Adjustments put F-35 on track, program director says
The Defense Department's joint strike fighter program is on track to field the F-35 Lightning II in fiscal 2016. (Lockheed Martin photo/Tom Harvey)
Download HiRes
Adjustments put F-35 on track, program director says

Posted 2/17/2011 Email story   Print story

    


by Army Sgt. 1st Class Michael J. Carden
American Forces Press Service


2/17/2011 - ARLINGTON, Va. (AFNS) -- The Defense Department's joint strike fighter program is on track to field the F-35 Lightning II in fiscal 2016, the program's director said here Feb. 15.

In remarks to the National Aeronautics Association, Navy Vice Adm. David Venlet said that although changes made to the program in January extended flight testing and slowed development by about a year at an additional cost of $4.6 billion, the program has made progress over the past year.

"We're not spending that amount of money in one year, but it's the added content across the years to (2016) that consume the $4.6 billion," Admiral Venlet said. "We have no doubts that achieving fairly high rates of production is obtainable, but it's going to take some discipline on the way."

The fiscal 2012 defense budget request submitted this week has little effect on the program, Admiral Venlet added.

"There's no change after (the Feb. 14 budget) announcement, and I believe I've got a very stable requirement," said Admiral Venlet, who has led the program since May. "We have not changed our inventory objectives."

The right plan is in place to ensure the program is efficient in terms of cost-savings and production, he added, noting that the program has undergone an intense technical review under his watch.

The latest restructuring, he said, was realistic, achievable and based on deep assessments of all aspects of the program.

"Previous plans had shortcomings, but this plan is very resilient," he said. "The plan has been able to overcome spotty parts shortages, engine delivery problems, (and) it absorbed snow days where weather shut down production in the Dallas-Fort Worth area."

Admiral Venlet said he has instituted more testing, increasing the number of hours and flights that test pilots fly, having recently increased the mandated number of test flights through fiscal 2016 from 5,800 to 7,700.

He's confident, he said, that the additional $4.6 billion will hold up, as development and testing concludes in 2016.

Competition for the F-35 contract began in 1996. The $200 billion contract was awarded to Lockheed-Martin in October 2001, and the program immediately went into a 10-year testing and development phase.

Defense Department officials plan to purchase 325 aircraft through 2016, and the overall program consists of 2,443 total aircraft in three different variations. The variations include a takeoff and landing variant for the Air Force, an aircraft carrier-suitable version for the Navy and short takeoff and vertical landing variant for the Marine Corps.



tabComments
2/18/2011 11:10:59 AM ET
Really...the USAF is getting the takeoff and landing variant I sure hope the USAF version can takeoff and land.
Brett, Edwards AFB
 
Add a comment

 Inside AF.mil

ima cornerSearch

tabSubscribe AF.MIL
tabMore HeadlinesRSS feed 
Top U.S. officials honor Americans who died in Libya  2  |  VIDEO

DOD recognizes Hispanic-American achievements  2

'Today's Air Force' goes from New Mexico to near space

Air Force announces OTS selection board results  1

Wounded warriors discuss transitions to new lives

Air Force begins testing newest AEHF satellite

Atlas V lifts off from Vandenberg AFB

Air Force, NASA leaders review F-22 findings, fixes with congressional subcommittee  1

Air Force Week in Photos  1

AFPC officials automate ADSC process

Wind energy at Cape Cod to save $1 million a year  1

Alaska Reserve F-22 unit becomes fully operational  1

Through Airmen's Eyes: NCO finds restorative hobby

Vandenberg launch unit 'small squadron with big responsibilities'

tabCommentaryRSS feed 
Losing Your Future to Sexual Assault   23

Attacking Symptoms  7


Site Map      Contact Us     Questions     Security and Privacy notice     E-publishing