Fermi National Laboratory
 

Fermilab Shutdown Report for June 29, 2009 - July 10, 2009

 

Fermilab Shutdown Report

6/29/09 – 7/10/09

LINAC

Shutdown Weeks 3 & 4

  • No Neutron Therapy Facility operations last two weeks. Expected return of NTF operations on week of 27th of July
  • Column ceramics resurfacing completed Electrodes are in. Continued refurbishing of ion source in progress
  • 480V panel breaker/Wiring replacement on Low Energy (LE) stations 4 & 5 & test station 7 completed
  • Quadrupole power supply Card upgrade completed.
  • Power strip replacement on all LE stations completed
  • Continued LE and High Energy (HE) RF station cleaning and component maintenance
  • Klystron RF station 8 and LRF7 operations for MTA tests took place
  • Opened tank 5 for DT20 replacement.
  • DT20 has been replaced and rough alignment is in progress
  • General vacuum maintenance in progress on vacuum pumps. LE ion pumps showing signs of needing to be replaced
  • NTF vacuum pump and valve will be replaced
  • Trying to locate and repair vacuum leaks in LE tanks 1-3
  • H- Dome and Pit cleaning in progress

Booster

Shutdown Weeks 3 & 4

  • Correction element upgrade ~80% with magnet removal/installation
    • 30 out of 36 magnets installed. 28 Surveyed
    • Booster Period 11-23 under vacuum.
    • Booster Period 24-2, 7-10 should be under vacuum at end of the day.
    • Old correctors in period 3-6 (6 magnets) still in place and under vacuum. Will pull in about two weeks.
    • 50% of corrector wire pulls completed. Will finish next week.
    • Cable termination and connections in progress
  • New Magnet Cooling Manifold installed at Long 14.
  • RF Cavity 14 tuner repair completed. Will pulse test today.
  • East Gallery LCW Cooling pipe upgrade 95% completed. Pressure test overnight with nitrogen.
  • GMPS upgrade ~60% complete
  • Making Wiring connections on switchgear and Transformers
  • Work on GMPS 1 & 2 also in progress

New Sink Hole patched

  • Sump Discharge sinkhole formed last weekend in East Booster Lot. (Found on Monday 4/6). Repairs made yesterday. Need to pressure test today
  • Will also look at ICW valve leak in east Booster Lot

Antiproton Source

Accumulator 4-8GHz DP Kicker Upgrade: ~50% complete

  • All beam line components are in place and final alignment is done. Pump down & leak check underway today. The A50-A60 bake will follow next week when baking system modifications are done. A40 bake is complete

Debuncher Septum Magnet Replacement: 50% complete

  • Old magnet removed and inspected. Fatigue crack in braze joint was the cause of our problems. New magnet is in place awaiting final alignment

IB7 (AP2 dipole magnet) Replacement: 5% complete

  • For ALARA reasons, this work will begin in August. As-found position survey was done this week

Other Work

  • Maintenance work on various RF systems continues
  • LCW leaks being addressed
  • Replacement of old drive couplings for movable stands to prevent failures
  • Alignment of tanks today (?)
  • Sump pumps in Transport enclosure replaced
  • Rad survey of rings/beam lines and inductance measurements of magnets
  • Power supply maintenance – LCW hoses, filter capacitors, etc.
  • Lithium lens 10mm-2 LCW leak repairs
  • Remote LCW filling system for lens
  • Target SEM work continues

Main Injector

MI10 area: On Schedule

  • Civil construction progressing
  • Tunnel boring: 5 of 18 holes completed

MI40 area: On Schedule

  • All holes cut
  • Conduit supports installed
  • Eight conduits installed and grouted

Instrumentation: On Schedule

RF: On Schedule

  • Working upstairs. This week: maintenance on modulators

PS: On Schedule

LCW: On Schedule

  • Cleaning up old hose, aligning LCW pumps, maintaining 3-way valves etc.

MI-40 Kickers On Schedule

  • Abort kickers moved, new beam valve installed, installing new kicker stands

MI-8 multiwires, MI-52 e cloud, collimator masks: all on schedule for work beginning later in the shutdown.

