Site Plans & Development Projects

Approved October 3, 1991 and amended April 1, 2004

Table of Contents

Section 1: Introduction

A. Statutory Authority
B. Applicability of Requirements 
C. Extension. Modification or Waiver 
D. Review for Plan Conformity

Section 2 - Exceptions

Section 3 - Submission Stages

Section 4 - Contents of Submissions

A. Narrative Materials and Data
B. Maps and Drawings
C. Presentation Materials
D. Form of Submissions

Section 5 - Project Plans Coordination and Review Process

A. Early Contact with Commission Staff
B. Early Consultation with Other Agencies
C. Submission Schedule
D. District of Columbia Projects in the Central Area
E. Coordinating Committee
F. Referral
G. Resolution of Planning Issues
H. Review Evaluation and Recommendation of the Commission Staff
I. Public Notice and Participation
J. Action of the Commission
K. Official Notification of Commission Action

Section 6 - Time Period For Review

Section 7 - Delegation of Authority to Executive Director

 

Section 1- Introduction

A. Statutory Authority

Congress created the National Capital Planning Commission (Commission) to serve as the central federal planning agency for the unique concentration of federal activities and interests in the National Capital Region (Region). (Note 1) One of the Commission's principal responsibilities is to coordinate development activities of federal and District of Columbia agencies in the Region. These agencies must submit development proposals to the Commission under the following statutes:

  1. Federal and District of Columbia Land Acquisition and Development Proposals (Note 2)

    Section 5(a) of the National Capital Planning Act of 1952, as amended (40 U.S.C. 71d(a)) ("Planning Act"), requires each federal and District of Columbia agency, prior to the preparation of construction plans, or to commitments for the acquisition of land in the region, to consult with the Commission in its preliminary and successive stages of planning.

  2. Federal Public Buildings in the District of Columbia (Note 2)

    Section 16 of the Act of June 20, 1938, ("Zoning Act," D.C. Code Ann. Sec. 5 432 (1981)), requires Commission approval of the location, height, bulk, number of stories, and size of federal public buildings in the District of Columbia and the provision of surrounding open space.

  3. District of Columbia Public Buildings in the Central Area

    Section 5(c) of the Planning Act (40 U.S.C. 71d(c)) requires Commission approval of District of Columbia public buildings within the central area of the District as concurrently defined by the Commission and Council of the District of Columbia (Central Area).

  4. Commemorative Works on Federal Lands

    Section 7(b) of "An Act to provide standards for placement of commemorative works on certain Federal lands in the District of Columbia and environs, and for other purposes", November 14, 1986 (Commemorative Works Act, 100 Stat. 3650, 40 U.S.C.S. 1007) requires Commission approval of site and design proposals for commemorative works proposed in the District or its environs.

    Top

B. Applicability of Requirements

This document details the process for submitting proposals and plans for Commission action. It applies to the following types of projects and proposals of the District and federal governments, including civilian and military installations and facilities in the region: (Note 3)

  1. site acquisition
  2. building construction or renovation, with or without related site improvements
  3. site development, such as grading, landscaping, street and road extensions
  4. improvements involving changes in cartway configurations, and surface parking
  5. all forms of commemorative works

    Top

C. Extension, Modification, or Waiver

The Executive Director of the Commission ("Executive Director") may extend, modify, or waive requirements under certain limited circumstances. Where a waiver affects submission materials that may address potentially significant offsite impacts, the Executive Director must provide notice to potentially affected public agencies and provide opportunity for consultation. Waivers may be granted or requirements extended or modified where the project submitted for review has:

  1. Unique or special character or qualities, such as extraordinarily limited size and/or scope, that make certain elements of the required materials unnecessary.

  2. Been sufficiently documented in prior submissions with materials that remain current.

  3. Unique implications necessitating the submission of specialized materials.

    Top

D. Review for Plan Conformity

1. The Commission's review includes assessment of conformance with applicable provisions of the Comprehensive Plan for the National Capital (Comprehensive Plan). Federal Elements of the Comprehensive Plan (available from the Commission) contain goals, policies, and implementation proposals addressing a variety of subjects, such as locations of federal facilities, employee services, affordable housing for federal employees, and energy conservation in the design and construction of federal facilities.

2. Since master plans are necessary for installations on which more than one principal building structure, or activity is located or proposed to be located, the Commission's Master Plan Submission Requirements where applicable, must also be followed. The Commission is unlikely to approve or recommend favorably on projects on installations for which there is no approved master plan.

