This is the accessible text file for GAO report number GAO-03-1093 
entitled 'Export Credit Agencies: Movement Toward Common Environmental 
Guidelines, but National Differences Remain' which was released on 
September 10, 2003.

This text file was formatted by the U.S. General Accounting Office 
(GAO) to be accessible to users with visual impairments, as part of a 
longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

Report to Congressional Requesters:

September 2003:

Export Credit Agencies:

Movement Toward Common Environmental Guidelines, but National 
Differences Remain:

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-03-1093] GAO-03-
1093:

GAO Highlights:

Highlights of GAO-03-1093, a report to congressional requesters        

Why GAO Did This Study:

Export credit agencies (ECA) are responsible for providing billions of 
dollars worth of support for large-scale industrial projects annually, 
but until recently most ECAs did not formally review the environmental 
impacts of these projects. The United States, whose Export-Import Bank 
began using environmental guidelines in 1995, pushed for negotiations 
on common ECA environmental guidelines at the Organization for 
Economic Cooperation and Development (OECD). The OECD negotiations 
halted in 2001 because the United States believed that the results, 
called the Common Approaches, were insufficient. The remaining OECD 
members then pledged to voluntarily implement the Common Approaches. 
In response to congressional interest in ECA environmental guidelines, 
GAO assessed (1) the level of convergence among OECD members and the 
prospects for further advancement and (2) what impacts such guidelines 
may have on U.S. exports.

What GAO Found:

Since OECD negotiations began, members have made progress in 
developing environmental guidelines for their ECAs and are moving 
toward common environmental review practices. However, important 
differences remain. Having agreed to voluntarily implement the Common 
Approaches beginning in 2002, many OECD members adopted similar basic 
procedures for reviewing sensitive projects. However, OECD members’ 
guidelines and practices differ in areas where the United States 
believes it has among the more advanced policies, including which 
technical standards ECAs use to review projects and the extent to 
which environmental impact information is publicly disclosed. Although 
OECD members are considering revising the Common Approaches in 2003, 
the United States is unlikely to achieve all of its original 
negotiating objectives because of the desire by some OECD members to 
gain more experience with the guidelines before renegotiating them and 
the reluctance of other members to take any steps that might be 
perceived as having a negative effect on the competitiveness of their 
exporters. 

There is limited evidence that the Export-Import Bank’s environmental 
guidelines have affected U.S. exports, although the complexity of 
potential effects and the lack of information make identifying and 
quantifying impacts difficult. The evidence GAO reviewed indicates 
that impacts are likely to be concentrated in the energy sector. Most 
Export-Import Bank transactions do not require an environmental review 
because they are either short-term transactions, are in certain 
excluded sectors, or are not considered environmentally sensitive. 
Finally, while some businesses are more concerned about the impacts of 
environmental guidelines than others, their specific concerns are 
largely anecdotal and difficult to confirm. 


www.gao.gov/cgi-bin/getrpt?GAO-03-1093

To view the full product, including the scope and methodology, click 
on the link above. For more information, contact Loren Yager, (202) 
512-4347, yagerl@gao.gov.

[End of section]

Contents:

Letter: 

Results in Brief: 

Background: 

Common Approaches Offers Environmental Policy Framework, but National 
Differences Remain: 

Prospects Mixed for Further Advancement on Common Environmental 
Guidelines for ECAs: 

Limited Evidence of Economic Impact, but Assessment Difficult for 
Several Reasons: 

Agency Comments and Our Evaluation: 

Appendixes:

Appendix I: Objectives, Scope, and Methodology: 

Appendix II: OECD Members and Common Approaches Adherents: 

Appendix III: Description of Five ECA-Supported Projects: 

Batu Hijau Mine Project: 

Camisea Natural Gas Project: 

Chad-Cameroon Petroleum Pipeline Project: 

Olkaria III Geothermal Power Plant: 

Three Gorges Dam: 

Appendix IV: Comparison of ECA Environmental Policies for Seven 
Selected Countries: 

Appendix V: Comments from the Department of the Treasury: 

Appendix VI: Comments from the Export-Import Bank: 

Appendix VII: GAO Contacts and Staff Acknowledgments: 

GAO Contacts: 

Acknowledgments: 

Tables:

Table 1: Comparison of Environmental Review Procedures for the Export-
Import Bank of the United States and the OECD's Common Approaches: 

Table 2: Air Emissions and Effluent Discharge Standards for ECA Project 
Review of Steam Driven Thermal Power Plants: 

Table 3: Percentage of Ex-Im Bank's Financing in Selected Sectors 
before and after Implementing Environmental Guidelines: 

Table 4: OECD Members and Common Approaches Adherents: 

Table 5: Comparison of Environmental Review Procedures and Policies for 
ECAs of Selected OECD Countries: 

Figures:

Figure 1: Milestones in Efforts to Develop Common Environmental 
Guidelines for ECAs: 

Figure 2: Generic Flow Chart of Basic Environmental Review Framework: 

Figure 3: Environmental Review Category of Long-Term Projects, October 
1995-May 2003: 

Figure 4: Sector Distribution of Full Review Projects: October 1995 - 
May 2003: 

Abbreviations: 

ECA: Export Credit Agency:

ECG: Working Party on Export Credits and Credit Guarantees:

ECGD: Export Credit Guarantee Department:

EDC: Export Development Canada:

EIA: Environmental Impact Assessment:

G-8: Group of Eight:

JBIC: Japan Bank for International Cooperation:

NGO: nongovernmental organization:

OECD: Organization for Economic Cooperation and Development:

OND: Office National du Ducroire:

SDR: Special Drawing Rights:

Letter September 10, 2003:

The Honorable Henry J. Hyde 
Chairman 
Committee on International Relations:

The Honorable Peter T. King 
Chairman 
Subcommittee on Domestic and International Monetary Policy, Trade, and 
Technology 
Committee on Financial Services:

The Honorable Doug Bereuter 
Chairman 
Subcommittee on Europe 
Committee on International Relations 
House of Representatives:

Concerns about the environmental impacts of large-scale industrial 
projects in developing countries have led international development 
agencies such as the World Bank to implement guidelines to minimize 
environmental damage. Until recently, however, the world's 
industrialized nations have not required that their export credit 
agencies (ECA)[Footnote 1] apply such policies to the projects they 
support. Since ECAs annually finance around $60 billion in exports each 
year for medium-and long-term projects, environmental organizations 
have been pressuring industrialized nations to develop guidelines to 
review the environmental implications of export credit-sponsored 
projects. In 1995, in response to language in its revised charter, the 
Export-Import Bank of the United States (Ex-Im Bank) became the first 
ECA to implement guidelines incorporating environmental standards as 
part of the project review process.

