Resolution 11-01 Approved change in work product due date for deliverable 4.6, Data Gap Report to August 23, 2011

Resolution 11-02 

 

Requests DOE to proceed with contracting PNNL for Visual Sample Plan Training

Resolution 11-03

 

Requests DOE to contract Mission Support Alliance (MSA) to conduct Study #1, “Hanford Radioactive Contamination in Biota” at a total cost not to exceed $350,000

 

Resolution 11-04 

Requests DOE to contract National Oceanic Atmospheric Administration (NOAA) to conduct Study #31, “Hanford NRDA Information Liaison for Aquatic Resources” at a total cost not to exceed $84,000

Resolution 11-05  

 

Requests DOE to contract US Fish and Wildlife Service (FWS) to conduct Study #43, “Effects of Hexavalent Chromium and Other Stressors on Native Mussels” at a cost not to exceed $310,000

Resolution 11-06

 

Requests DOE to contract US Fish and Wildlife Service (FWS) to conduct Study #53, “Regeneration of Hanford Groundwater Contaminant Plume Maps and Calculate Plume Volumes” at a total cost not to exceed $125,000

Resolution 11-07

 

Appoints Larry Goldstein, representing the State of Washington as the Vice Chair of the HNRTC for FY2012

Resolution 11-08  

 

Recommends DOE continue the contract of Ruth Nicholson for Facilitator to the HNRTC for FY2012

 

Resolution 11-09 

Authorizes DOE to spend up to $500,000 for Industrial Economics (IEc) and Ridolfi Inc. to undertake Project #5/6 Preliminary Estimate of Damages with certain contract conditions

 

Resolution 11-10 

Authorizes DOE to add up to $85,000 to the current IEc contract to enable IEc to continue to participate in Council and TWG meetings at IEc’s current level of engagement

  

2010

Resolution No. 10-02 Selects Jack Bell as Vice-Chair for a one year term starting in September 2010 and Chair for a one year term starting in September 2011 

Resolution No. 10-03

 

Approves continued use of a facilitator in FY 2011

2009

Resolution No. 09-01

Approves continued use of a facilitator utilizing funds provided by US DOE for FY 2010

 

Resolution No. 09-02 Requests US DOE to continue the service of Dr. Teresa Michelson as facilitator in 2010
Resolution No. 09-03

Establishes 6 technical working groups to support the injury assessment including: 1) Contaminant Source/Pathway; 2) Groundwater/Vadose Zone Resources; 3) Aquatic Resources; 4) Terrestrial Resources; 5) Human Uses; and 6) Restoration


 

Resolution No. 09-04

Requests US DOE to develop a funding instrument with the National Fish and Wildlife Foundation for administration of funds and contracts on behalf of the HNRTC

Resolution No. 09-05

Election of Russ MacRea to serve as the Vice-Chair for a one-year term beginning October 1, 2009

                

2008

Resolution No. 08-01

Recognizes Susan Hughs for her service to the council
 

Resolution No. 08-02

Honors Don Steffick for his many years of service to the council
 

Resolution No. 08-03

Selects Jay McConnaughey as Vice-Chair for a one year term starting in September 2008 and Chair for a one year term starting in September 2009  


 

Resolution No. 08-04

HNRTC agreement to continue to function as a council and proceed with a natural resource damage assessment

 

 

2007

Resolution No. 07-01

Election of Paul Shaffer to serve as the Vice-Chair for a one-year term beginning October 1, 2007

 

2006

Resolution No. 06-01

Selecting Larry Goldstein as the Temporary Chair, beginning September 1, 2005

Resolution No. 06-02

Selecting Dr. Barbara Harper as the Vice-Chair beginning September 1, 2005 and Gabriel Bohnee as Vice-Chair beginning September 1, 2006


 

 

 

 

 