Site acquisition (location and program) proposals and schematic development or preliminary plan submissions serve as the basic planning documents for intergovernmental coordination on sites where no master plan is required (see Section 5.F).

Top

Section 2 - Exceptions

As authorized by the Planning Act, the Commission has determined that plans need not be submitted for projects where:

A. Replacement of walks, roadways, and parking areas involves no change in the location or the existing character or extent of the improvement.

B. Rehabilitation and improvement of buildings and structures involve no change in the existing character, predominant use, or extent of the building or structure.

C. Replacement of trees, shrubs, and other plant materials, including changes in species, involves no change in the existing character of the site.

D. Replacement (excluding relocations or extensions) of underground utility lines such as pipes and cables (excluding pumping stations and treatment facilities) will not (1) necessitate removal of existing trees or changes in the natural topography or (2) perpetuate or create an adverse environmental impact.

Top

Section 3 - Submission Stages

Sponsoring agencies should contact the Commission staff at the earliest possible time in site acquisition or project planning to confirm appropriate submission stages and resolve questions concerning submission contents (see Section 5.A). When the agency holding jurisdiction over an affected site and the agency proposing a development differ, the former is normally considered as the sponsoring agency. Project plans and related documentation must be submitted to the Commission at the following stages, where applicable:

A. Location and Program submissions must precede commitments for the acquisition of land to be paid for in whole or in part from Federal or District funds.

B. Schematic Development submissions are required where size, complexity, and/or projected impacts of proposed projects (including site improvements and commemorative works) necessitate early Commission guidance prior to the expenditure of substantial funds for more detailed project design. In cases involving complex planning and development proposals, the Executive Director may require schematic development submissions.

Where issues relate to the potential suitability of a proposed site, the Executive Director may require that schematic development proposals accompany the location and program submission. Any sponsoring agency may choose to make a schematic development submission to solicit the Commission's views prior to preparation of preliminary plans.

C. Preliminary submissions must be made for all new construction or renovation projects (except as outlined in Section 2) after tentative design decisions have been made but well before detailed design work begins, typically at the 20 to 25 percent development stage. Timely submissions of preliminary plans are vital to avoid costly revisions in later detailed design stages.

If major changes are made in either the design or program of a proposed development after the Commission has reviewed a preliminary submission, the affected sponsoring agency shall submit revised preliminary plans for review as far in advance of completion and submission of final plans as possible, except where such changes have been made specifically in response to Commission recommendations on the preliminary submission. Preliminary submissions may take the form of:

  1. preliminary site and building plans for projects involving both building construction or renovation and related site improvements;
  2. preliminary building plans for projects involving additions or renovation where no site improvements are involved;
  3. preliminary site development plans for projects involving only site improvements;
  4. preliminary designs for all commemorative works proposals. In cases in which the proposed commemorative works involve only site improvements, including sculpture, content requirements for preliminary site development plans apply. Where proposed commemorative works include substantial structures, content requirements for preliminary site and building plans apply.

D. Final submissions must follow preliminary submissions (see Section 3.C), after design decisions have been made (including building and landscaping materials), typically at the 60 to 70 percent development stage, and prior to advertisement and award of construction contracts

Final site and building plans for Federal public buildings in the District of Columbia and District government public building within the central area will ordinarily satisfy requirements under Section 16 of the Zoning Act and Section 5(c) of the Planning Act.

Sponsoring agencies may not lawfully deviate from final plans approved by the Commission under these provisions. Therefore sponsoring agencies are urged to resolve all outstanding planning and design issues with affected agencies and organizations prior to the submission of final site and building plans.

If substantial changes (see Section 2, for guidance) must be made in final plans after the Commission has taken action on them but prior to construction, sponsoring agencies are required to submit revised final plans for Commission review and action.

Top

Section 4 - Contents of Submissions

Project plan submissions include narrative materials and data, maps and drawings, and presentation materials which describe and illustrate existing conditions and proposed developments. Although the required narrative materials, data, and supporting documentation requirements are generally consistent for all submission stages, greater detail must be provided at successive stages to reflect decisions made as project planning advances.

Before preparing a submission, please review the Environmental and Historic Preservation Policies and Procedures, adopted April 2004. The recently adopted requirements for environmental and historic preservation compliance differ from those outlined in this document, which was last adopted by the Commission in 1991 and is now being updated. Please defer to the requirements outlined in the Environmental and Historic Preservation Policies and Procedures.

