Unit |
Power |
Down |
Reason or Comment |
Change in report (*) |
Number of Scrams (#) |
Braidwood 1 |
100 |
|
|
|
|
Braidwood 2 |
100 |
|
|
|
|
Byron 1 |
100 |
|
|
|
|
Byron 2 |
79 |
|
COASTDOWN TO REFUELING OUTAGE. REDUCED POWER FOR PLANNED TESTING |
* |
|
Clinton |
97 |
|
100% ELECTRICAL CAPABILITY |
|
|
D.C. Cook 1 |
100 |
|
|
|
|
D.C. Cook 2 |
100 |
|
|
|
|
Davis-Besse |
100 |
|
|
* |
|
Dresden 2 |
99 |
|
100% ELECTRICAL CAPABILITY |
* |
|
Dresden 3 |
99 |
|
100% ELECTRICAL CAPABILITY |
|
|
Duane Arnold |
98 |
|
100% ELECTRICAL CAPABILITY |
|
|
Fermi 2 |
100 |
|
MAINTENANCE OFFSITE AFFECTING BROWNSTOWN 2 LINE UNTIL 3/29/07 |
|
|
Kewaunee |
99 |
|
|
|
|
La Salle 1 |
100 |
|
|
|
|
La Salle 2 |
100 |
|
|
|
|
Monticello |
0 |
03/13/2007 |
REFUELING OUTAGE |
|
|
Palisades |
100 |
|
|
* |
|
Perry 1 |
95 |
|
COASTDOWN TO REFUELING OUTAGE |
|
|
Point Beach 1 |
100 |
|
|
|
|
Point Beach 2 |
100 |
|
|
|
|
Prairie Island 1 |
100 |
|
345 KV OFFSITE PWR LINE OOS UNTIL 1ST WEEK IN MAY |
|
|
Prairie Island 2 |
100 |
|
345 KV OFFSITE PWR LINE OOS UNTIL 1ST WEEK IN MAY |
|
|
Quad Cities 1 |
86 |
|
COASTDOWN TO REFUELING OUTAGE |
* |
|
Quad Cities 2 |
96 |
|
100% ELECTRICAL CAPABILITY |
|
|