To ensure that its exporters were not disadvantaged by environmental 
standards that other nations' exporters did not have to meet, the 
United States began an effort to establish common environmental 
guidelines for ECAs. Negotiations began at the Organization for 
Economic Cooperation:

and Development (OECD) in 1999[Footnote 2] but concluded without formal 
agreement at the end of 2001 due to U.S. objections. The United States 
was concerned that the negotiators' recommendations, formally called 
the Draft Recommendation on Common Approaches on Environment and 
Officially Supported Export Credits (Common Approaches) did not level 
the playing field for exporters. Specifically, the U.S. negotiators 
felt that the Common Approaches granted ECAs too much latitude in 
establishing guidelines and did not provide for sufficient public 
disclosure or explicit direction regarding which technical standards to 
use in the review process, such as those for allowable emissions. While 
the lack of consensus prevented the OECD from formally adopting the 
Common Approaches, most members nevertheless voluntarily agreed to 
abide by the terms of the most recent version of the Common Approaches. 
They also agreed to undertake a review of efforts to revise the Common 
Approaches by the end of 2003.

As a result of the potential impact of different ECA environmental 
requirements on U.S. exports, you asked us to assess (1) the 
achievements of the Common Approaches and the remaining differences 
among the OECD members, (2) the prospects for further advancement on 
common environmental guidelines for export credit agencies, and (3) the 
impact that environmental guidelines for export credit agencies may 
have on U.S. exports.

To meet these objectives, we reviewed documentation and interviewed 
knowledgeable officials from the departments of the Treasury and State 
and the Ex-Im Bank, the key U.S. agencies involved in export credit 
negotiations. We also traveled to Belgium, Canada, France, Germany, and 
the United Kingdom to interview senior government and ECA officials and 
OECD officials, and met with senior officials from the Japanese ECA in 
Washington. To evaluate the impact of environmental guidelines and 
regulations of ECAs on U.S. exports, we analyzed financing data and 
environmental assessments for 24 medium-and high-risk Ex-Im Bank 
projects. We supplemented this information with interviews with U.S. 
and foreign business representatives and nongovernmental organization 
representatives familiar with the environmental review process for both 
ECAs and multilateral development banks. (App. I provides detailed 
information on our scope and methodology.):

Results in Brief:

ECAs have moved toward common environmental policies, but important 
differences remain. While the environmental guidelines of the Export-
Import Bank are more specific than the Common Approaches, many OECD 
members are following similar basic procedures for reviewing 
environmentally sensitive projects. However, given the latitude 
permitted by the Common Approaches, there are differences in OECD 
member guidelines and practices, including which technical standards 
are used to review projects and the extent to which environmental 
impact information is publicly disclosed. For example, the French 
export credit agency recently developed its own technical standards for 
its three primary export sectors, including thermal power and 
hydroelectricity. In contrast, the German export credit agency 
guidelines require that projects meet host country environmental 
standards, and only call for further explanation if the host country 
standards are deemed significantly below other internationally 
recognized standards. With respect to public disclosure, while several 
OECD members are taking steps to provide environmental information on 
potential projects before project approval, as does the Export-Import 
Bank, some OECD members do not routinely disclose project information 
at any point, and some maintain that they are legally prohibited from 
doing so.

While OECD members are considering revising the Common Approaches, it 
will be challenging for OECD members to go beyond approving limited 
changes in the near term. The current version of the Common Approaches 
contains provisions for members to review their collective experience 
with environmental guidelines by the end of 2003. However, certain 
factors continue to make advancement difficult. For example, a number 
of OECD members prefer to gain more experience with environmental 
guidelines before renegotiating the Common Approaches, and some OECD 
countries are reluctant to take any steps that might be perceived as 
having a negative effect on the competitiveness of their exporters. 
While OECD members stated that they would like the United States to 
join the Common Approaches, the United States is unlikely to achieve 
all of its original negotiating objectives. Nevertheless, recent 
events, including an informal effort that environmental experts at 
export credit agencies undertook to share their experiences in applying 
standards to specific projects, may ultimately provide greater 
confidence to members about the benefits of having better defined 
technical standards. This could become the basis for a possible 
compromise on the Common Approaches.

There is limited evidence of the Export-Import Bank's environmental 
guidelines having affected U.S. exports, although the complexity of 
potential effects and the lack of information make identifying and 
quantifying impacts difficult. The vast majority of transactions 
authorized by the Export-Import Bank do not require an environmental 
review because they are either short-term transactions, are in certain 
excluded sectors such as aircraft, or are not considered to be 
potentially environmentally sensitive. Most projects that receive a 
full review are in the energy sector, largely because of the financing 
structure of many energy projects. For the types of projects that are 
subject to environmental review, available information does not show 
significant impacts, but assessments are difficult for several reasons. 
Trends in Export-Import Bank financing to sectors where environmental 
reviews have been concentrated do not show clear changes since the 
guidelines have been in place. In addition, available data on 
applications and approvals do not capture decisions early in the 
applications process or through informal channels and cannot account 
for other factors that affect the competitiveness of U.S. exports. 
Finally, while some businesses are more concerned about the impacts of 
environmental guidelines than others, their specific concerns are 
largely anecdotal and difficult to confirm.

The Department of the Treasury and Ex-Im Bank provided written comments 
on a draft of this report, which are reprinted in appendixes V and VI, 
respectively. The agencies generally agreed with the contents of the 
report and also provided technical comments that have been incorporated 
into this report as appropriate.

Background:

Between 1999 and 2001, the OECD member nations negotiated environmental 
policy framework for their ECAs. (See fig. 1.) With the exception of 
the United States,[Footnote 3] OECD members agreed in November 2001 to 
voluntarily implement a version of this framework, known as the 
Common Approaches. This process of negotiation followed a 1997 
communiqué from the Group of Eight (G-8)[Footnote 4] that indicated a 
strong interest in negotiating common environmental guidelines for 
ECAs. At the 1999 G-8 summit, the heads of state issued a second 
communiqué stating that they hoped for agreement within the OECD by 
their 2001 summit, a deadline the G-8 reiterated the following year.

The United States led the effort to regularly place common ECA 
environmental procedures on the G-8 agenda. The United States sought to 
promote uniform standards because it was concerned about unequal export 
market conditions and growing concern from nongovernmental 
organizations (NGO) that ECA-funded projects had the potential to cause 
significant environmental harm. However, the most current version of 
the Common Approaches required neither public disclosure of project 
information nor establishment of a single set of technical standards. 
Because the United States believed that these provisions were 
essential, it objected and said it would block the agreement if it were 
sent before the OECD Council for approval. Twenty-eight of 29 OECD 
members of the Working Party on Export Credits and Credit Guarantees 
(ECG)[Footnote 5] subsequently opted to voluntarily adhere to the 
Common Approaches, thus implementing the framework without a formal 
decision. Application of the Common Approaches began on January 1, 
2002. (See app. II for a list of OECD participants and ECG members that 
are implementing the Common Approaches.):

Figure 1: Milestones in Efforts to Develop Common Environmental 
Guidelines for ECAs:

[See PDF for image]

[End of figure]

Some ECAs have used environmental guidelines from the World Bank 
Group[Footnote 6] as a model for the development of environmental 
procedures and standards to use in evaluating projects. The 
environmental guidelines of Ex-Im Bank, for example, were developed 
using World Bank standards as a reference point.[Footnote 7] While the 
environmental review policies of different organizations within the 
World Bank Group vary somewhat, they generally follow a similar 
screening and categorization process (see fig. 2). The World Bank's 
environmental policies include evaluation and technical standards, such 
as those for emissions, which are laid out in the Pollution Prevention 
and Abatement Handbook. It also has a set of qualitative environmental 
and social standards, known as safeguard policies. These outline broad 
project and evaluation expectations, including guidelines on 
involuntary movement of peoples, impacts on cultural property, and 
conservation of natural habitats.