A. Narrative Materials and Data

1. Project Report

A project report is required at all stages (except that, where required information is fully provided in accompanying environmental documentation, it need not be repeated in the project report). Where a project report has been submitted at an earlier review stage, a fully updated supplement may be submitted at successive stages. The Supplement should include responses to any Commission recommendations from the previous stage.

The project report serves as required development program information for location and program submissions. Project reports must contain the following information:

a. name and telephone number of agency project manager;

b. narrative description of the project, including existing conditions to be affected and a summary of the basic design concept on which the physical form of the proposal is base.

c. total area of site and allocation of land to proposed uses;

d. area of building(s) and site coverage;

e. existing assigned employment and projected assigned employment over a 20-year period, in five-year increments;

f. description of the relationship of the project to the agency's master plan, where applicable, including rationale for any deviations;

g. status of coordination with affected local and state governments and the Metropolitan Washington Council of Governments (COG) for projects not previously coordinated through an installation master plan;

h. status of community participation, including a summary of community views;

i. schedule for construction and occupancy;

j. total estimated cost of project and funding status;

k. A Transportation Management Program (TMP) for any project that will increase the employment level on a work site to 500 or more employees (including existing and proposed employees). Over and above this requirement, sponsoring agencies are encouraged to prepare TMPs for projects that will increase employment levels to 100 or more employees

Where the TMP for a project is an integral part of an installation TMP approved by the Commission as part of a master plan submission, a summary of provisions of the installation TMP applicable to the project will satisfy the requirements of this section.

The TMP should incorporate the following:
  1. stated goals for trip reduction, mode split, and vehicle occupancy;
  2. firm commitments to strategies to minimize vehicle work trips and discourage single-occupant travel during peak and off-peak hours;
  3. description of measures to monitor achievement of goals and to adjust trip reduction strategies as needed;
  4. description of existing and projected peak hour traffic by mode and a summary of existing and proposed parking by type of assignment (official cars, vanpools, carpools, single occupant vehicles, handicapped persons, visitors, etc.);
  5. evaluation of projected transportation impacts and description of proposed mitigation measures;
  6. summary of the relationship of the TMP provisions to transportation management requirements of local, state and regional agencies, including provisions for working cooperatively with affected agencies to address those requirements.
The format and content of each TMP may vary on a case by case basis, according to transportation management requirements of local jurisdictions and specific details of the project and site. The Commission staff is available to facilitate coordination of a sponsoring agency's transportation management planning with the Metropolitan Washington Council of Governments Transportation Planning Board, affected local officials, and the General Services Administration. A transportation management strategies handbook will be available through this coordination.

2. Environmental Documentation

a. The environmental document prepared by a Federal sponsoring agency pursuant to the National Environmental Policy Act of 1969, as amended, (NEPA) and Council on Environmental Quality Regulations must be part of each submission. The document must be an Environmental Impact Statement (EIS), if required by NEPA Section 102(2)(C). Otherwise, an Environmental Assessment (EA) must be submitted (along with the agency's formal determination that an ElS is not required), unless the agency demonstrates that the project qualifies as a Categorical Exclusion in its environmental policies and procedures.

For Federal public building projects in the District of Columbia, or any other developments requiring Commission approval, the sponsoring agency must consult with the Commission at the earliest possible time and permit it to participate with the agency in determining the appropriate environmental document

The NEPA process must be completed prior to the initial submission, but the initial stage document may be used for successive stages if current and substantively sufficient. Where substantial changes are made, the environmental document must be amended by the sponsoring agency and resubmitted at the appropriate successive review stage.

b. Each submission by a District of Columbia sponsoring agency must include an EA. If the proposed development is a District of Columbia public building within the boundaries of the central area, the Executive Director will determine the appropriate environmental document for Commission action.

If an EIS is required, it will be filed by the Commission, based on environmental information provided by the sponsoring agency (see Section 5.D).

3. Historic Preservation Documentation

a. Each submission by a Federal sponsoring agency must include a determination by the agency head or other authorized official, as to whether the project is subject to Section 106 of the National Historic Preservation Act of 1966, as amended (Section 106), or Section 2(b) of Executive Order 11593 of May 13, 1971.

In addition, an analysis must be submitted of any effects of the proposed project on recognized historic resources, both on the site and in such close proximity that their setting or use may be altered by the project.

