SGIG Program Data for September 30th, 2012
Section 1
AMI Assets |
Quantity * |
Incurred |
Number of |
AMI smart meters *** |
11,092,567 |
$1,781,401,341 |
73 |
Communications networks and hardware that enable two way communications |
|
$520,910,743 |
71 |
IT hardware, systems, and applications that enable AMI features and functionalities |
|
$420,259,793 |
69 |
Other AMI related costs |
$198,567,316 |
85 |
|
Total AMI cost |
$2,921,139,193 |
85 |
* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.
* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).
** Projects only report data on devices they plan to install. Each project installs equipment that best supports their individual goals. Therefore, the number of projects reporting is expected to vary by equipment category. The individual project reporting pages show what equipment that project is installing.
*** SGIG recipients are also required to submit monthly reports to DOE through SIPRIS that include the number of smart meters they have installed. DOE reports both numbers. The count provided here includes meters that are installed AND functioning (i.e., they are transmitting information to the utility in support of their primary function). The SIPRIS numbers report the number of meters installed.
Section 2
Customer System Assets |
Quantity * |
Incurred |
Number of |
In home displays |
7,789 |
$8,359,985 |
40 |
Direct load control devices |
161,344 |
$99,409,112 |
43 |
Programmable communicating thermostats |
160,657 |
$65,983,541 |
31 |
Smart appliances |
220 |
$515,128 |
7 |
Communication networks and home area networks |
|
$0 |
0 |
IT hardware, systems, and applications that enable CS features and functionalities |
|
$148,370,611 |
45 |
Other customer system related costs |
$60,558,870 |
78 |
|
Total customer system cost |
$383,197,247 |
78 |
* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.
* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).
** Projects only report data on devices they plan to install. Each project installs equipment that best supports their individual goals. Therefore, the number of projects reporting is expected to vary by equipment category. The individual project reporting pages show what equipment that project is installing.
Section 3
Electric Distribution Automation Assets |
Quantity * |
Incurred |
Number of |
Automated feeder switches |
6,102 |
$334,448,071 |
47 |
Automated capacitors |
9,720 |
$86,685,041 |
44 |
Automated regulators |
5,937 |
$24,148,027 |
32 |
Fault current limiter |
0 |
$928,967 |
4 |
Feeder monitors |
3,234 |
$98,842,253 |
29 |
Substation monitor |
14,814 |
$104,262,472 |
18 |
Distribution automation/Substation communication networks |
|
$113,090,468 |
52 |
Distribution management systems |
|
$145,154,801 |
41 |
IT hardware, systems, and applications that enable distribution functionalities |
|
$11,895,007 |
30 |
Other electric distribution automation related costs |
$126,976,929 |
72 |
|
Total electric distribution automation cost |
$1,046,432,035 |
72 |
Electric Distribution Distributed Energy Resource (DER) Assets |
Quantity * |
Incurred |
Number of |
Stationary electricity and energy storage devices |
181 |
$3,579,602 |
3 |
EV charging stations |
220 |
$2,948,857 |
10 |
DER interconnection and communication equipment |
5 |
$38,850 |
5 |
Other DER related costs |
$2,170,122 |
32 |
|
Total electric DER cost |
$8,737,430 |
32 |
* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.
* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).
** Projects only report data on devices they plan to install. Each project installs equipment that best supports their individual goals. Therefore, the number of projects reporting is expected to vary by equipment category. The individual project reporting pages show what equipment that project is installing.
Section 4
Electric Transmission System Assets |
Quantity * |
Incurred |
Number of |
PMUs |
420 |
$31,552,313 |
12 |
Phasor data concentrators |
86 |
$9,318,341 |
12 |
Dynamic rating systems |
0 |
$0 |
0 |
IT hardware, systems, and applications that enable transmission functionalities |
|
$46,659,874 |
31 |
Advanced applications |
|
$14,853,263 |
14 |
Other transmission related costs |
$143,446,787 |
22 |
|
Total transmission installed cost |
$245,830,579 |
22 |
* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.
* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).
** Projects only report data on devices they plan to install. Each project installs equipment that best supports their individual goals. Therefore, the number of projects reporting is expected to vary by equipment category. The individual project reporting pages show what equipment that project is installing.