Pipeline Accident Report

Enbridge Incorporated Hazardous Liquid Pipeline Rupture and Release

Marshall, Michigan
July 25, 2010

NTSB Number: PAR-12-01
NTIS Number: PB2012-916501
Adopted: July 10, 2012
PDF

Executive Summary

On Sunday, July 25, 2010, at 5:58 p.m., eastern daylight time, a segment of a 30-inch-diameter pipeline (Line 6B), owned and operated by Enbridge Incorporated (Enbridge) ruptured in a wetland in Marshall, Michigan. The rupture occurred during the last stages of a planned shutdown and was not discovered or addressed for over 17 hours. During the time lapse, Enbridge twice pumped additional oil (81 percent of the total release) into Line 6B during two startups; the total release was estimated to be 843,444 gallons of crude oil. The oil saturated the surrounding wetlands and flowed into the Talmadge Creek and the Kalamazoo River. Local residents self-evacuated from their houses, and the environment was negatively affected. Cleanup efforts continue as of the adoption date of this report, with continuing costs exceeding $767 million. About 320 people reported symptoms consistent with crude oil exposure. No fatalities were reported.

Probable Cause

The National Transportation Safety Board (NTSB) determines that the probable cause of the pipeline rupture was corrosion fatigue cracks that grew and coalesced from crack and corrosion defects under disbonded polyethylene tape coating, producing a substantial crude oil release that went undetected by the control center for over 17 hours. The rupture and prolonged release were made possible by pervasive organizational failures at Enbridge Incorporated (Enbridge) that included the following:

Contributing to the accident was the Pipeline and Hazardous Materials Safety Administration's (PHMSA) weak regulation for assessing and repairing crack indications, as well as PHMSA's ineffective oversight of pipeline integrity management programs, control center procedures, and public awareness.

Contributing to the severity of the environmental consequences were (1) Enbridge's failure to identify and ensure the availability of well-trained emergency responders with sufficient response resources, (2) PHMSA's lack of regulatory guidance for pipeline facility response planning, and (3) PHMSA's limited oversight of pipeline emergency preparedness that led to the approval of a deficient facility response plan.

Safety issues identified during this accident investigation include the following:

As a result of this investigation, the NTSB makes safety recommendations to the U.S. Secretary of Transportation, PHMSA, Enbridge, the American Petroleum Institute, the Pipeline Research Council International, the International Association of Fire Chiefs, and the National Emergency Number Association. The NTSB also reiterates a previous recommendation to PHMSA.

Recommendations

New Recommendations

To the U.S. Secretary of Transportation:

Audit the Pipeline and Hazardous Materials Safety Administration's onshore pipeline facility response plan program's business practices, including reviews of response plans and drill programs, and take appropriate action to correct deficiencies. (P-12-1)

Allocate sufficient resources as necessary to ensure that the Pipeline and Hazardous Materials Safety Administration's onshore pipeline facility response plan program meets all of the requirements of the Oil Pollution Act of 1990. (P-12-2)

To the Pipeline and Hazardous Materials Safety Administration:

Revise Title 49 Code of Federal Regulations 195.452 to clearly state (1) when an engineering assessment of crack defects, including environmentally assisted cracks, must be performed; (2) the acceptable methods for performing these engineering assessments, including the assessment of cracks coinciding with corrosion with a safety factor that considers the uncertainties associated with sizing of crack defects; (3) criteria for determining when a probable crack defect in a pipeline segment must be excavated and time limits for completing those excavations; (4) pressure restriction limits for crack defects that are not excavated by the required date; and (5) acceptable methods for determining crack growth for any cracks allowed to remain in the pipe, including growth caused by fatigue, corrosion fatigue, or stress corrosion cracking as applicable. (P-12-3)

Revise Title 49 Code of Federal Regulations 195.452(h)(2), the "discovery of condition," to require, in cases where a determination about pipeline threats has not been obtained within 180 days following the date of inspection, that pipeline operators notify the Pipeline and Hazardous Materials Safety Administration and provide an expected date when adequate information will become available. (P-12-4)

Conduct a comprehensive inspection of Enbridge Incorporated's integrity management program after it is revised in accordance with Safety Recommendation P-12-11. (P-12-5)

Issue an advisory bulletin to all hazardous liquid and natural gas pipeline operators describing the circumstances of the accident in Marshall, Michigan—including the deficiencies observed in Enbridge Incorporated's integrity management program—and ask them to take appropriate action to eliminate similar deficiencies. (P-12-6)

Provide additional training to first responders to ensure that they (1) are aware of the best response practices and the potential consequences of oil releases and (2) receive practical training in the use of appropriate oil-containment and -recovery methods for all potential environmental conditions in the response zones. (P-12-14)

Review and update your oil pipeline emergency response procedures and equipment resources to ensure that appropriate containment equipment and methods are available to respond to all environments and at all locations along the pipeline to minimize the spread of oil from a pipeline rupture. (P-12-15)

Update your facility response plan to identify adequate resources to respond to and mitigate a worst-case discharge for all weather conditions and for all your pipeline locations before the required resubmittal in 2015. (P-12-16)

To the American Petroleum Institute:

Facilitate the development of a safety management system standard specific to the pipeline industry that is similar in scope to your Recommended Practice 750, Management of Process Hazards. The development should follow established American National Standards Institute requirements for standard development. (P-12-17)

To the Pipeline Research Council International:

Conduct a review of various in-line inspection tools and technologies—including, but not limited to, tool tolerance, the probability of detection, and the probability of identification—and provide a model with detailed step-by-step procedures to pipeline operators for evaluating the effect of interacting corrosion and crack threats on the integrity of pipelines. (P-12-18)

To the International Association of Fire Chiefs and the National Emergency Number Association:

Inform your members about the circumstances of the Marshall, Michigan, pipeline accident and urge your members to aggressively and diligently gather from pipeline operators system-specific information about the pipeline systems in their communities and jurisdictions. (P-12-19)

Reiterated Recommendation

As a result of this accident investigation, the National Transportation Safety Board reiterates the following previously issued safety recommendation:

Require operators of natural gas transmission and distribution pipelines and hazardous liquid pipelines to provide system-specific information about their pipeline systems to the emergency response agencies of the communities and jurisdictions in which those pipelines are located. This information should include pipe diameter, operating pressure, product transported, and potential impact radius. (P-11-8)