Animas La-Plata Project Schedule | |
June 2002 - Nov. 2002 | Ridges Basin Inlet Conduit, Stage 1 |
Nov. 2002 - 2009 | Ridges Basin Dam |
April 2003 - April 2009 | Durango Pumping Plant |
2008 - 2011 | Navajo Nation Municipal Pipeline |
2007 - 2009 | Ridges Basin Inlet Conduit, Stage 2 |
2008 - 2010 | Relocation of CR 211 |
2009 - 2011 | Reservoir Filling |
** This schedule and approximate dates are subject to change and refinement