![](https://webarchive.library.unt.edu/web/20090514204009im_/http://www.ne.doe.gov/images/spacer_white.gif) |
![](https://webarchive.library.unt.edu/web/20090514204009im_/http://www.ne.doe.gov/images/spacer.gif) |
You are here: Nuclear Energy Home > Nuclear Power 2010 > Nuclear Scorecard
|
![](https://webarchive.library.unt.edu/web/20090514204009im_/http://www.ne.doe.gov/images/spacer.gif) |
![](https://webarchive.library.unt.edu/web/20090514204009im_/http://www.ne.doe.gov/images/spacer.gif) |
![](https://webarchive.library.unt.edu/web/20090514204009im_/http://www.ne.doe.gov/images/neNP2010Header.gif)
Nuclear Power Deployment Scorecard
Powering Future Decades
Current Scorecard - May 11, 2009
What's New
- TVA and NuStart announced on May 1 and April 30, 2009, respectively, their intent to transfer the Westinghouse AP1000 reference application (R-COL) from Bellefonte to Vogtle.
- NRC announced Atomic Safety and Licensing Board (ASLB) panels to preside over hearings for the following COL applications:
- Ameren UE – Callaway, on May 1
- STPNOC – South Texas Project, on April 2
- Progress Energy announced a 20-month delay the Levy County construction schedule on May 1, 2009, upon NRC's determination that excavation and foundation preparation work can only begin after a COL is granted.
- On May 1, NRC announced the opportunity for the public to request a hearing on TVA's Operating License application for Watts Bar Unit 2 near Spring City, TN.
- NRC held a public meeting in Homestead, FL on April 23, to discuss the Progress Energy COL application for two AP1000 reactors at Turkey Point, expected to be submitted 2009.
- An ASLB heard oral arguments on a request for a hearing for the Levy County COL proceeding on April 20, in Bronson, FL.
- Exelon informed NRC on March 13 of its selection of the ABWR for Victoria County, replacing the original ESBWR; submittal of a COLA revision expected 3rd quarter 2009.
Quick Statistics
- Early Site Permits issued—3
- Permits under review—1
- COL applications submitted—17
No. reactors submitted—26
- COL applications docketed—17
No. reactors docketed—26
Docketed but suspended—4
- Total expected license applications—23
Expected number of reactors—34
- Certified reactor designs—2
- Reactor designs under review—4
- Announced plant locations—21
- Companies applying for COL—20
|
|
Number of Planned Reactors (34)
Vendor Technology Under Consideration
General Electric
- Advanced Boiling Water Reactor (ABWR) – 1,356 MWe (certified 10CFR52 App A)
- Economic Simplified Boiling Water Reactor (ESBWR) – 1,560 MWe
Westinghouse
- Advanced Passive Pressurized Water Reactor (AP1000) – Twin units 1,117 MWe each (certified 10CFR52 App D)
AREVA
- United States Evolutionary Pressurized Water Reactor (US EPR) – 1,600 MWe
Mitsubishi Heavy Industry
- United States Advanced Pressurized Water Reactor (US APWR) – 1,700 MWe
|
|
Status of License Applications (23) Safety/Environmental Review Status
Announced Nuclear Locations
- Amarillo (TX)—Amarillo Power
- Bell Bend (PA)—PPL (formerly Susquehanna)
- Bellefonte (AL)—Tennessee Valley Authority
- Elmore County (ID)—Alternate Energy Holdings
- Callaway (MO)—AmerenUE
- Calvert Cliffs (MD)—UniStar
- Clinton (IL)—Exelon
- Comanche Peak (TX)—Luminant
- Fermi (MI)—DTE Energy
- Grand Gulf (MS)—Entergy
- Shearon Harris (NC)—Progress Energy
- Levy County (FL)—Progress Energy
- Nine Mile Point (NY)—UniStar
- North Anna (VA)—Dominion Energy
- River Bend (LA)—Entergy
- South Texas Project (TX)—STP Nuclear
- V.C. Summer (SC)—SCE&G
- Turkey Point (FL)—Florida Power & Light
- Victoria County (TX)—Exelon Generation
- Vogtle (GA)—Southern Nuclear
- William States Lee III (SC)—Duke Energy
|
|
|
|
![](https://webarchive.library.unt.edu/web/20090514204009im_/http://www.ne.doe.gov/images/spacer.gif) |
Nuclear Scorecard |
|
|
![](https://webarchive.library.unt.edu/web/20090514204009im_/http://www.ne.doe.gov/images/int_padbtm2_right.gif) |
|
|