Figure 2: Generic Flow Chart of Basic Environmental Review Framework:

[See PDF for image]

[End of figure]

Representatives of both the business community and the environmental 
NGO community have expressed considerable interest in the issue of 
environmental review procedures for ECAs, but for different reasons. 
Some businesses in the United States are concerned that if Ex-Im Bank 
maintains environmental standards more stringent than the standards of 
some competitor ECAs, the additional project review and mitigation 
costs may hurt U.S. exports. Businesses in other OECD countries are 
also concerned that disclosure requirements, which the United States 
proposed in OECD negotiations, will make sensitive business information 
public. In contrast, environmental NGOs in numerous countries have 
become interested in ECA environmental review standards as a result of 
actual or proposed ECA funding of large potentially environmentally 
harmful projects as the Three Gorges Dam in China, the Chad-Cameroon 
oil pipeline, and the Camisea gas field development project in Peru. 
(See app. III for descriptions of selected ECA projects.) NGO 
representatives stated that ECAs, as public entities, should provide 
members of the public with the opportunity to provide input on projects 
that their governments are supporting. A number of these NGOs have 
joined in a campaign to change ECA practices to include strong review 
standards and open disclosure policies.[Footnote 8]

Common Approaches Offers Environmental Policy Framework, but National 
Differences Remain:

While most OECD members have adopted a common environmental policy 
framework through the Common Approaches, some notable differences 
remain in their ECA environmental review procedures and policies. 
Because the Common Approaches is only a framework, it allows important 
differences in members' national polices in certain key areas, such as 
the application of technical standards and the disclosure of project-
specific information.

Ex-Im Bank's Environmental Guidelines Are More Specific than the Common 
Approaches:

Ex-Im Bank guidelines provide much more specific detail than the Common 
Approaches framework (see table 1). Ex-Im Bank guidelines clearly 
describe which types of applications must undergo environmental review. 
For those transactions requiring review, Ex-Im Bank guidelines contain 
nine detailed sector tables delineating specific environmental 
requirements.[Footnote 9] Ex-Im Bank guidelines also provide for a 
public disclosure period prior to a final decision by its Board of 
Directors. During this period, it lists the name and location of 
projects which will be subject to an environmental review and makes 
certain environmental information available upon request. In contrast, 
the Common Approaches is a framework that allows for variations in 
project review specifics. The Common Approaches framework differs from 
Ex-Im Bank guidelines in that it does not specify the use of a single 
set of technical standards, does not establish a set review procedure, 
and does not require public disclosure of project information prior to 
final funding decisions. Adherents to the Common Approaches are, 
however, expected to assess projects using specific standards selected 
by the ECA involved, categorize projects according to environmental 
risk level, and annually report to the OECD information on 
environmentally sensitive projects.

Table 1: Comparison of Environmental Review Procedures for the Export-
Import Bank of the United States and the OECD's Common Approaches:

Stages in environmental review process: Initial application and 
screening process; Export-Import Bank of the United States: Specifies 
that projects either exceeding a $10 million threshold or exceeding a 
7-year repayment period must submit a screening document containing 
environmental information; OECD's Common Approaches: Broadly outlines 
the goals of a screening process but does not specify how the process 
should proceed. Expects that members will screen projects exceeding 10 
million special drawing rights[A].

Stages in environmental review process: Categorization; Export-Import 
Bank of the United States: Places projects in three classes of 
environmental review: high, medium, and low; OECD's Common Approaches: 
Places projects in three classes of environmental review: high, medium, 
and low.

Stages in environmental review process: Technical standards for 
evaluation; Export-Import Bank of the United States: Utilizes 
preestablished technical standards against which projects are 
evaluated; OECD's Common Approaches: Allows individual members to 
determine which standards are applied to projects. Members may 
establish their own standards or draw upon other organizations' or 
countries' preestablished standards.

Stages in environmental review process: Project disclosure; Export-
Import Bank of the United States: Requires that some project 
information, including the environmental impact assessment, be made 
public prior to funding decisions; OECD's Common Approaches: 
Encourages members to make project information public but makes no 
disclosure requirement prior to funding decisions.

Stages in environmental review process: Final approval; Export-Import 
Bank of the United States: Requires the Bank's Board of Directors to 
make final funding decisions for long-term projects; OECD's Common 
Approaches: Does not specify a process for making final funding 
decisions.

Source: GAO.

Note: Analysis based on Ex-Im Bank's environmental guidelines and the 
OECD's Common Approaches as outlined in Revision 6.

[A] Special Drawing Rights is a standardized unit of money calculated by 
the International Monetary Fund and not associated with a particular 
currency. As of July 24, 2003, $1 was equal to 0.713 special drawing 
rights.

[End of table]

Framework Has Promoted Some Convergence of ECA Environmental Policies:

When the OECD members developed the Common Approaches, they effectively 
established a framework to create or update their own ECA environmental 
review policies. Most OECD members have taken action to implement the 
Common Approaches' provisions. Some members, including Belgium, Greece, 
Hungary, and Portugal, did not previously have any environmental review 
practices but since adopting the Common Approaches have taken steps to 
create them. These include hiring staff to review projects for 
environmental concerns or training current staff to do so and 
implementing procedures for reviewing potential projects.

Many of the members that had environmental policies in place before 
adopting the Common Approaches have revised those policies since 
January 2002 to adhere to the Common Approaches. For example, as shown 
in appendix IV, ECAs in the six countries we visited have made 
revisions based on the provisions of the Common Approaches. Other OECD 
members have made similar revisions. For example, Norway introduced an 
environmental review policy in 1998 but reviewed it in 2003 to be sure 
it conformed to the Common Approaches.

Most OECD members are now following similar basic procedures for 
reviewing sensitive projects. For example, most of the countries we 
visited require applicants for financing to complete a questionnaire 
regarding the potential environmental impacts of their proposed 
project, which the ECA uses to categorize the project. Projects likely 
to have significant adverse environmental impacts are placed in 
category A, while projects with questionable environmental impacts are 
classified as category B. Most ECAs place projects with little or no 
potential environmental impact in category C. Most ECAs require 
applicants to complete an environmental impact assessment[Footnote 10] 
if their projects are placed in category A (high risk of environmental 
impact).

ECA projects may be approved despite adverse environmental impacts. 
Each ECA we visited relies on the judgment of its experts to evaluate 
the overall environmental impact of projects. Moreover, several ECAs, 
including Ex-Im Bank, allow their Boards to approve projects, 
notwithstanding the results of the environmental review. For example, 
Canada's ECA cites grounds where it could approve projects with adverse 
impacts under certain circumstances, including if it believes that the 
project represents an opportunity to improve environmental conditions 
in the host country or transfer environmentally sound technology and 
services.