If a Section 106 review is required, submissions must include documentation of consultation with the affected State Historic Preservation Officer (SHPO) and the Advisory Council on Historic Preservation (ACHP), as follows:

  1. The initial submission stage must include a copy of the sponsoring agency's letter to the affected SHPO initiating the review process. Generally, such letters will provide sufficient analysis of the effects of a proposed project to satisfy submission requirements. Where potential impacts on historic resources merit special attention, the Executive Director may require that the sponsoring agency obtain the views of the affected SHPO, or the review body advising that SHPO, prior to Commission action.
  2. The final submission stage must include a copy of the letter(s) from the SHPO and, if applicable, the ACHP, certifying compliance with Section 106.

b. The Commission undertakes the section 106 process, if applicable, for District of Columbia public buildings in the central area (see Section 5.D.2).

4. Floodplain Management and Wetlands Protection

The initial submission by a Federal agency for a project located in a floodplain or wetland must include a copy of the agency's Statement of Findings pursuant to Executive Order 11988 or Executive Order 11990. This statement must evaluate potential impacts and identify proposed mitigation measures.

Top


B. Maps and Drawings

1. Location and Program Submissions

As noted in Section 3.A, these submissions are required where land acquisition is proposed. They must include the following maps, as applicable:

a. A vicinity map must be submitted, uncolored, at a minimum scale of 1 inch equals 400 feet, except where extremely large sites require a smaller scale to meet sheet size limitations (see Section 4.0.l), and must contain the following information:

  1. boundaries of the proposed site, existing uses, building outlines, streets, and other physical features, both within the site and in the surrounding area extending at least 500 feet in all directions;
  2. existing zoning on non-Federal lands surrounding the site and proposals of adopted local and/or state plans affecting land use, zoning, and transportation facilities in the surrounding area (a separate map depicting the site in relation to planned surrounding conditions may be used if proposed changes cannot be dearly presented in combination with existing conditions).

b. A boundary map must be submitted, uncolored, at a minimum scale of 1 inch equals 50 feet for sites of less than 40 acres and 1 inch equals 100 feet for larger sites, except where extremely large sites require a smaller scale to meet sheet size limitations (see Section 4.D.1). Where appropriate, multiple sheets, with match lines, may be used to present the boundary map for such large sites.

The boundary map must contain the following information:

  1. site boundaries, including dimensions;
  2. topography of the site (preferably at 1- or 2-foot contour intervals);
  3. outlines of buildings (with annotations indicating those proposed to remain and to be demolished); roadways and parking areas; vehicular entrances to the site; major utilities; walkways, fences, walls and other man-made improvements; and substantial groupings of trees and shrubs.

c. A basic development proposals map, although not required at the location and program stage, should be submitted where early development proposals have been identified in order to provide for Commission review and recommendations at the earliest possible opportunity. This map must be submitted, uncolored, at the same scale as the boundary map (these two maps may be combined if the information presented is clear and readable) and must contain the following information:

  1. proposed building locations;
  2. proposed vehicular access points and roadway locations;
  3. proposed groupings of trees and other basic landscape features;
  4. any other tentatively identified building or site design features.

2. Schematic Development Submissions

As noted in Section 3.B, these submissions are made where, because of a project's size, complexity, and/or projected impacts, early Commission review and guidance is needed. Because such submissions often focus on specific development issues or expected impacts, flexibility is permitted in the type and detail of information provided

The Commission staff is available to advise on the appropriate level of detail for schematic development submissions. Such submissions must include the following maps and drawings, as applicable:

a. A vicinity map (see Section 4.B.1.a);

b. Schematic development drawings including the following:

  1. A schematic site plan is required where the project involves new buildings or structures and/or other site changes in order to depict the siting relationships of proposed improvements and existing site features. The schematic site plan must contain the following information:

    (a) site boundaries, including dimensions

    (b) existing topography of the site (preferably at 1 or 2 foot contour intervals) and a general indication of proposed substantial site grading

    (c) existing man-made features to remain; general location and footprint of proposed buildings and structures; and general location and layout of major proposed site improvements, including roadways and parking areas, public transportation facilities such as bus bays and shelters, major walkways, stormwater management facilities, and landscape proposals

    (d) any additional information helpful in depicting early site planning direction

  2. Schematic architectural drawings are required where the project involves proposed buildings or structures, except in cases in which the sponsoring agency and the Commission staff have concluded that the schematic development submission should be limited to site development proposals.

    These drawings must contain the following information, as applicable:

    (a) schematic floor plans indicating pedestrian and vehicular entrances, general allocation of principal uses, public areas, and any proposed special interior features;

    (b) schematic elevations indicating the height of the building or structure, general bulk and massing, tentative fenestration proposals, and other features affecting the general design and character of the proposed building or structure;

    (c) any additional information helpful in depicting early design direction for the building or structure.

