USDOT Federal Highway Administration USDOT Home | FHWA Home | Feedback
Skip to main content

Project Profiles

Presidio Parkway

Location

San Francisco, California

Project Sponsor / Borrower

Project Sponsor: California Department of Transportation (Caltrans),
San Francisco County Transportation Authority
Borrower: Golden Link Concessionaire, LLC (GLC)

Program Areas

Project DeliveryProject FinanceP3TIFIA

Fiscal Year Approved

Fiscal Year 2012

Mode

Highway

Description

The Presidio Parkway project is a replacement of Doyle Drive, a 1.6-mile segment of Route 101 in San Francisco that is the southern access to the Golden Gate Bridge, connecting Marin and San Francisco counties and providing a major regional traffic link between the peninsula and North Bay Area counties. The current structure, built in 1936, does not meet current highway standards and is seismically deficient.

The Presidio Parkway project area extends from the Golden Gate Bridge Toll Plaza on the west to Broderick Street on the east, and includes Richardson Avenue, Gorgas Avenue and Marina Boulevard. The Presidio Parkway will be a six-lane facility with a southbound auxiliary lane between the Park Presidio Interchange and the new Presidio access at Girard Road. The roadway will consist of various sections (from the toll plaza east to Richardson Avenue) with a landscaped median:

  • a high-viaduct between the Park Presidio Interchange and the San Francisco National Cemetery (Presidio Viaduct)
  • shallow cut-and-cover tunnels past the cemetery to Battery Blaney (Battery Tunnels)
  • at-grade roadways to the Main Post
  • cut-and-cover tunnels from the Main Post to east of Halleck Street (Main Post Tunnels)
  • a low causeway from Halleck Street to Girard Road
  • at-grade connection to Richardson Avenue

The project is being developed  in two phases. Caltrans is responsible for the design, financing and construction of Phase I, currently nearing completion. Phase I, delivered through a traditional design-bid-build process, consists of a replacement bridge at the Park Presidio Interchange, the new southbound Presidio Viaduct, the southbound Battery Tunnel, and a temporary bypass east of the Main Post to allow construction of the Main Post Tunnels and roadway to Richardson Avenue.

Through a competitive procurement process, Caltrans selected a private consortium, the Golden Link Concessionaire, to deliver Phase II as a design, build, finance, operate, and maintain (DBFOM) availability-pay concession. The P3 Project Agreement with GLC was executed on January 3, 2011. GLC will receive milestone payments following substantial completion and quarterly availability payments through the concession period, based on performance.

Major construction will begin in late 2012 to complete the remaining elements of the Presidio Parkway, including the northbound Presidio Viaduct and Battery Tunnel, the Main Post Tunnels, and the new Girard Road Interchange with a direct connection to the Presidio. This phase will also include final landscaping.

Cost

Estimated Total Cost: $851.6 million

Funding Sources

Phase I:  $486.9 million
Federal funds - $70.8 million
ARRA grant - $83.3 million
State funds - $229.0 million
Local funds - $103.9 million

Phase II: $364.7million
Bank Loan - $166.6 million
TIFIA Tranche A Loan - $89.8 million
TIFIA Tranche B Loan - $60.2 million
Parent Company Contribution - $2.6 million
Private Equity - $43.0 million
TIFIA Capitalized Interest - $2.5 million

Project Delivery / Contract Method

Phase I: Design-bid-build

Phase II: DBFOM (design, build, finance, operate, and maintain)

Project Partner

Phase II
Golden Link Partners, LLC

  • HOCHTIEF PPP Solutions North America
  • Meridiam Infrastructure

Construction  Joint Venture (design-build members):

  • Flatiron West, Inc.
  • Kiewit Infrastructure West, Co.

Project Advisors / Consultants

Phase I Construction:

  • C.C. Myers
  • R&L Brosamer

Phase II
Project Design:

  • HNTB Corporation

To the Borrower:

  • Scotia Capital, Inc. – Financial advisor
  • Milbank, Tweed, Hadley & McCloy LLP – Legal Counsel
  • Moore-McNeil, LLC – Insurance Consultant

To USDOT TIFIA JPO:

  • TIFIA Legal Advisor – Bryant Miller Olive
  • TIFIA Financial Advisor – Montague DeRose and Associates, LLP/High Street Consulting Group, LLC

To Public Sector Sponsor:

  • Sperry Capital, Inc. – Financial Advisor
  • KPMG Corporate Finance LLC – Financial Advisor
  • Nossaman, LLP – Legal Advisor

Lenders

Banks, USDOT TIFIA

Duration / Status

Phase I:
Construction to be completed Summer 2012

Phase II:
P3 Agreement with Golden Link Concessionaire signed January 3, 2011 (commercial close).
Pre-construction began mid-2011
Financial close: June 14, 2012
Major construction start: late 2012
Expected completion: September 2015

Duration of concession: 30 years
TIFIA Credit Assistance

Direct Loan: $150.0 million

TIFIA credit assistance totals $150 million and is structured into two tranches, to reflect the two distinct sources of repayment and state and local funding limitations. The $89.8 million short-term loan (Tranche A) is to be repaid fully following substantial completion in the form of a milestone payment.  The $60.2 million long-term loan (Tranche B) is to be repaid using the non-Federal portion of the quarterly availability payments to GLC  over a 28 year period. The TIFIA loans will be secured by a lien on project collateral. 

Financial Status / Financial Performance

TIFIA credit agreement executed on June 14, 2012

The first TIFIA interest payment is scheduled for June 2016. Principal repayments are scheduled to begin in December 2018.  Level debt service payments commence in 2019.  The final maturity of the TIFIA loan is December 2045.

Innovations

  • California’s first P3 transaction under its new (2009) legislation and since the development of the South Bay Expressway and SR 91 Express Lanes
  • California’s first availability payment contract for transportation infrastructure
  • First project with direct Federal-aid participation in availability payments.  
  • First TIFIA loan to be repaid in part with a milestone payment following substantial completion.
  • Incorporation of numerous Context Sensitive Design features to minimize traffic impacts and to protect and enhance environmental and cultural resources

Related Links / Articles

Project Website

Caltrans P3 Website

Caltrans Construction Contracting Website

Contacts

Kome Ajise, P3 Program Manager
California Department of Transportation
1120 N Street, MS 49, Sacramento, CA 95814
Tel: (916) 654 4227

Leroy L. Saage, PE, Deputy Director for Capital Projects
San Francisco County Transportation Authority
1455 Market Street, 22nd Floor, San Francisco, CA 94103
Tel: (415) 522-4800
Fax: (415) 522-4829
www.sfcta.org
lee.saage@sfcta.org

Bob Kuo, CEO
Golden Link Concessionaire, LLC
Tel: (925) 899-6421
bob.kuo@GLC-presidioparkway.com