§ 52.133 Relationship to other subparts.
(a) This subpart applies to a person
that requests a standard design approval
from the NRC staff separately from an
application for a construction permit
filed under 10 CFR part 50 or a
combined license filed under subpart C
of this part. An applicant for a
construction permit or combined license
may reference a standard design
approval.
(b) Subpart B of this part governs the
certification by rulemaking of the design
of a nuclear power plant. Subpart B may
be used independently of the provisions
in this subpart.
(c) Subpart F of this part governs the issuance of licenses to manufacture nuclear power reactors to be installed and operated at sites not identified in the manufacturing license application. Subpart F of this part may be used independently of the provisions in this subpart.
[72 FR 49538, Aug. 28, 2007]