Recycler

Recycler

  • Pot RR129 (i.e. MI-10 injection kicker)
    • Not started
  • Move 6 magnets (80% complete)
    • 5 magnets have been moved
      • Last one today
  • HLS installation at MI-10 (possibly)
    • ALARA planning in progress
  • Vacuum maintenance
    • Not started
    • Key vacuum tech unavailable for 3-4 weeks
      • May limit the extent of the work done
  • Power supplies maintenance
    • VDPA1 & VDPA2 maintenance (75% complete)
    • Correctors (not started)

Electron Cooling

  • Pelletron maintenance (20% complete)
    • Chains (2), sheaves (4) have been removed
  • Flush Water/Glycol skid (and magnets) (10-15% complete)
    • Water lines have been flushed
    • One magnet (out of 3) has been flushed
      • Recovered nominal flow
  • NMR probe replacement (50% complete)
    • Probes in the 45 bend magnets have been replaced
      • Recovered nominal operation
    • One (out of two) probe in the 90 bend magnets has been replaced
      • Tuning in these magnets is tricky (and can take a lot of time)
  • Recycler Pump Out
    • Vented regions show stable vacuum/pressure
    • Looks like the MI-40 region could be pumped out late next week or early the following week
      • Depends on progress of the work installing conduits, etc…

Tevatron

Six House to Fix: A3, E3, D3, A1, D1, and E1

Other Items

  • Unroll TeV magnet 50% complete
  • TeV RF water leaks Fix leak on RF 5 this week RF 2 later
  • Horizontal Crystal collimator installed at E-0
  • Repairing HLS systems around Tevatron
  • Realign A side low beta quads Mid August
  • Realign D0 low beta?

CDF had a change in elevation due to its detector sinking.

NuMI

Shutdown Weeks 3 & 4

  • Modify Horn Power Supply for Anti-Neutrino Mode
  • Install & Test Transport Rail System in Target Hall
    • Install New 480 Electrical Service
    • Install Controls System
    • Complete Dry Run with Horn Coffin
  • Replace Target Pile Bypass Air System Damper
  • Replace & Shield Target Pile Humidity Monitors
  • Complete Investigation of Horn 2 Water Leak-Identified a Water Leak from the EVAC Seal between the Horn and Bellows to the Water Tank
    • Completed and As-found Survey of Horn 2
    • Developed Seal Repair Procedure & ALARA Plan
    • Practice Seal Replacement Procedure
    • Drain and Remove Horn 2 Water Lines
  • As-found survey completed of the Pre-Target and Target Hall
  • Removed Electrical Hardware and Freon for Rowald Chiller and ship to storage
  • Complete Preventative Maintenance on T-Hall and Decay Pipe Dehumidification Systems
  • Start Mobilization for Hadron Monitor Replacement
  • Absorber Hall Dehumidification System 85% Complete
    • Waiting For Pumps & Heat Exchanger
    • Controls Installation In Process
  • EPB Dipoles PEEK Installation Continues
    • HV101-1 & 101-2 Install Complete, Survey Needed
    • 101-6 PEEK installation started
    • Bore Scope of HV101 Line Found Nothing
  • Profile Monitor Replacement Started on PM101 &PM105
    • Stands in Place, PM101 Installed By End of Day Today

Alignment

Tevatron – 59% completed

Main Injector – 35% completed

Booster – 70% completed

Pbar – 70% completed

Recycler – 67% completed

Switchyard – 50 % completed

NuMI – 47% completed

Linac – 0$ completed

FESS– 0% completed

D0 – 60% completed

CDF – 100% completed

400 MeV Area – 0% completed

MTA – 0% completed

Cryogenic System
TeV at LN2 Temperatures

  • Continued support AD/MSD for A3 & D3 repairs; E3 warming up to room temperature
  • FRIG A2 low-pressure heat exchanger helium-air leak found; weld crack repairs planned
  • Planned power outages went well except for some controls issues resolved by AD/Controls
  • Continued ringwide vacuum pump maintenance, repairs, and pumpdown of various components to assure stable Tevatron LN2 Mode Operations
  • 8 wet engine flywheels replaced, 4/5 wet engine motors replaced, 12/24 wet engine overhauled, 4/6 IHI cold compressors replaced
  • Mycom Compr Benshaw starter modifications, 7/8 (TEV) completed
  • Mycom Compr relief valves replaced (1/8)
  • Ongoing numerous FRIG/Compr controls/instrumentation maintenance/repairs
  • CHL at room temperature for maintenance (equip greasing/oil changes, NRL Niagara aftercooler cleaning-50% done, relief valves inspection/testing, instr. repairs, NRL R22 precooler condenser fixed. Liquid nitrogen supply to Tevatron relying on Linde deliveries (~3 per day) to CHL’s 150,000 gallons of tank storage

Controls

Completed:

  • AD General Network Switch Upgrade
  • New AD firewalls in place
  • UPS Maintenance - Network & TLG
  • S/R and SDA Database Firmware, OS & Sybase S/W Updates
  • General Maintenance

Upcoming Week:

  • BSSB Update & TLG reboot (Tuesday)
  • Java Engine S/W Updates (Tuesday)
  • Application & Device Database Firmware, OS & Sybase S/W updates (Wednesday & Thursday)
  • Maintenance as necessary

MTA

Roll-up Shield Door

  • Electrical cable pull, top of berm complete
  • Shield wall outside of roll-up door complete

Hatch Shielding

  • Started 7/02/09
  • Anticipated completion 7/15/09

Permanent Magnet Construction and Installation

  • PM parts ready for VB01 replacement
  • Construction waiting for Linac technicians
  • Construction area undecided, requires crane
  • No “parasitic” beam without PM.

