Ft. Bliss Projects (February 2011)

McGregor Shoppette

4,000 sq ft Prefab building at training ranges, in solicitation process.
Construction start May 2011, Open Facility February 2012

Cassidy Subway

Add Subway to Cassidy Shoppette; upgrade Shoppette.
Start Construction May 2011, Open facility September 2011

Purple Heart Mini Mall #4

9,000 Sq ft Mini Mall, 5,000 sq ft Shoppette, Burger King, Subway, Gas, Diesel fuel, Barber Shop.
Start Construction December 2010, Open Facility June 2011

Community Troop Mall #2

27,000 sq ft  Mini Mall  with 12,000 sq ft troop store, 4 NBFF: Popey's, Charley’s Grilled Subs, Starbucks, Taco Bell, Barber, Beauty shop, Laundry Dry Cleaners and Alterations.
Start Construction Oct 2010, Open Facility September 2011

Biggs Shoppette #5

5,000 sq ft Shoppette, upgrade gas, add 2 dispensers (total 4 dispensers/8pumps) add Arby’s NBFF.
Projected start construction June 2011, Open facility April 2012