Index | Site Map | FAQ | Facility Info | Reading Rm | New | Help | Glossary | Contact Us |
EA-97-518 - Baxter Healthcare CorporationOctober 9, 1998 EA 97-518
Dear Mr. Betancourt: This refers to a Nuclear Regulatory Commission (NRC) inspection conducted on August 19, 1998, at your facility in Aibonito, Puerto Rico. The purposes of the inspection were to determine whether activities were conducted safely and in accordance with regulatory requirements and to followup on a July 31, 1998, operational event at the facility involving a fatality. The results of the inspection were discussed with you on September 16, 1998. The enclosed report presents the results of the inspection. Based on the results of this inspection, the NRC identified that a violation of regulatory requirements occurred. The violation involved a failure to adhere to the requirements of 10 CFR 36.31(a), which requires that the lock for the source control of a panoramic irradiator be designed so that the key may not be removed if the sources are in an unshielded position. The NRC inspection identified that between November 19 and 25, 1996, Baxter operated the irradiator with a lock for the source control that allowed the key to be removed with the sources in an unshielded position. The inspection revealed that individuals at Baxter were apparently aware that the design of the replacement source control switch permitted the key to be removed while the sources were in the unshielded position. In addition, based on discussions with the inspector, these same individuals knew, or should have known, that NRC regulations at 10 CFR 36.31 specifically prohibit this condition because the individuals contacted the irradiator manufacturer and took measures to compensate for the lack of a properly functioning switch. Notwithstanding this knowledge, these individuals allowed the irradiator to be operated in noncompliance with 10 CFR 36.31. During this time, Baxter did institute compensatory measures recommended by the irradiator manufacturer; however, those measures were not a substitute for compliance with NRC requirements. The NRC is citing the above violation and amending and reissuing the Notice of Violation and Proposed Imposition of Civil Penalties (Notice) originally issued to Baxter on May 14, 1998. As discussed in the enclosed inspection report, this violation is directly related to Violation I.B. of the May 14, 1998 Notice, which was associated with the unauthorized replacement of the lock for the irradiator source control on November 19 and 25, 1996. At the time that the original Notice was issued, the NRC was unaware that the replacement lock was a different design, and that this design allowed the key to be removed with the sources in an unshielded position, resulting in a violation of 10 CFR 36.31(a). This new violation is included in Section I.B. of the amended Notice as Violation I.B.(2). The civil penalty assessed for the violations cited in Section I.B. of the amended Notice remains the same as in the original Notice, $5,500. In its letters dated July 8 and 15, 1998, Baxter provided responses to the May 14, 1998 Notice. Baxter is hereby required to respond to Violation I.B.(2) of the enclosed amended Notice. You may also supplement or amend any portion of your previous responses in order to take into account this new violation, or for any other reason. You should follow the instructions specified in the enclosed amended Notice when preparing your response. In your response, you should document the specific actions taken and any additional actions you plan to prevent recurrence of Violation I.B.(2). In addition to the enclosed amended Notice of Violation and Proposed Imposition of Civil Penalties, the NRC is issuing a Demand for Information (Demand) because, as discussed above, Baxter employees were apparently aware that the design of the replacement source control switch permitted the key to be removed while the sources were in the unshielded position; and they apparently also knew, or should have known, that 10 CFR 36.31 specifically prohibits this condition. Therefore, in addition to the response required above, further information is needed to determine whether the Commission can have reasonable assurance that Baxter will, in the future, conduct NRC- licensed activities in compliance with NRC requirements. Accordingly, pursuant to sections 81, 161c, 161o, 182 and 186 of the Atomic Energy Act of 1954, as amended, and the Commission's regulations in 10 CFR 2.204 and 10 CFR 30.32(b), in order to determine whether your license should be modified, suspended or revoked, or other enforcement action taken to ensure compliance with NRC requirements, Baxter is hereby required to submit to the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852-2738, within 30 days of the date of this Demand, with a copy to the Regional Administrator, U.S. Nuclear Regulatory Commission, Region II, the following information, in writing and under oath or affirmation:
You may provide any other information you deem appropriate, including an assessment of whether the facts related to this issue as documented in Inspection Report 52-21175-01/98-02 are correct. The NRC's evaluation of your responses of July 8 and 15, 1998, is ongoing. After we review the responses required by the enclosed amended Notice and the Demand, the NRC will inform you of our decision as to whether additional Agency action will be taken with regard to these violations. In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter, its enclosures, and any response will be placed in the Public Document Room (PDR). To the extent possible, your response should not include any personal privacy, proprietary, or safeguards information so that it can be placed in the PDR without redaction. If you have any questions regarding this letter, please contact Douglas M. Collins, Director, Division of Nuclear Materials Safety at (404) 562-4700.