FESS

Electrical and High Voltage

  • MSS-Buss Duct Work and Relay Testing-ahead of schedule-to be energized next week
  • 345kv-relief system testing
  • TeV Ring-Service Building HV/Electrical Pm’s-A thru F3 completed per schedule
  • TEV-EO [B] faulted feeder replaced to pond pump pit transformer
  • MI-MI12 SD & switch replacement [4 bay S&C]
  • TEV-lighting re-lamp WIP on 4-12 pm shift
  • Linac-Lighting replacement started
  • CDF/BO-VFD for LCW Pumps failure [pump sizing in question]
  • CHL-FDR 38 power outage work, complete
  • No major findings to date

Mechanical

  • APT40-both sumps replaced
  • TEV-Tunnel Supply fans/systems PM
  • Pond-Pond Pump PM & repack
  • MI-Make-up Air Units to tunnel PM
  • MI-MI10 Sump replaced

HVAC

  • MI-dehumidifiers PM
  • Minor findings found on condenser fans/dehumidifier relays/controls

CUB

  • Klystron cooling switched to Comfort Chilled Water System (Chillers1, 5, &HX2) due to 55LCW pumps/system scheduled shutdown
  • #3 Chiller-Setting up condenser cleaning work to be completed next week with Eagle Services (New Contractor)
  • HE9 plate frame heat exchanger-scheduled for cleaning next week by Eagle Services
  • #4 Chiller-on schedule for cleaning later next week
  • Additional chemical cleanings have been required due to calcium deposits & longer run period from last shut down (2007)
  • 55 LCW LP4 & 5-VFD Drive Replacements, now through 7/17
  • Cooling Tower piping repairs to HE1 (Booster) and HE9 (Pbar) scheduled for 7/13, 7/14 & 15
  • CUB Shut Down set for 7/25 -FDR 42- Electrical/ HV & Sunday 7/26-mechanical maintenance to include inspection of tower water tank (Fdr 40 PM for Linac/X Gallery)

Other Work and Comments

  • BTE new sink hole in parking lot-break in BGE Sump discharge line common to recent Break under BTE Transformer YBE1A.
  • BTE –ICW leak in same area as sump discharge line leak
  • ICW water main repair-the section of 14” line @Roads A1/A2 being replaced with a 12’ HDPE line by directional boring (in progress)
  • Zebra Mussel status-minimal infestation findings in MI and TeV Ponds/Intakes
  • ICW Site Wide Flush-mobilization & tentative start on 8/1 & 8/3 thru 8/6
  • Zebra Mussel Treatment Site Wide-Friday AM 8/7 to Sat AM (24 hrs)
  • Casey’s Pond Shut Down- Tentative schedule for Sat 7/25 for 8-10 hrs to inspect/clean ICW sump with Divers-ICW valve configuration to start @ 6AM to provide FCC ICW from C-4 Pump House

Safety

Safety

  • MuCool Test Area (MTA) crane work should be complete this week
  • Aside from the unexpected NuMI horn water leak location, shutdown tasks are progressing as planned
  • Thanks to Pbar for patiently waiting for coverage as we address other areas

Interlock Work

  • Oxygen cell replacements
    • Complete
  • Safety System Interface Unit capacitor replacements
    • Complete
  • Single Line Electrical Drawing Verifications
    • 20% complete
  • Tevatron ground fault diagnostics installation
    • 15% complete
  • Misc. Tevatron Interlock repairs
    • 50% complete
  • Safety System Testing
    • Not started

Shutdown Safety

  • Injuries
    • None to report since last meeting
  • Construction Areas
    • Any access must be coordinated through the Construction Coordinator
    • Must comply with construction HA and all PPE requirements Construction attire, work boots, hardhat, and safety glasses
  • Remind work crews to use PPE
    • Gloves, safety glasses, and bump caps available from the ESH Department
  • Continue to stress housekeeping in work areas

Continue using the Take Five principles Before, During, and After work activities to:

  • Avoid Injuries
  • Reduce Environmental Impacts
  • http://www.fnal.gov/takefive/
 

Accelerator Update Archive

More Information
For Tevatron luminosity charts and the current status of Fermilab's accelerators and detectors (live!), please go to Fermilab Now.

Comments and Suggestions
What do you think about the Accelerator Updates? Please send comments and suggestions to: accelupdates@fnal.gov.

last modified 07/10/2009    email Fermilab