Differences Exist in OECD Members' Specific Environmental Guidelines:

Despite the commonalities among OECD members' environmental impact 
review systems, differences exist in how ECAs review potential projects 
and report on projects they undertake. These differences involve the 
application of technical standards and the disclosure of certain 
information.

Technical Standards Vary but Have Common Elements:

OECD members vary in terms of the technical standards they use to 
assess environmental impacts. We found that it is common for members to 
use World Bank technical standards for their reviews. For example, most 
countries review projects for compliance with World Bank technical 
standards regarding air quality, greenhouse gas emissions, water 
consumption, and waste management (see table 2 for selected examples of 
air emissions and water quality not-to-exceed standards).

Table 2: Air Emissions and Effluent Discharge Standards for ECA Project 
Review of Steam Driven Thermal Power Plants:

[See PDF for image]

Source: GAO analysis based on published environmental guidelines for 
relevant organizations.

Legend:

mg/Nm^3 = milligrams per normal cubic meter.

MWe = megawatts electricity.

ng/J = nanograms per joule of heat input.

mg/l = milligrams per liter.

[A] Ex-Im Bank's standards were drawn from the 1995 version of World 
Bank guidelines; the World Bank guidelines were updated in 1998.

[B] Plants larger than 500 MWe may emit an additional 0.10 tons per day 
for each MWe of capacity beyond 500 Mwe.

[C] Not applicable to diesel driven plants.

[D] Indicates effluent should result in a temperature change of no more 
than the degrees indicated; from the ambient temperature of receiving 
water at the edge of the zone where initial mixing and dilution take 
place.

[E] Values shown for chromium represent total chromium.

[End of table]

While most members use World Bank technical standards, many also look 
to standards that other organizations have established. The World Bank 
has not updated its technical standards since 1998, and some officials 
stated that they prefer standards that are more up to date. For 
example, several ECA officials said they use World Bank standards in 
the majority of cases; but in some situations, standards set by the 
World Health Organization or the European Union are more appropriate or 
current. Canadian ECA officials reported that they use standards of the 
World Bank, World Health Organization, Canada, and regional development 
banks as benchmarks in their reviews. The French ECA established its 
own set of technical standards for three sectors. These sectors involve 
the most environmentally sensitive projects and represent a large 
portion of France's ECA-financed exports: conventional thermal power 
plants, large dams, and oil and gas projects. The standards contain a 
minimum set of criteria, which is largely linked to World Bank 
standards. In addition, French ECA officials said they encourage but do 
not require applicants to meet best practice standards, based on the 
best available technology or practices within the project's sector.

The German ECA, in contrast, does not rely on a defined set of 
environmental standards. It requires that all projects meet the 
environmental standards of the country in which the project is being 
constructed. German ECA officials stated that if the host country's 
standards are not comparable with internationally recognized standards 
or German national environmental standards, additional information is 
required before approval.

Some ECAs Consider Social Impacts:

ECAs do not commonly follow the World Bank safeguard policies on social 
impacts. During the OECD negotiations there was no consensus on how to 
account for these impacts, so they are not a part of the Common 
Approaches. However, some ECAs have taken steps to include 
considerations for social impacts in their environmental standards. For 
example, the British ECA requires applicants to answer questions about 
social and human rights impacts during the screening process. Projects 
that will have social impacts must submit a social impact assessment or 
some mitigation plan to address those potential impacts. The Japanese 
ECA has also included provisions on social impacts, including impacts 
on indigenous peoples, in its environmental policy. Ex-Im Bank also 
considers social impacts in its reviews and has specific guidelines in 
two of its nine sector tables (forestry operations and hydropower and 
water resources management).

Disclosure Policies Differ across ECAs:

ECA policies regarding public disclosure of project information vary. 
Some OECD members do not routinely disclose environmental or other 
project information, some disclose information after project approval, 
and others disclose before they make approval decisions. Many experts 
stated that, although ECAs are publicly financed, they are commonly 
less open about their activities than other government agencies because 
of their private sector orientation. Some countries such as Belgium, 
Germany, Portugal, and Spain cite national laws and regulations 
prohibiting disclosure of some information regarding export credit 
transactions as a barrier to disclosure of project information. Several 
ECAs provide information to the public, but only after an export credit 
transaction has been signed. For example, Canada and France are willing 
to make environmental information about their projects available to the 
public after the transactions have been approved.

Some ECAs are taking steps to provide environmental information on 
projects to the public before making a decision on whether to approve 
the project for financing. This is known as "ex ante" disclosure, the 
policy practiced by the United States,[Footnote 11] and often involves 
a public comment period in which outside parties are invited to submit 
comments on projects that will then be incorporated into the ECA's 
environmental review. For example, although it has a law restricting 
disclosure of project-specific information without consent from the 
financing applicant, the British ECA announced in April 2003 that it 
would publish information on its Web site about the environmental 
impacts of its most sensitive projects before making a financing 
decision. Officials from the British ECA said they made this policy 
change because they understand that environmental information often 
becomes public through third parties anyway. In addition, they believe 
that full disclosure of environmental information is an appropriate 
policy. They also cited pressure from nongovernmental organizations as 
a factor in their policy change.

Japan and Australia have made a similar commitment to disclosing 
environmental information about their most sensitive projects before 
finalizing an export credit agreement, with consent from their 
exporters. For example, following the environmental screening process, 
Japan's ECA discloses the project name, location, and sector, and 
reason for its category placement. In addition, for projects that are 
more sensitive, the ECA publishes on its Web site the status of major 
environmental and social documents prepared by or on behalf of the 
exporter, such as environmental impact statements, and makes these 
documents available to the public. The Japanese ECA also says that it 
encourages input from concerned organizations or stakeholders regarding 
the environmental impacts of projects under review. Australia's ECA has 
also adopted an ex ante disclosure policy. It provides for a 45-day 
public consultation period for accepting and reviewing comments from 
outside parties prior to final project approval.

Other Differences Remain in Policy Implementation:

In addition to the differences in their use of technical standards and 
disclosure policies, ECAs differ in implementing their environmental 
policies, specifically their criteria for categorizing and defining 
projects. In instances where several ECAs provide financing for a 
single project, they might place the project in different categories. A 
mining project, for example, might be categorized as high risk 
(category A) in one country, and medium risk (category B) in another. 
The Common Approaches has no prescriptions requiring countries to place 
specific types of projects in particular categories, thus allowing 
categorization to be a subjective activity that depends on the opinion 
of the official reviewing the project. In addition, the very nature of 
how to define a project can be in dispute. For example, officials from 
one ECA described a situation where another ECA treated a project with 
multiple components as a single project for categorization purposes, 
while they categorized each component separately.

Prospects Mixed for Further Advancement on Common Environmental 
Guidelines for ECAs:

OECD members are currently reviewing their efforts to voluntarily abide 
by the terms of the Common Approaches and may propose an alternative 
version by the end of 2003. However, a number of factors, including the 
resistance of some of the participants to certain proposed policies, 
present challenges to revising the Common Approaches. Nevertheless, 
several developments outside the formal OECD negotiations, including a 
series of meetings between ECA environmental experts, may lend some 
momentum to advancing the Common Approaches.

