Recommendation 1992-2 Closed

DOE's Facility Representative Program at Defense Nuclear Facilities

Calendar Information

Thursday, May 28th, 1992Date Recommendation Delivered to DOE
Thursday, June 4th, 1992Date Recommendation Printed in Federal Register
Monday, July 6th, 1992Due Date for Public Comment on Recommendation
Monday, July 20th, 1992Due Date for DOE Response
Tuesday, July 21st, 1992Date DOE Response Received
Friday, July 31st, 1992Date DOE Response Printed in Federal Register
Monday, August 31st, 1992Due Date for Public Comment on DOE Response
Thursday, October 29th, 1992Due Date for DOE Implementation Plan
Thursday, November 5th, 1992Date DOE Implementation Plan Received
Friday, January 15th, 1993Date of DOE Implementation Plan Approval
Tuesday, October 1st, 1996Date Recommendation Closed