3. Preliminary and Final Submissions

As noted in Sections 3.C and 3.D, these submissions are required for all projects and must include the following maps and drawings, as applicable:

a. A vicinity map (see Section 4.B.1.a);

b. A site plan is required for all preliminary and final plan submissions, except building plans for additions to or renovation of existing buildings where no site improvements are proposed. This plan must be submitted, uncolored, at a minimum scale of 1 inch equals 50 feet for sites of less than 40 acres and 1 inch equals 100 feet for larger sites, except where an extremely large site requires a smaller scale to meet sheet size limitations (see Section 4.D.I). Where appropriate, multiple sheets, with match lines, may be used to present the site plan for such large sites.

Where proposed improvements involve only a portion of a site, the site plan must show the entire site area, indicating relationships between the portion to be improved and the portion to remain undisturbed.

Where an existing adjacent facility has an integral supporting relationship to a proposed facility, such as an existing parking lot proposed to serve a new office building, the existing facility must be included on the site plan to show functional relationships. The site plan must contain the following information:

  1. site boundaries, including dimensions;
  2. existing and proposed topography of the site (preferably at 1- or 2-foot contour intervals);
  3. existing man-made features to remain and all proposed buildings, structures, and related improvements on and immediately adjacent to the site, including, but not limited to, access ways, driveways, sidewalks, walls, fences, loading areas, off-street parking, and public transportation facilities such as bus bays and shelters.

c. A landscape and grading plan is required for all preliminary and final plan submissions, except building plans for additions to or renovation of existing buildings where no site improvements are proposed. Although a separate landscape and grading plan drawing is preferable, it may be combined with the site plan if proposals are clear and readable. If submitted as a separate plan, the landscape and grading plan must be at the same scale as the site plan. The landscape and grading plan must be submitted, uncolored, and contain the following information:

  1. existing and proposed topography of the site (preferably at 1- or 2-foot contour intervals);
  2. general locations of all existing-to-remain, existing-to-be-removed, and proposed trees, shrubs, and other plant materials;
  3. at the preliminary stage, general identification of proposed plant materials, and, at the final stage, a list of the type, quantity, and size of proposed plant materials.

d. A stormwater management and erosion and sediment control plan is required for all final plan submissions for projects for which there is more than 5,000 square feet of disturbed site area. The plan must include locations and sizes of natural drainageways, storm sewer lines and outfalls, infiltration devices, retention and detention ponds, and any other needed mitigation measures to control stormwater runoff and limit erosion and sedimentation on the site, with back-up calculations. The plan may be incorporated in the project environmental document.

e. Floor plans must be submitted at preliminary and final stages, uncolored, for each floor of proposed buildings (a single drawing is sufficient for identical floors) at a scale commensurate with sheet size limitations (see Section 4.D.l). The scale should be sufficiently large to permit presentations in a conference room at a distance of 20 to 25 feet. Floor plans must contain the following information:

  1. uses allocated to all interior spaces;
  2. interior partitions, stairs, and elevators;
  3. overall dimensions;
  4. dimensions of interior spaces;
  5. elevation of each floor level.

f. Elevations of all sides (facades) of proposed buildings or structures must be submitted, uncolored, at preliminary and final stages, at the same scale as the floor plans, indicating the following:

  1. height, bulk, and massing of the building or structure;
  2. pedestrian and vehicular entrances;
  3. fenestration;
  4. general identification of materials (preliminary stage) and detailed identification of materials (final stage);
  5. treatment of the roof and all related appurtenances, including features such as penthouses, ventilation shafts, chimneys, smoke stacks, antennas, and related screening;
  6. in the District of Columbia, the point of measurement of the height of the building in accordance with the Zoning Act

g. At least two cross sections through proposed buildings, at the same scale as the floor plans, and one or more exterior wall sections showing the proposed installation of principal exterior materials must be submitted uncolored at preliminary and final stages.

h. Roof plans for proposed buildings must be submitted at preliminary and final stages, at the same scale as the floor plans, indicating the following:

  1. roof design, including materials and finishes to be used;
  2. roof appurtenances, including all proposed screening. (Note: Antenna installations are also subject to separate Commission guidelines and submission requirements.)

i. Construction and equipment drawings for exterior building features, site work, and any other proposals requiring coordination with off-site facilities and activities must be submitted at the final stage.

