|
SELA -- GRETNA / ALGIERS (5 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
SELA-06
| Gardere Canal - Phase 2 | Unrestricted - Best Value | B&K Construction Co. LLC. | $31.35 | 01-12-2007 |
06-24-2010
|
SELA-14
| Industry Canal | HUBZONE - MATOC - Low Bid | Fleming Construction Company, LLC. | $18.64 | 07-05-2012 |
|
SELA-15
| Trapp Canal | Unrestricted - Low Bid | Hamps Construction | $14.68 | 09-04-2012 |
|
SELA-16
| Gardere Canal Phase III and Murphy Canal Phase I, Jefferson Parish (West Bank) | HUBZONE - MATOC - Low Bid | Conquistidor Dorado JV | $22.36 | 09-26-2012 |
|
SELA-16A
| Murphy Canal - South | SDV-MATOC - Low Bid | | $5-20M | Q-3-2013 |
|
SP -- JEFFERSON EAST BANK / ST.CHARLES (5 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
JSP-01
| Jefferson Storm Proofing - Climber Screens | HZ-MATOC | Cycle Construction Co., LLC | $8.94 | 05-14-2009 |
05-14-2010
|
JSP-06
| Jefferson Storm Proofing - Storm Proofing Two Pump Stations | 8(a) | Healtheon | $7.68 | 01-27-2010 |
02-17-2012
|
JSP-07
| Jefferson Storm Proofing - Storm Proofing Two Pump Stations | SDV | Benetech, LLC. | $7.44 | 11-24-2009 |
02-14-2011
|
JSP-10
| Jefferson Storm Proofing - Storm Proofing Two Pump Stations | 8(a) | Reeves Electrical Service (RES) | $2.42 | 05-14-2010 |
07-08-2011
|
JSP-11
| Jefferson Storm Proofing - Storm Proofing One Pump Station | 8(a) | Healtheon | $1.91 | 04-28-2010 |
07-12-2011
|
NFPS -- ST BERNARD (5 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
OPS-02
| Orleans Pump Stations - Motor Rewinds Pump Stations #2, #3, #5 and #7 | Unrestricted | Bollinger Quick Repair | $4.07 | 05-15-2006 |
03-09-2007
|
SBPS-01
| Saint Bernard Pump Stations - Design Build Contract Rebuild Pump Station #2, #3, and #5 | Firm Fixed Price | CDM | $17.99 | 05-17-2007 |
12-12-2008
|
SBPS-02
| Saint Bernard Pump Stations - Electric/Mechanical and Misc Repairs | 8(a) | Healtheon | $0.79 | 01-25-2007 |
09-20-2008
|
SBPS-04
| Saint Bernard Pump Stations - Gate Package | 8(a) | Southern Services & Equipment, Inc. | $0.48 | 09-28-2006 |
02-16-2007
|
SBPS-05
| Saint Bernard Pump Stations - Roofing Repairs | 8(a) | Crown Roofing | $0.08 | 04-14-2006 |
06-30-2006
|
NFPS -- PLAQUEMINES (4 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
PPS-01A
| Plaquemines Pump Stations - Hayes, Epalh, Bellevue, Scarsdale | HUBZONE | Healtheon | $8.00 | 06-19-2008 |
12-14-2009
|
PPS-01B
| Plaquemines Pump Stations - Gainard Woods 2 and Sunrise 2 | 8(a) | Healtheon | $2.65 | 08-26-2008 |
09-18-2009
|
PPS-01C
| Plaquemines Pump Stations - Diamond and Wpalh | SDV | DV & Associates | $1.99 | 12-17-2008 |
07-22-2009
|
PPS-02
| Plaquemines Pump Stations - Electric Services | 8(a) | Reeves Electrical Service (RES) | $0.70 | 08-25-2006 |
01-02-2007
|
GI -- GRAND ISLE (3 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
GI-01
| Grand Isle Federal Levee | HUBZONE | Bertucci Industrial Services, LLC | $12.50 | 04-08-2008 |
11-25-2008
|
GI-01A
| Grand Isle Federal Levee (Post Gustav) | Unrestricted | Weeks Marine, Inc. | $25.73 | 04-01-2009 |
02-17-2010
|
GI-01B
| Grand Isle Federal Levee | HZ-MATOC | Healtheon | $0.67 | 12-16-2009 |
07-28-2010
|
