Schedule rating is calculated as the variance between the investment's planned and actual progress so far, in days as a percentage of the scheduled work so far. Visit the FAQs for details on how the IT Dashboard calculates Cost and Schedule rating and factors them into the Overall Rating.
Milestone # | Description | Start Date Planned | Start Date Actual | Completion Date Planned | Completion Date Actual | Schedule Variance in Days | Planned % Complete | Actual % Complete |
---|---|---|---|---|---|---|---|---|
MS-26726
|
FY 2009 Telecommunications DME | 10/01/2008 | 10/01/2008 | 09/30/2009 | 09/30/2009 | 0 | 100.00 | 100.00 |
MS-26727
|
FY 2009 Telecommunications SS | 10/01/2008 | 10/01/2008 | 09/30/2009 | 09/30/2009 | 0 | 100.00 | 100.00 |
MS-26728
|
FY 2010 Telecommunications DME | 10/01/2009 | 10/01/2009 | 09/30/2010 | 09/30/2010 | 0 | 100.00 | 100.00 |
MS-26729
|
FY 2010 Telecommunications SS | 10/01/2009 | 10/01/2009 | 09/30/2010 | 09/30/2010 | 0 | 100.00 | 100.00 |
MS-15721
|
FY 2011 Telecommunications DME | 10/01/2010 | 10/01/2010 | 09/30/2011 | 0 | 66.00 | 66.00 | |
MS-15722
|
FY 2011 Telecommunications SS | 10/01/2010 | 10/01/2010 | 09/30/2011 | 0 | 66.00 | 66.00 | |
MS-15723
|
FY 2012 Telecommunications DME | 10/01/2011 | * | 09/30/2012 | * | * | * | * |
MS-15724
|
FY 2012 Telecommunications SS | 10/01/2011 | * | 09/30/2012 | * | * | * | * |
MS-15725
|
FY 2013 Telecommunications DME | 10/01/2012 | * | 09/30/2013 | * | * | * | * |
MS-15726
|
FY 2013 Telecommunications SS | 10/01/2012 | * | 09/30/2013 | * | * | * | * |
MS-15727
|
FY 2014 Telecommunications DME | 10/01/2013 | * | 09/30/2014 | * | * | * | * |
MS-15728
|
FY 2014 Telecommunications SS | 10/01/2013 | * | 09/30/2014 | * | * | * | * |
MS-15729
|
FY 2015 Telecommunications DME | 10/01/2014 | * | 09/30/2015 | * | * | * | * |
MS-15730
|
FY 2015 Telecommunications SS | 10/01/2014 | * | 09/30/2015 | * | * | * | * |