Project Number |
427 |
Date of Summary |
January
28, 2005 |
Subject |
Dispersant Effectiveness Test
Protocol Development for Ohmsett |
Performing Activity |
S.L. Ross Environmental Research
Limited and
MAR, Inc. |
Principal Investigator |
Ian Buist and Steve Potter
|
Contracting Agency |
Minerals Management Service |
Estimated Completion |
Completed |
Description |
This project developed a
standard test protocol for a wide range of dispersant related variables at
the Ohmsett facility. The test protocol can be used in the Ohmsett
facilities simulated open ocean conditions in a reproducible manner. The
development of this test protocol added a new testing capability at Ohmsett.
|
Progress |
Final report was submitted
March 2000
|
Report |
AA (67 pages, 1.9 MB)
|
SL Ross. 2001. Ohmsett
Dispersant Test Protocol Development. Final Report
|