Docket Nos: 030-19882
AMENDED NOTICE OF VIOLATION
During NRC inspections conducted on October 29, 1996, April 2, 1997, and August 19, 1998, and an investigation completed on November 19, 1997, violations of NRC requirements were identified. In accordance with the "General Statement of Policy and Procedures for NRC Enforcement Actions," NUREG-1600, the NRC proposes to impose civil penalties pursuant to Section 234 of the Atomic Energy Act of 1954, as amended (Act), 42 U.S.C. 2282, and 10 CFR 2.205. The particular violations and associated civil penalties are set forth below:
Pursuant to the provisions of 10 CFR 2.201, Baxter Healthcare Corporation of Puerto Rico (Licensee) is hereby required to submit a written statement or explanation to the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, within 30 days of the date of this Amended Notice of Violation and Proposed Imposition of Civil Penalties (Notice) for Violation I.B.(2) only. The Licensee has already responded to the remaining violations in its letters dated July 8 and 15, 1998. However, the Licensee may amend its responses or provide any additional information at this time, and may address the aggregation of Violations I.B.(1) and I.B.(2) if it chooses to do so. This reply should be clearly marked as a "Reply to a Notice of Violation" and should include, for Violation I.B.(2): (1) admission or denial of the alleged violation, (2) the reasons for the violation if admitted, and if denied, the reasons why, (3) the corrective steps that have been taken and the results achieved, (4) the corrective steps that will be taken to avoid further violations, and (5) the date when full compliance will be achieved. If an adequate reply is not received within the time specified in this Notice, an order or a Demand for Information may be issued as why the license should not be modified, suspended, or revoked or why such other action as may be proper should not be taken. Consideration may be given to extending the response time for good cause shown. Under the authority of Section 182 of the Act, 42 U.S.C. 2232, this response shall be submitted under oath or affirmation. Although the licensee's responses of July 8 and 15, 1998, protested the
civil penalties proposed in the NRC's May 14, 1998 Notice, the Licensee
may pay the civil penalties at this time if it chooses to do so; or the
Licensee may await NRC's determination concerning this matter, including
the Licensee's response to Violation I.B.(2) and any other information
that the Licensee chooses to submit. If the Licensee chooses to pay the
civil penalties at this time, payment should be made within 30 days by
letter addressed to the Director, Office of Enforcement, U.S. Nuclear
Regulatory Commission, with a check, draft, money order, or electronic
transfer payable to the Treasurer of the United States in the amount of
the civil penalties proposed above. The Licensee may, if it chooses, submit
a further response protesting the imposition of the civil penalties in
whole or in part, by a written answer addressed to the Director, Office
of Enforcement, U.S. Nuclear Regulatory Commission. Should the Licensee
fail to answer within the time specified, the NRC will proceed with its
review on the basis of the information available to date. Should the Licensee
elect to file an answer in accordance with 10 CFR 2.205 protesting the
civil penalties, in whole or in part, such answer should be clearly marked
as an "Answer to a Notice of Violation" and may: (1) deny the violation(s)
listed in this Notice, in whole or in part, (2) demonstrate extenuating
circumstances, (3) show error in this Notice, or (4) show other reasons
why the penalties should not be imposed. In addition to protesting the
civil penalties in whole or in part, such answer may request remission
or mitigation of the penalties. Upon failure to pay any civil penalties due which subsequently have been determined in accordance with the applicable provisions of 10 CFR 2.205, this matter may be referred to the Attorney General, and the penalties, unless compromised, remitted, or mitigated, may be collected by civil action pursuant to Section 234c of the Act, 42 U.S.C. 2282c. The responses noted above (Reply to Notice of Violation, letter with payment of civil penalties, and Answer to a Notice of Violation) should be addressed to: Mr. James Lieberman, Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, One White Flint North, 11555 Rockville Pike, Rockville, MD 20852-2738, with a copy to the Regional Administrator, U.S. Nuclear Regulatory Commission, Region II. Because your response will be placed in the NRC Public Document Room (PDR), to the extent possible, it should not include any personal privacy, proprietary, or safeguards information so that it can be placed in the PDR without redaction. If personal privacy or proprietary information is necessary to provide an acceptable response, then please provide a bracketed copy of your response that identifies the information that should be protected and a redacted copy of your response that deletes such information. If you request withholding of such material, you must specifically identify the portions of your response that you seek to have withheld and provide in detail the bases for your claim of withholding (e.g., explain why the disclosure of information will create an unwarranted invasion of personal privacy or provide the information required by 10 CFR 2.790(b) to support a request for withholding confidential commercial or financial information). If safeguards information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Dated at Atlanta, Georgia 1. "General Statement of Policy and Procedures for NRC Enforcement Actions," NUREG-1600.
|