Recommendation 1991-3 Closed

DOE's Comprehensive Readiness Review Prior to Initiation of the Test Phase at the Waste Isolation Pilot PIant (WIPP)

Calendar Information

Thursday, April 25th, 1991Date Recommendation Delivered to DOE
Wednesday, May 1st, 1991Date Recommendation Printed in Federal Register
Friday, May 31st, 1991Due Date for Public Comment on Recommendation
Monday, June 17th, 1991Due Date for DOE Response
Wednesday, June 5th, 1991Date DOE Response Received
Wednesday, July 24th, 1991Date DOE Response Printed in Federal Register
Friday, August 23rd, 1991Due Date for Public Comment on DOE Response
Tuesday, September 3rd, 1991Due Date for DOE Implementation Plan
Wednesday, June 5th, 1991Date DOE Implementation Plan Received
Thursday, October 24th, 1991Date of DOE Implementation Plan Approval
Friday, May 1st, 1992Date Recommendation Closed