C. Presentation Materials

1. Rendered Plans and Perspectives

One set of rendered plan maps and drawings must be submitted at each review stage. Rendered presentation maps and drawings should be presented in color. At least one rendered perspective of all proposed buildings and substantial site developments is required at the schematic development stage, as applicable, and at preliminary and final stages. Perspectives prepared at an early stage may be resubmitted at later stages if the project design is unchanged.

2. Models

A model must be submitted for all major development proposals (model requirements for a particular submission may be obtained from the Commission staff). Models must depict topography, existing-to-remain and proposed buildings and improvements, pedestrian and vehicular circulation parking and loading areas, public transportation facilities, and principal landscape features. They should be prepared at the same scale as the project site plan, or larger if necessary for presentation purposes.

D. Form of Submissions

1. Sheet Size

Submission drawings should be a standardized sheet size, whenever possible, and in no event exceed a sheet size of 33 by 44 inches, in order to be compatible with the Commission's microfilm file requirements. For projects requiring larger maps or drawings, multiple sheets with match lines within the maximum size limits may be submitted.

2. Orientation

Maps and drawings, where applicable, should be oriented so that north is at the top of the sheet, confirmed by a north arrow. Map and drawing scales should be indicated in numerical and graphic form for reference at full sheet size and in copy reductions.

3. Number of Copies

At least three sets of full size maps and drawings (except construction and equipment drawings) and narrative materials must be submitted at each stage. One set of construction and equipment drawings must be submitted at the final stage (see Section 4.B.3.i).

As discussed in Sections 1.D.2 and 5.F, where projects are located on sites for which master plans are not required, the location and program and schematic development or preliminary plan submissions will normally function as the master plan and must be referred to other agencies and organizations as part of the Commission review process.

The number of sets of submission materials required in such cases is defined in Section 4.D of the Commission's Master Plan Submission Requirements

4. Reduced Size Drawings

One set of maps and drawings, including vicinity map, boundary map, site plan, landscape and grading plan, floor plans of the entrance level and any other levels containing major public spaces, and elevations, as applicable to the specific type of submission, must be submitted at a reduced page size no greater than 8-1/2 by 14 inches and in a form that permits reproduction by a standard copying machine.

5. Electronic Data

The Commission, in collaboration with affected Federal and District of Columbia agencies, will seek in the near future to establish guidelines for the optional submission of narrative materials and maps and drawings in electronic data form. In the interim, sponsoring agencies are encouraged to contact the Commission staff if they have an interest in transferring electronic data for projects on a demonstration trial basis.

Top

Section 5 - Project Plans Coordination and Review Process

A. Early Contact with Commission Staff

Sponsoring agencies should contact the Commission staff at the earliest planning stage for land acquisition and siting and design of proposed new developments in order to prepare for required submissions. On a case-by-case basis the Commission staff will assist sponsoring agencies in determining;

  1. whether a schematic development submission is required for a complex project and, if so, the appropriate level of detail;
  2. type and scope of required environmental documentation;
  3. level of progress required in the Section 106 review process at the initial submission stage;
  4. whether a model is required for presentation;
  5. appropriate intergovernmental review process, including the need for early consultation with affected non-Federal agencies.

Top

B. Early Consultation with Other Agencies

If the potential for off-site impacts necessitates early consultation with other agencies, the Commission staff will contact the planning agency, intergovernmental review officer, chief administrative officer, and responsible elected official of the affected local government and regional and state clearinghouses to arrange a meeting about the project and its anticipated submission schedule. (In general, early consultation will be required on sites not covered by master plans. Frequently, the coordination previously provided through the review of an agency's master plan will satisfy early consultation requirements for projects within the installation covered by the master plan.)

Early consultation meetings, which occur prior to initial submissions to the Commission, give local, regional, and state agencies necessary information about proposed developments; facilitate early identification of issues and concerns; and establish continuing coordination for planning and construction stages, as needed (see Section 5(a) of the Commission's Procedures for Intergovernmental Cooperation in Federal Planning in the National Capital Region.

Top

C. Submission Schedule

Submissions (including all required materials) must meet established deadlines (available from the Commission staff) in order to qualify for Commission review at a scheduled monthly meeting.

Top

D. District of Columbia Projects in the Central Area

As noted in Sections 4.A.2&3, if the proposed development is a District of Columbia public building within the central area, the Commission is responsible for environmental documentation and compliance with Section 106 where applicable. Where the Executive Director has determined that Commission action requires an EIS, the NEPA process must be completed prior to the initial action.

