Application Information:
License Renewal Review Schedule*:
* These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.
Milestones | Schedule Date | Actual Date |
---|---|---|
Receive license renewal application (LRA) | 08/30/10 | 08/30/10 |
Publish Federal Register Notice (FRN) - LRA receipt and availability | 09/17/10 | 09/20/10 |
Publish FRN - LRA acceptability and opportunity for hearing | 10/20/10 | 10/25/10 |
Publish FRN – intent to conduct environmental scoping | 10/20/10 | 10/28/10 |
Public Meeting - license renewal process and environmental scoping | 11/04/10 | 11/04/10 |
Deadline for filing hearing requests and petitions for intervention | 12/24/10 | 12/24/10 |
Environmental scoping periods ends | 12/27/10 | 12/27/10 |
Audit - scoping and screening methodology | 01/24/11 | 01/24/11 |
Audit - aging management programs (AMPs) | 02/14/11 | 02/14/11 |
Audit - environmental | 03/07/11 | 03/07/11 |
Inspection - scoping, screening, and AMPs | 04/2011 | 04/25/11 |
Environmental Requests for Additional Information (RAIs) - Issued | 04/08/11 | 02/23/11 |
Safety RAIs - Issued | 04/29/11 | 04/29/11 |
Environmental RAIs - Response Received | 05/13/11 | 03/23/11 |
Safety RAI - Responses Received | 05/30/11 | 05/30/11 |
Issue draft supplemental environmental impact statement (SEIS) | TBD | |
Issue safety evaluation report (SER) with open item(s) | 7/2012 | 07/31/2012 |
Public Meeting - draft SEIS | TBD | |
ACRS subcommittee meeting on SER with open item(s) | 09/19/12 | |
End of comment period for the draft SEIS | TBD | |
Issue final SEIS | TBD | |
Issue SER | 10/2012 | |
ACRS full committee meeting on SER | 12/2012 | |
Decision – Director, Office of Nuclear Reactor Regulation | TBD | |
Commission decision (hearing pending) | TBD |
Note: The Davis-Besse review schedule was revised as described in the letter below:
- Revised Schedule Letter (March 9, 2012)
- Revised Schedule Letter (January 31, 2012)
- Revised Schedule Letter (December 27, 2011)
- Revised Schedule Letter (October 31, 2011)
- Original Schedule Letter (December 28, 2010)
Safety Evaluation Report
The NRC staff reviewed the Davis-Besse Nuclear Power Station license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared this report to document its preliminary findings. The document was issued on July 31, 2012, as "Safety Evaluation Report with Open Items Related to the License Renewal of Davis-Besse Nuclear Power Station."
Project Managers for Davis-Besse
Davis-Besse Nuclear Power Station, Unit 1 PMs | |
---|---|
License Renewal (Safety) | Samuel Cuadrado de Jesús |
License Renewal (Environmental) | Paula Cooper |