OECD Members Committed to Review and Revise the Common Approaches:

OECD members are in the process of reviewing the Common Approaches. The 
most recent version of the Common Approaches contains a provision 
stating that the ECG will review all aspects of the draft to enhance 
it. Participants stated this is typical of OECD multilateral 
negotiations, which often begin with general principles and gradually 
advance to a more detailed, comprehensive agreement. In this regard, 
officials from most of the countries we visited agreed to voluntarily 
comply with the terms of the Common Approaches. They stated that the 
most recent version is a good first step toward achieving a common 
approach to environmental standards for ECAs. For example, one official 
stated that, given the inexperience of many ECAs applying environmental 
standards, it would take several years for OECD members to accept 
guidelines similar to the Ex-Im Bank's.

A key aspect of the review process for the Common Approaches is the 
annual reporting among members of information about sensitive projects. 
During the negotiations, most members would not support prior 
disclosure of projects, which would have allowed the public to evaluate 
the application of environmental standards before projects are 
approved. As a compromise, members agreed to report annually on 
sensitive projects to evaluate how countries are abiding by their 
voluntary obligations. The Common Approaches states that members shall 
provide certain details about projects that members classified as 
either category A or B projects exceeding 10 million special drawing 
rights. The required details include a brief description of the 
project, its sector, the type of environmental review conducted, and 
the standards or benchmarks used in the review. Some ECA officials 
stated that the quality of reporting was not uniform across ECAs. They 
added that some of the countries have been very forthcoming with 
information but others have not. For example, in several instances the 
project's host country was not identified, making it difficult to 
assess the technical standards used to review the project.

Several key meetings in 2003 will give ECG members an opportunity to 
review and potentially revise the initial version of the Common 
Approaches. In April, ECG members discussed the results of the first 
annual report and agreed to provide recommendations for modifications 
to the Common Approaches to the ECG Chair by July 2003. The Chair plans 
to summarize these recommendations, which ECG members will then discuss 
in September. The final meeting in November 2003 may then serve as the 
venue for agreement on a revision of the Common Approaches that can be 
put to the OECD Council for a formal decision, according to OECD 
officials.

Near-Term Changes to Common Approaches May Be Limited:

Any revisions or enhancements to the Common Approaches during 2003 may 
be limited because of the nature of the OECD negotiating process and 
the resistance of many members to some of the more controversial 
aspects of environmental guidelines. The United States is therefore 
unlikely to fully achieve its original negotiating objectives, although 
most OECD members would like the United States to accept the Common 
Approaches as a formal OECD agreement.

The institutional framework of the OECD makes dramatic changes to the 
Common Approaches unlikely. The OECD commonly uses a combination of 
dialogue, peer review, and other forms of noncoercive peer pressure to 
encourage members to coordinate policies. In addition, OECD committees 
operate by consensus. Controversial topics can therefore be blocked by 
any single member, as the United States did with the Common Approaches. 
While such blocking is considered extreme and rare, according to OECD 
officials, it ensures that OECD policies evolve gradually.

Several specific factors make it difficult to go beyond incremental 
changes to the Common Approaches, particularly in areas of interest to 
the United States. First, while the United States has sought to 
negotiate a firm set of technical standards that all OECD members would 
have to use in their reviews, most ECA officials we spoke with prefer 
to apply a flexible approach to technical standards. Another, more 
difficult, obstacle to surmount is the resistance to disclosing project 
information. While the United States has pushed for ex ante disclosure 
of project information, other ECG members are either unable or 
unwilling to do this. In addition, some other ECG members are unwilling 
to adopt disclosure practices that are significantly advanced over 
their major ECA competitors. For example, the Canadian ECA pulled back 
a proposed ex ante disclosure policy once it was clear that the Common 
Approaches would not require such a policy, out of concern that the 
competitiveness of Canadian exporters might be compromised.

A final impediment to achieving a more than incremental advance in the 
Common Approaches is the effect of competing pressure on ECAs by both 
public interest and business groups. OECD members' positions on 
environmental standards reflect an internal balance achieved in 
response to domestic pressure. While nongovernmental organizations in 
some OECD countries were successful in getting their governments to 
push for the start of negotiations on environmental standards for ECAs, 
they have been less successful in achieving their objectives in the 
negotiations. Nongovernmental organizations in all the countries we 
visited are uniformly displeased with the results of the Common 
Approaches to date and are pressing for a broader Common Approaches 
that includes human rights, labor, and other social issues as part of 
the review process. However, business groups we met with are resistant 
to expanding the scope of the Common Approaches. While some ECAs, such 
as those of the United Kingdom and Japan, may unilaterally take up 
these social issues, most countries in our sample are not yet ready to 
consider adopting them. This reluctance occurs primarily because 
business concerns are considered of paramount importance to legislators 
at this point, according to several experts.

It will be difficult for the United States to fully achieve the 
objectives it sought at the conclusion of the Common Approaches 
negotiations in 2001. The United States no longer has the level of 
influence it had at the start of the negotiations. This is because the 
United States did not join the Common Approaches, which remains a 
source of resentment, and Ex-Im Bank no longer has the unique 
environmental expertise that it once did. Nevertheless, OECD members 
see benefits if the United States signs an OECD agreement. All the ECG 
members we met with stated that they would like to see the United 
States accept the OECD's Common Approaches. Some of these officials 
believe that a formal OECD agreement will provide ECAs with a stronger 
basis for improvements and convergence. For example, some officials 
note that a multilateral agreement permits countries to bring 
ministerial pressure to bear on issues. This is not possible under the 
current framework, which is supported under a voluntary agreement.

Recent Events May Provide Impetus to Negotiations:

Several recent events, including an informal effort by ECG 
environmental experts, may lend momentum to the negotiations. At the 
negotiations' outset, many ECG members did not have environmental 
guidelines and were reticent to negotiate on unfamiliar technical 
issues. However, as OECD members become more familiar with the 
application of environmental standards for ECAs, the likelihood of 
compromise increases, according to a number of the participants. 
Participants view a recent effort to share information among ECAs as a 
particularly promising vehicle for increasing their familiarity with 
technical aspects of environmental reviews. After the cessation of the 
negotiations in 2001, some of the members that had environmental 
experts (practitioners) in-house began to meet informally to discuss 
technical issues that were not 
addressed during the negotiations. These included issues such as 
defining a "greenfield site,"[Footnote 12] applying technical standards 
in specific instances, and more generally defining a project for the 
purpose of environmental review. To date, three such practitioners' 
meetings have been held, with broad participation by ECG members.

While the practitioners' meetings are an unexpected consequence of the 
conclusion of the negotiations, ECA officials we spoke with stated that 
the meetings may help advance the Common Approaches. First, they have 
been very useful in giving practical information on technical issues to 
ECG members that have only recently adopted environmental guidelines. 
In addition, they may provide helpful information to the negotiators on 
technical issues. For example, the practitioners have recently created 
four subgroups to focus on issues in specific sectors that will report 
back to the ECG on their findings.[Footnote 13] Finally, the 
practitioners may also provide members with some assurance that the 
terms of the Common Approaches are being met. As one official told us, 
the practitioners can ask specific questions of one another about how 
environmental standards were applied to specific projects. This 
information would not otherwise be available through the formal annual 
reporting process.