NFPS -- JEFFERSON EAST BANK / ST.CHARLES (3 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
JPS-01
| Jefferson Pump Stations - Roofing Repairs Bonnabel | 8(a) | BENCO | $0.10 | 05-10-2006 |
07-31-2006
|
JPS-02
| Jefferson Pump Stations - Roofing Repairs Duncan | 8(a) | BENCO | $0.10 | 05-11-2006 |
07-31-2006
|
JPS-04
| Jefferson Pump Stations - Misc Repairs #1 | 8(a) | Healtheon | $0.06 | 11-08-2006 |
03-01-2007
|
IHNC -- NEW ORLEANS EAST (2 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
IHNC-01
| IHNC Flood Protection - Seabrook | ECI | Alberici Constructors, Inc. | $0.50 | 10-30-2009 |
06-30-2012
|
IHNC-02
| IHNC Flood Protection - GIWW/MRGO | Design Build | Shaw Environmental | $695.49 | 04-03-2008 |
|
NFPS -- NEW ORLEANS EAST (2 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
OPS-06A
| Orleans Pump Stations - Bearings - Pump Stations #1, #14, #15, #16, #I-10 | 8(a) | IPS | $3.22 | 12-01-2006 |
11-04-2009
|
OPS-11
| Orleans Pump Stations - Elaine Pump Station Repair | 8(a) | Healtheon | $3.20 | 08-13-2009 |
10-14-2010
|
SELA -- NEW ORLEANS EAST (2 contracts)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
SELA-18
| Dwyer Road PS Intake Culvert | Unrestricted - Best Value | Hill Brothers Construction Co. | $58.83 | 08-27-2008 |
|
SELA-OG-3
| Dwyer Road Pump Station Improvements | Unrestricted - Best Value | C.R. Pittman | $13.62 | 09-20-2000 |
11-15-2010
|
SP -- ST BERNARD (1 contract)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
OSP-05
| Orleans Storm Proofing - Pump Station No. 5 - Two Pumps with Generator | HUBZONE | Cycle Construction Co., LLC | $24.84 | 04-06-2011 |
|
SP -- GRETNA / ALGIERS (1 contract)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
OSP-12/13
| DPS 12/13 Generator and Storm Proofing | 8(a) | Southern Services & Equipment, Inc. | $16.20 | 09-27-2010 |
03-12-2012
|
NF -- PLAQUEMINES (1 contract)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
NF-02
| Braithwaite to Scarsdale Non-Federal | HUBZONE | Ceres Caribe | $14.12 | 06-15-2006 |
10-01-2007
|
NFPS -- BELLE CHASE (1 contract)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
PPS-01D
| Plaquemines Pump Stations - Belle Chasse 1+2, Ollie, Grand Deliard, Duvic | 8(a) | Healtheon | $1.65 | 12-19-2008 |
09-18-2009
|
PCCP -- NEW ORLEANS METRO (1 contract)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
PCCP-01
| Outfall Canal Closures | Design Build | | $500M-1B | Q-4-2012 |
|
WBV -- PLAQUEMINES (1 contract)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
WBV-06a.2
| Belle Chasse Hwy to Hero Cutoff (West) - Phase 2 | 8(a) - MATOC | DQSI | $2.91 | 09-30-2010 |
06-17-2011
|
-- NEW ORLEANS METRO (1 contract)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
PSG-01
| Pump Station # 6 Emergency Generator and Pump Station # 6 Fuel Tanks | 8(a) | Reeves Electrical Service (RES) | $2.59 | 10-31-2006 |
05-30-2007
|
NF -- GRAND ISLE (1 contract)
= Construction Complete
= Under Construction
Contract ID | Contract | Contracting Package | Prime Contractor | Contract Estimate (in millions $) | Contract Awards (quarters based on calendar year) | Substantial Construction Completed |
NF-01
| Grand Isle Non Federal | 8(a) | | $5-20M | Q-4-2013 |
|