ANNOTATION: A facility development process plan is provided. Process phases are noted along the top of this flowchart: project recognition, needs assessment, go—no go, design, bidding, go—no go, construction, occupancy, and post occupancy. Elements occupying different places in the phases are listed on the side—tasks and then process tracks of non facility alternatives, transition, site, capital and operational funding, project delivery method, outcomes, professional services acquisition, and building support for the project.