Another development that may lend some momentum to advancement in the 
Common Approaches is the commercial banking sector. Recently, 15 of the 
world's leading project finance institutions agreed to apply a set of 
principles incorporating environmental reviews of their 
projects.[Footnote 14] These principles, called the Equator Principles, 
set out provisions calling for the application of World Bank technical 
standards in the Pollution Prevention and Abatement Handbook and the 
International Finance Corporation safeguard policies standards for 
projects costing $50 million or more and for which project sponsors are 
seeking direct lending from the banks involved. The banks that follow 
the Equator Principles pledged that they will screen and categorize 
projects based on environmental risk. They also will require 
environmental assessments demonstrating compliance with the World Bank 
guidelines for projects with high or medium environmental or social 
risk. While adherence to the Equator Principles is voluntary, it 
indicates a growing understanding in the commercial banking sector of 
the importance of assessing environmental risk along with credit risk 
for these types of projects. Some officials believe that this is 
evidence that the business community is increasingly accepting the 
environmental assessment process as the norm for large development 
projects. This development may exert a positive influence on the ECA 
negotiations.

Limited Evidence of Economic Impact, but Assessment Difficult for 
Several Reasons:

There is limited evidence that Ex-Im Bank's environmental guidelines 
have affected U.S. exports, although the complexity of potential 
effects and the lack of information make identifying and quantifying 
impacts difficult. The evidence we reviewed indicates that any impacts 
are likely to be concentrated in certain areas, especially the energy 
sector. The majority of projects authorized by Ex-Im Bank do not 
require significant environmental review, and most projects in the full 
environmental review category are in the energy sector. Almost all are 
project finance cases. Trends in Ex-Im Bank financing to sectors where 
environmental reviews have been concentrated do not show clear impacts, 
and available data on applications and approvals are not adequate to 
capture decisions early in the applications process or through informal 
channels. Finally, we found that the evidence of business impacts is 
largely anecdotal and lack of data makes objective quantitative 
analysis difficult.

Ex-Im Bank's Environmental Reviews Have Been Concentrated in Certain 
Sectors:

A substantial portion of Ex-Im Bank financing does not require 
significant environmental review. Ex-Im Bank's environmental reviews 
are concentrated in the energy sector, largely because of the financing 
structure of many energy projects. Energy sector projects are expected 
to be of continuing importance to Ex-Im Bank because of rising energy 
demand in developing countries.

Only about one third of long-term Ex-Im Bank financing undergoes an 
environmental review after initial screening. Out of 522 long-term 
transactions authorized by Ex-Im Bank from October 1995 to May 2003, 42 
were subject to a full environmental review,[Footnote 15] and 181 were 
subject to a medium review. As figure 3 shows, these transactions 
represented 14 percent and 22 percent respectively of long-term Ex-Im 
Bank financing in terms of contract value. The remaining long-term 
transactions were only subject to an initial screening. This is because 
Ex-Im Bank's guidelines exempt from further review certain categories 
of projects considered to have little or no potential environmental 
effects, such as sales of aircraft, locomotives, and air traffic 
control systems.

Figure 3: Environmental Review Category of Long-Term Projects, October 
1995-May 2003:

[See PDF for image]

[End of figure]

The remainder of Ex-Im Bank financing does not undergo environmental 
review. This is because medium-and short-term transactions are 
generally not subject to either screening or review.[Footnote 16] Our 
analysis of Ex-Im Bank data showed that about 40 percent of its 
financing is for short-term transactions.

Environmental reviews of Ex-Im Bank's long-term financing tended to be 
concentrated in the energy sector. For example, from October 1995 to 
March 2003, authorized transactions that underwent full environmental 
reviews were mainly energy-related transactions (that is, thermal power 
plants, oil and gas development, hydropower plants). Of the 42 that 
went through a full environmental review, 16 were for thermal power 
plants and 9 were for oil and gas exploration projects.[Footnote 17] 
(See fig. 4 for the sector breakdowns for full review projects.):

Figure 4: Sector Distribution of Full Review Projects: October 1995 - 
May 2003:

[See PDF for image]

[End of figure]

Energy-related projects represent a high percentage of projects 
undergoing a full environmental review, largely because many are 
financed under project financing terms,[Footnote 18] which signifies 
greater overall financial risk to:

Ex-Im Bank. For example, the 16 thermal power projects and 9 oil and 
gas exploration projects were all financed under project finance 
terms.[Footnote 19]

Energy-related projects have been an important part of the financing 
portfolio for both Ex-Im Bank, as noted above, and for other ECAs. For 
example, financing for energy sector transactions represented about 27 
percent of Ex-Im financing during the 1990s and was 47 percent in 
1995.[Footnote 20] In 2001, out of $12.5 billion of U.S. exports 
supported by Ex-Im Bank, nearly $2 billion was in energy sectors, 
including electric power generation and transmission and oil and gas 
explorations and refineries. In 2001, oil and gas facilities accounted 
for 38 percent of the Japanese ECA's financing, and power generation 
and transmission projects accounted for 25 percent of the British ECA's 
financing. According to the OECD, 36 percent of OECD member projects 
(18 out of 50) that required full environmental reviews (category A 
reviews) in 2002 were energy projects, and these projects accounted for 
48 percent of ECA financing.

Energy sector financing is expected to continue to be important for 
ECAs because of projected increases in energy demand and associated 
investment needs in developing countries. The International Energy 
Agency's 2000 World Energy Outlook projects that over the next 2 
decades, nearly $3 trillion worth of investment in worldwide 
electricity generating capacities will be needed, not counting the need 
for transmission and distribution network sectors. The same report 
projects that world electricity generation is going to increase at an 
annual rate of 2.7 percent until 2020 and nearly 3,000 
gigawatts[Footnote 21] of new generating capacity is projected to be 
installed around the world, with more than half of this in developing 
countries, especially in Asia. The report also projects that OECD 
countries' share of world energy demand will continue to decline while 
developing nations' share will accelerate.

Impact of Environmental Guidelines Is Complex and Not Quantifiable:

For the types of ECA projects that are subject to environmental 
reviews, available data are limited and do not show clear impacts, and 
assessments are difficult because of the complex interplay of factors 
affecting financing and export trends. Trends in Ex-Im Bank financing 
to sectors where environmental reviews have been concentrated do not 
show clear impacts. In addition, available data on applications and 
approvals are insufficient for analytical purposes because they do not 
capture decisions early in the applications process or through informal 
channels. Further, environmental policies are only one among many 
factors that may affect the competitiveness of U.S. exports, and 
impacts vary depending on the nature of the exporter. At the company 
level, business views on the impacts of environmental guidelines are 
mixed. While many business representatives we spoke with have concerns 
about the environmental review process, including project delays, 
additional costs, and disclosure, most evidence is anecdotal. Several 
business representatives said they were less concerned about meeting 
technical standards of environmental guidelines than about dealing with 
uncertainties associated with the environmental review process, 
including reactions to the public disclosure of project information. We 
could not generally assess the magnitude or the extent to which the 
concerns reflected actual impacts caused by environmental guidelines. 
In addition, some business representatives stated that meeting Ex-Im 
Bank guidelines was consistent with their own requirements to identify 
issues that could potentially undermine projects.

