Audubon Fly/Carrollton Levee Enlargement Construction Project
Audubon Fly/Carrollton levee enlargement project will extend from Audubon Park's Riverview to the Jefferson Parish line.
Presentation from September 20th public meeting
News Release announcing public meeting to be held September 20, 2012
Timeline
Construction Contract Award: 28 September 2012
News Release announcing award of construction contract
Initiate Construction: 1 November 2012
Construction Completion: 1 November 2013
Contact
Webmaster
504-862-1606
webmaster-mvn@usace.army.mil