If a Section 106 review is required, initial action will normally be scheduled immediately after the Executive Director initiates the process, unless, because of potential impacts on recognized historic resources, the views of the District of Columbia SHPO or the District of Columbia Historic Preservation Review Board are required. Compliance with Section 106 must be completed prior to Commission action on final site and building plans.

Top

E. Coordinating Committee

Pursuant to Section 2(d) of the Planning Act, submissions for proposed projects located in, or adjacent to, the District of Columbia will be referred by the Commission staff to the Coordinating Committee to ensure coordination with interested and affected District of Columbia and Federal agencies.

Top

F. Referral

Upon receipt of location and program and schematic development or preliminary plan submissions for projects on sites not covered by a master plan and not subject to review by the Commission's Coordinating Committee, the Commission will refer the submissions to affected local planning agencies and regional and state clearinghouses for review and comment. Such submissions are also referred by the regional clearinghouse (COG) to designated intergovernmental review officials of affected jurisdictions for review and comment.

Top

G. Resolution of Planning Issues

As planning issues are raised by the Coordinating Committee or from the referral process, the Commission staff, in conjunction with the COG staff, will work with affected local, regional, or state agencies and the sponsoring agency to resolve such issues.

Top

H. Review Evaluation and Recommendation of the Commission Staff

Following receipt of comments from other organizations and the Coordinating Committee, the staff will prepare recommendations for Commission action. Staff recommendations will normally be provided to the Commission and made available to the sponsoring agency and general public approximately one week in advance of scheduled Commission meetings. In the event unresolved issues delay staff recommendations, the staff will inform the sponsoring agency of the steps to be taken to resolve outstanding concerns.

Top

I. Public Notice and Participation

In accordance with the Commission's Revised Procedures for Public Participation, organizations in the vicinity of a project site will be mailed a notice of "Tentative Agenda Items" indicating a tentative schedule for Commission review of the proposals described. Organizations or individuals may submit written comments for consideration by the Executive Director in preparing staff recommendations. In addition, organizations or individuals may register to appear before the Commission to comment on project submissions and/or staff recommendations.

Top

J. Action of the Commission

The Commission reviews project submissions at scheduled meetings. The Commission staff will notify the sponsoring agency of the schedule for review and any requirements concerning its participation in the presentation to the Commission.

Top

K. Official Notification of Commission Action

A letter notifying the sponsoring agency of Commission action on its project submission will immediately follow such action.

Top

Section 6 - Time Period For Review

Submissions requiring referral to local, regional, and state agencies will normally require a 90-day review period, of which 60 days will be devoted to review by agencies receiving-the referral. Under special circumstances, a sponsoring agency may request a waiver of up to 30 days of this review period from the Executive Director. Project submissions for sites not requiring referral are subject to a review period of approximately 30 days.

Top

Section 7 - Delegation of Authority to Executive Director

In the following circumstances, authority may be delegated to the Executive Director:

A. For federal projects on sites in the environs for which the Commission has submitted to the agency its reports and recommendations on the master plan or for projects in the District of Columbia for which the Commission has, where appropriate, an approved master plan, and which are not located on the Mall Complex, the Executive Director may approve preliminary and final site and building plans for proposed buildings or additions of less than 50,000 square feet of floor area, if the Executive Director determines that:

  1. The proposed development is consistent with the recommendations of the Commission on the land use and circulation plan elements of the master plan.
  2. The proposed development will have no significant adverse impact on the environment, cultural and historic resources, and access and egress to facilities and utilities.
  3. The proposed development is compatible with existing and proposed developments in its immediate vicinity.
  4. The addition or relocation of employees to the proposed development will not cause an adverse impact.

B. The Executive Director may approve preliminary and final site and building plans for District of Columbia projects in the Central Area that have less than 50,000 square feet of floor area, if the Executive Director determines that:

  1. The proposed development will have no significant adverse impact on the environment, cultural and historic resources, and access and egress to facilities and utilities.
  2. The proposed development is compatible with existing and proposed developments in the immediate vicinity.
  3. The addition or relocation of employees to the proposed development will not cause an adverse impact.

C. The Executive Director may approve or comment on, as appropriate, site development projects that do not include buildings when the projects are not inconsistent with a master plan that has been approved or reported on by the Commission. This delegation does not include memorials or projects on the Mall Complex.

D. The Executive Director may comment on District of Columbia projects outside of the central area that do not affect federal interests.