Impact of Guidelines Complex and Not Evident from Available Data:

Trends in Ex-Im Bank financing to certain environmentally sensitive 
sectors do not show evidence of impacts of environmental guidelines, 
although a simple trends analysis would not be able to isolate those 
impacts from others. We reviewed Ex-Im Bank's financing in four 
sectors: thermal power, oil and gas development, hydro power, and metal 
mining. Table 3 illustrates the share of authorized financing to these 
sectors for periods before and after the adoption of Ex-Im Bank 
guidelines. The proportion of financing to oil and gas development 
projects stayed about the same after the implementation of 
environmental guidelines. Financing of thermal power plants experienced 
a drop, and metal mining an increase.

Table 3: Percentage of Ex-Im Bank's Financing in Selected Sectors 
before and after Implementing Environmental Guidelines:

Sectors: Thermal Power; 1988-1995: 13.28%; 1995-2003: 9.95%.

Sectors: Oil and Gas Development; 1988-1995: 10.41; 1995-2003: 10.31.

Sectors: Hydro Power; 1988-1995: 0.51; 1995-2003: 0.19.

Sectors: Metal Mining; 1988-1995: 0.57; 1995-2003: 1.12.

Source: Ex-Im Bank and GAO analysis.

[End of table]

An additional data limitation is that formal decisions on Ex-Im Bank 
projects provide only partial information regarding the impact of 
environmental guidelines on projects for several reasons. First, 
several companies said they use informal channels to determine whether 
environmental issues are likely to be a stumbling block before they 
submit final applications and that they might not do so if they 
anticipated concerns. Second, projects may be withdrawn or cancelled 
throughout the application process for any number of reasons that are 
not publicly reported. Finally, some projects that might have been 
submitted to Ex-Im Bank in the past may have been withheld because of 
the belief that Ex-Im Bank may no longer be willing to approve 
applications for certain types of environmentally sensitive projects, 
although it is impossible to determine the extent of this phenomenon.

Since the implementation of its environmental guidelines, Ex-Im Bank 
has only denied one final application on environmental grounds--the 
Peruvian gas field development project that was denied in August 
2003.[Footnote 22] In 1996, it also rejected the Three Gorges project 
in an earlier phase of the application process. After undertaking an 
environmental assessment, the Ex-Im Bank Board of Directors decided not 
to issue letters of interest--the document Ex-Im Bank issues in its 
preliminary review of a project seeking long-term loans and guarantees. 
Ex-Im Bank cited a number of environmental concerns that would have to 
be addressed by the Three Gorges project sponsors before it would 
reconsider requests for support, and requested information from the 
sponsors to that end. The sponsors did not provide the information, and 
the project eventually proceeded with financing from other sources.

Environmental policies are only one of many among many factors that 
affect the competitiveness of U.S. exports financed by Ex-Im Bank. 
Other factors include various Ex-Im Bank policies such as domestic 
content requirements,[Footnote 23] its application process and 
underwriting requirements, and the terms of coverage its policies 
provide. Other competitiveness factors are unrelated to Ex-Im Bank 
policies, such as foreign exchange rates and the geographic location of 
projects. In addition, factors such as the technological specifications 
of U.S. exports can be important to sourcing decisions. For example, 
one multinational company told us that whether the host country has 50 
cycle or 60 cycle electricity technology is the overriding factor for 
determining where their products are going to be manufactured.

The potential impacts of ECA environmental guidelines on U.S. exports 
depend in part on the overall business structure of the firms seeking 
ECA financing. For businesses that produce, or source, their products 
in the United States, the implementation of common environmental 
guidelines across ECAs should theoretically lower the threat of losing 
businesses to other ECAs with lax environmental standards. Since these 
companies are generally confined to doing business with Ex-Im Bank, 
they would otherwise lose export business if project sponsors select 
another ECA instead of Ex-Im Bank; therefore these companies have been 
the strongest business advocates for common guidelines. However, 
multinational companies may not be affected to the same degree. 
Officials from several of the companies we met with stated that as 
multinational companies they have been able to get financing from ECAs 
other than the U.S. Export-Import Bank. These companies are large and 
flexible enough that they can seek financing from ECAs in other 
countries where they have a business presence if they believe that Ex-
lm Bank's policies, including its environmental review process, would 
constitute a significant barrier to winning a project.

Business Groups Have Concerns, but Impacts Are Difficult to Confirm:

Business views on ECA environmental guidelines are mixed. Some business 
representatives we spoke with expressed concerns about specific impacts 
of the environmental review process, such as delays and costs. Others 
were concerned about the impacts of more intangible aspects that lend 
uncertainty to the process, such as public disclosure of project 
information. Some business representatives also acknowledged that their 
businesses are integrating the ECA environmental review policies and 
procedures into their own risk assessment processes.

Representatives of several companies cited delays during the project 
approval process as the key impact of the environmental assessment. Ex-
Im Bank often asks for additional information from the project sponsors 
and suppliers to supplement the initial environmental impact assessment 
submitted. In our review of 24 thermal power plant, oil and gas 
development, and metal mining projects authorized by Ex-Im Bank between 
1995 and 2003, we could not determine if the environmental assessment 
caused any project delays claimed by the companies. We found delays in 
some instances related to the gathering and submission of existing 
documentation to Ex-Im Bank for review and discussion of any 
outstanding issues, but the records were insufficient for attributing 
delays to environmental reasons as opposed to financial or other 
issues. We did find that Ex-Im Bank, in some cases, took measures to 
limit delays caused by environmental reviews and requirements. This 
included sending staff to review documentation in country, and making 
project support contingent on certain documents being provided at a 
later date.

Business representatives also cited additional costs as an area of 
concern, especially when project costs increased due to modifications 
necessary to meet environmental requirements. We found that in some 
instances Ex-Im Bank engineering staff did require project 
modifications to meet Ex-Im Bank guidelines for the 24 projects we 
reviewed. For example, a coal-fired power plant located in China met 
all of the air quality standards except for particulate emissions. The 
Chinese-built pollution control device met local standards but daily 
emissions would exceed the Ex-Im Bank guidelines. The local operator 
agreed to operate the device at a slightly higher control efficiency, 
which reduced emissions sufficiently to meet Ex-Im Bank's daily 
emission limit. Ex-Im Bank officials noted that, as companies have 
become more familiar with Ex-Im Bank guidelines, new projects are now 
much less likely to require modifications upon review.

