Application Information:
- License Renewal Application
- Applicant's Environmental Report
License Renewal Review Schedule*
*These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.
Milestones | Schedule Date | Actual Date |
---|---|---|
Receive license renewal application (LRA) | 11/01/11 | 11/01/11 |
Publish Federal Register Notice (FRN) – LRA availability | 11/2011 | 11/17/11 |
Publish FRN – acceptance/rejection and opportunity for hearing | 12/2011 | 12/27/11 |
Publish FRN – environmental scoping meeting | 12/2011 | 12/29/11 |
Audit – Scoping & Screening Methodology | 01/09/12 | 01/09/12 |
Audit – Aging Management Programs | 01/23/12 | 01/23/12 |
Public Meeting – License Renewal Overview and Environmental Scoping meeting | 01/31/12 | 01/31/12 |
Deadline for filing hearing requests and petitions for intervention | 02/2012 | 02/27/12 |
Environmental scoping period ends | 02/2012 | 02/27/12 |
Audit – Environmental | 03/27/12- 03/29/12 |
03/27/12- 03/29/12 |
Inspection – Regional | 08/2012 | 08/06/12 |
Issue safety evaluation report (SER) with open items | 01/2013 | |
Issue draft supplemental environmental impact statement (SEIS) | 02/2013 | |
Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting | 03/2013 | |
Publish FRN – draft SEIS available for comments | 03/2012 | |
Public Meeting – draft SEIS meeting | 04/2013 | |
End of draft SEIS comment period | 05/2013 | |
Issue final SER | 07/2013 | |
Issue final SEIS | 08/2013 | |
ACRS full committee meeting | 09/2013 | |
U.S. Environmental Protection Agency FRN Published – availability of final SEIS | 09/2013 | |
Decision – Director, NRR (no hearing) | TBD | |
Commission decision (if hearing is granted) | TBD |
Note: The Grand Gulf Nuclear Station review schedule was revised as described in the letter below:
Public Involvement
The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.
Public Meetings Related to Environmental Review
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
Date | Description |
---|---|
01/31/12 | Meeting to discuss the license renewal process and environmental scoping for Grand Gulf Nuclear Station. |
Project Managers for Grand Gulf
Grand Gulf Nuclear Station, Unit 1 PMs | |
---|---|
License Renewal (Safety) | Nathaniel Ferrer |
License Renewal (Environmental) | David Drucker |
Lead Power Plant | Alan Wang |