Nuclear Power Deployment Scorecard |
|
![On Schedule](images/on_schedule_chk_lg.gif) |
Early Site Permit (ESP) > |
|
- Three site permits issued by NRC (Clinton, Grand Gulf, North Anna)
- One site permit application under NRC review (Vogtle)
- Submission of three other ESP applications expected in 2010-2012
|
![On Schedule](images/on_schedule_lg.gif) |
Combined Construction and Operating License (COL) > |
![On Schedule](images/on_schedule_sm.gif) |
License Applications Submitted to NRC
- Thirteen COLAs docketed and under review
- Three docketed COLAs suspended pending technology decision
- One docketed COLA is delayed as the power company focuses on a previously submitted COLA
- Submission of 6 additional COLs expected in 2009-2010
|
|
![On Schedule](images/on_schedule_sm.gif) |
Status of Reference R-COLs
- All five R-COLs have been submitted and are undergoing NRC review (Bellefonte, Calvert Cliffs, Comanche Peak North Anna, South Texas Project, Vogtle)
|
![On Schedule](images/on_schedule_lg.gif) |
Reactor Design Certification (DC) > |
|
- Two advanced reactor designs certified by NRC (ABWR and AP1000)
- Four reactor designs undergoing NRC review (ESBWR, US-EPR, AP1000 amend., and US-APWR
|
![On Schedule](images/on_schedule_lg.gif) |
New Nuclear Plant Orders > |
![On Schedule](images/on_schedule_sm.gif) |
Long-Lead Equipment Orders
- Nine utilities have ordered large, long-lead nuclear component forgings from three reactor vendors
- Four steel containment shells and 24 reactor coolant pumps have been ordered for AP1000 units
- Two domestic large component facilities being built
- Japan Steel Works is the only manufacturer of ultra-large forgings; worldwide-capacity limited
|
|
![On Schedule](images/on_schedule_sm.gif) |
Engineering, Procurement, and Construction Contracts (EPC)
- Four EPC contracts initiated (Vogtle, V.C. Summer, STP, and Progress)
- Plant engineering is in progress; completion required to start construction
|
![Delayed](images/delay_lg.gif) |
New Nuclear Plant Construction, Operation, & Deferral > |
|
- No utility has committed to constructing a new advanced reactor
- TVA resumed construction of Watts Bar 2 and construction permits for Bellefonte 1 & 2 were reinstated
|
![Delayed](images/delay_lg.gif) |
Federal Financial Incentives > |
![On Schedule](images/on_schedule_sm.gif) |
Standby Support (Risk Insurance)
- Final 10 CFR Part 950 Rule issued August 11, 2006
- Two active Notices of Intent to Request a Conditional Agreement; a third notice has been withdrawn. One formal request under review by DOE.
|
|
![On Schedule](images/on_schedule_sm.gif) |
Production Tax Credits
- Internal Revenue Bulletin 2006-18 published May 2006
- IRS considering revised guidance
|
|
![Delayed](images/delay_sm.gif) |
Nuclear Power Loan Guarantees
- The Department is authorized to guarantee $18.5 billion in loans for nuclear power projects. First NRC-issued COL not expected before mid-2011.
- Fifteen power companies have submitted Part II applications by the December 19, 2008 deadline, requesting a total of $93 billion in loans to be guaranteed. The applications cover 10 sites with a total of 16 reactors, capable of providing 22 GW in generating capacity.
- DOE has narrowed the new reactors eligible to receive loan guarantee to five applicants.
|
|
|
Scorecard Legend |
|
![On Schedule](images/on_schedule_sm.gif) |
Implementation proceeding according to plan and schedule |
![Delayed](images/delay_sm.gif) |
Progress being made; however, issues or uncertainties exist that could impede progress |
![Failure](images/failure_sm.gif) |
Unlikely to realize objectives absent significant management attention |
![Unspecified](images/no_date_sm.gif) |
No dates or end state established |
![Arrows](images/arrows.gif) |
Indicates change in status or progress since last evaluation |
![Check](images/check.gif) |
Regulatory Demonstration completed. No further government assistance is warranted. |
|