E. The Executive Director may take responsibility for the scope and content of environmental documents prepared for Commission action by:

  1. Determining whether to prepare an Environmental Impact Statement (EIS) or to make a Finding of No Significant Impact (FONSI).
  2. Obtaining the information required for the preparation of a draft EIS or an Environmental Assessment (EA).
  3. Preparing a draft EIS.
  4. Circulating a draft EIS for review and comment to EPA, affected and interested public agencies, and the general public.
  5. Integrating agency and public comments, where appropriate, and preparing for the final EIS.
  6. Distributing the final EIS to EPA and all agencies and individuals who commented on the draft EIS.
  7. Determining the appropriate environmental documentation for each phase of Commission review of federal and federally assisted projects. The Executive Director must require completed environmental documentation for all final project approvals.

F. The Executive Director may comment to the Council of the District of Columbia on street closings outside the L’Enfant City where the proposed closing: would not affect a federal interest; is consistent with the Comprehensive Plan; and would not have an adverse impact on major historic or natural features.

G. The Executive Director may comment to the Council of the District of Columbia on alley closings where the proposed closing would not be inconsistent with the Comprehensive Plan and would not have an adverse impact on a federal interest.

H. The Executive Director may report directly to the Zoning Commission on all zoning referrals determined to have no federal interest or minimal adverse impacts.

I. The Executive Director may approve receive-only antennas that are:

  1. Located on a reservation or site for which the Commission has submitted its report and recommendations on a current master plan.
  2. Not inconsistent with the recommendations of the Commission on the land use and circulation plan elements of the master plan or its action on final project plans.
  3. Determined by the Executive Director to have no adverse impact on the environment, no adverse visual impact on properties beyond the boundaries of the federal reservation or site, and meet the general criteria of the Guidelines and Submission requirements.

J. The Executive Director may consult with appropriate state and local planning agencies, and comment on local and state plans where there is no adverse impact on identified federal interests, capital programs, and other state and local activities that are voluntarily submitted to the Commission for review.

K. The Executive Director may advise and consult with appropriate planning agencies having jurisdiction over the affected part of the environs with respect to general plans for proposed federal and District developments and projects within the environs.

L. The Executive Director, with regard to matters under the Pennsylvania Avenue Plan, may be responsible for:

  1. Determining whether a project conforms with the Pennsylvania Avenue Plan and making appropriate recommendations to the General Services Administration.
  2. Reviewing requests for building permits and certifying appropriate requests to the D.C. government.

M. The Executive Director may review all prospectuses involving only the leasing of privately owned space in the region by a federal agency or department to identify if any appear to be inconsistent with the Comprehensive Plan and other Commission policies. This delegation does not extend to all prospectuses which:

  1. Are determined by the Executive Director to be inconsistent with Commission policies and which contain proposals that involve 100,000 or more occupiable square feet of floor area in a single building.
  2. Are located outside of an established Major Federal Employment Area and would accommodate more than 150 employees.
  3. Would exceed the targeted federal employment levels established for Major Federal Employment Areas by more than five percent.

N. The Executive Director may execute agreements with state officials as to the arrangements for acquisition by the Commission of lands in Maryland and Virginia for the National Capital park, parkway, and playground system and agreements with State officials over the control of such lands.

O. The Executive Director may determine appropriate federal and District of Columbia authorities to whom federal elements of the Comprehensive Plan, or amendments thereto, shall be presented for comments and recommendations prior to adoption thereof.

Note: The Mall Complex is defined as the portion of the Monumental Core east of the Potomac River that includes the Mall (area bounded by Constitution and Independence Avenues and First and 14th Street, NW and SW), the Ellipse, the Washington Monument Grounds, West Potomac Park, the Jefferson Memorial Grounds, and the Capitol Grounds.

Note 1. The Region includes the District of Columbia; Montgomery and Prince George's Counties in Maryland; Arlington, Fairfax, Loudoun and Prince William Counties in Virginia; and all cities that exist or may come to exist in Maryland and Virginia within the geographic area bounded by the outer boundaries of the combined area of said counties. (Return to 1A)

Note 2. Section 5(b) of the Planning Act generally exempts projects within the U.S. Capitol grounds or structures erected by the Department of Defense during wartime or national emergency within existing military, naval, or Air Force reservations. In the latter case, the affected Defense agency should consult with the Commission if off-site effects are anticipated. (Return to 1A)

Note 3. Submission requirements for the installation of antennas on Federal sites are covered in the Commission's Guidelines and Submission Requirements for Antennas on Federal Property, in the National Capital Region. (Return to 1B)

Top