Some businesses are also concerned about other aspects associated with 
the environmental review process. Many business representatives we 
spoke with believe that their products can readily meet the technical 
standards of environmental guidelines. They are concerned, however, 
about aspects that may result in lost business. For example, some 
elements of Ex-Im Bank's environmental guidelines require a more 
qualitative judgment of project impacts, such as how to mitigate 
socioeconomic and sociocultural impacts (such as those associated with 
the dislocation of people). However, some business representatives 
stated that these more qualitative areas of environmental standards 
present challenges and risks to businesses, because of the importance 
of other parties such as host governments in making and carrying out 
commitments.

Disclosure of project information during environmental review is 
another concern for some businesses.[Footnote 24] Some companies are 
concerned that disclosure of project information may result in their 
losing business to competitors if their competitors become aware of a 
project through the disclosure process. Other companies were also 
concerned about the potential impacts of public scrutiny. One company 
representative said that part of the reason the company's sourcing has 
shifted to Europe was because of Ex-Im Bank's disclosure policy, since 
European ECAs do not disclose information prior to project approval, 
although most did not identify differences in environmental guidelines 
as the determining factor in sourcing decisions.

We did not find specific examples where the disclosure of project 
information had negative impacts. Company representatives we spoke with 
did not provide us with any specific cases where they lost business 
because of the publication of the environmental impact assessment; 
their concerns were primarily hypothetical. The environmental impact 
assessments we reviewed did not contain any business proprietary 
information and did not contain information on the specific companies 
involved in the projects. According to Ex-Im Bank officials, any such 
information would be removed by the applicant or owner of the 
environmental assessment prior to the release of the document to 
interested parties.

Some companies have acknowledged that they are integrating the ECA 
environmental review policies and procedures into their own risk 
assessment processes. For example, several companies said that 
environmental review is increasingly viewed as a key component of their 
overall due diligence, which they conduct regardless of ECA 
requirements. Companies also acknowledge that since environmentally 
sensitive projects are coming under increasing NGO scrutiny, their 
reputations may be at risk if the projects they are involved in are 
deemed to be environmentally damaging.

Agency Comments and Our Evaluation:

We provided a draft of this report to the Secretaries of State and the 
Treasury, and the Chairman of Ex-Im Bank. The Department of the 
Treasury and Ex-Im Bank provided written comments on the draft report, 
which are reprinted in appendixes V and VI, respectively. The 
Department of the Treasury considered the report well balanced, but 
also emphasized its belief that U.S. leadership on this issue has had a 
significant positive impact among export credit agencies, despite the 
lack of a formal OECD agreement. Ex-Im Bank stated that the report 
provides a thorough analysis, but emphasized its view that, despite 
progress, the broad nature of the Common Approaches does not yet level 
the playing field for U.S. exporters. The Department of State did not 
provide formal comments.

We are sending copies of this report to interested congressional 
committees, the Secretaries of State and the Treasury, and the Chairman 
of Ex-Im Bank. We will also make copies available to others upon 
request. In addition, the report will be available at no charge on the 
GAO Web site at [Hyperlink, http://www.gao.gov.] http://www.gao.gov.

If you or your staff have any questions about this report, please 
contact me at (202) 512-4347. Other GAO contacts and staff 
acknowledgments are listed in appendix VII.

Loren Yager, Director International Affairs and Trade:

Signed by Loren Yager: 

[End of section]

Appendixes:

Appendix I: Objectives, Scope, and Methodology:

The Chairman of the House Committee on International Relations and the 
Chairman of the Subcommittee on Europe, House Committee on 
International Relations asked us to examine the effect of environmental 
standards for export credit agencies. In response, we assessed (1) the 
achievements of the Common Approaches and the remaining differences 
among the members of the Organization for Economic Cooperation and 
Development (OECD), (2) the prospects for further advancement on common 
environmental guidelines for export credit agencies, and (3) the impact 
that environmental guidelines for export credit agencies may have on 
U.S. exports.

To identify the achievements of the Draft Recommendation on Common 
Approaches on Environment and Officially Supported Export Credits 
(Common Approaches) and the remaining differences among the OECD 
members, we met with and obtained information from officials at the 
OECD secretariat, export credit agency (ECA) officials in a number of 
OECD member countries (Belgium, Canada, France, Germany, Japan, and the 
United Kingdom), and from several U.S. government agencies. 
Specifically, we interviewed officials in the OECD Trade Directorate's 
Export Credit Division and reviewed OECD documents presented in 
meetings of the Working Party on Export Credits and Credit Guarantees 
(ECG). We also met with ECA and other government officials in Belgium, 
Canada, France, Germany, and the United Kingdom. In addition, we met 
with senior officials from the Japanese ECA in Washington, D.C. We 
reviewed and compared the environmental policies of these countries' 
ECAs as well. We also met with officials from the U.S. Departments of 
the Treasury and State and the Export-Import Bank. We obtained an 
understanding of the environmental policies of each ECA we visited 
based on information we received in interviews and the documents we 
were provided. We reviewed and compared the ECA policies according to 
key procedural elements we identified, such as the screening and 
categorization of projects, the technical standards used during the 
review, and public disclosure policies.

To determine the prospects for further advancement on environmental 
guidelines for ECAs, we interviewed and obtained information from OECD, 
ECA, and other officials from Belgium, Canada, France, Germany, Japan, 
and the United Kingdom. We also interviewed representatives from 
nongovernmental organizations (NGO) active in ECA issues in Belgium, 
Canada, France, Germany, the United Kingdom, and the United States. In 
addition, we interviewed business groups knowledgeable about export 
credit issues in Canada, France, Germany, the United Kingdom, and the 
United States to understand their views on the progress that OECD 
countries have made since the conclusion of the negotiations and on 
what they believe will and should happen next. We gained these 
officials' perspectives on their goals for further negotiations on ECA 
environmental guidelines and what additional provisions they would like 
to include in the next revision of the OECD Common Approaches. We also 
reviewed documents from the OECD detailing members' experiences with 
implementing the Common Approaches.

To understand what impacts environmental guidelines for export credit 
agencies may have on U.S. exports, we met with, and obtained and 
analyzed data from, officials at Ex-Im Bank and representatives of U.S. 
businesses. We first obtained and analyzed data from Ex-Im Bank on 
long-term transactions that had been authorized by Ex-Im Bank to 
determine the number of transactions and the amount of Ex-Im Bank 
financing that falls into each of the three environmental risk 
categories. We determined that Ex-Im Bank data were sufficiently 
reliable for analyzing for this engagement, based on our assessment of 
the completeness and accuracy of the data. We reviewed the data to 
determine industry sector representation in each of the categories. We 
then selected 24 of the authorized projects to more specifically 
determine how they had been affected by Ex-Im Bank environmental 
guidelines. These 24 projects were selected using several criteria. 
First, we focused on the three industry sectors (thermo power, oil and 
gas development, and metal mining) representing about 70 percent of 
non-nuclear long-term higher risk projects. We also selected projects 
from the entire period that Ex-Im Bank's guidelines were in effect. 
Finally, we selected projects that received both a full and a medium 
environmental review, with an equal number in each category for oil and 
gas and thermo power. We selected all four metal mining projects, since 
there was a limited number. We analyzed Ex-Im Bank environmental 
assessments for each of these projects and met with Ex-Im Bank 
officials in the Engineering and Environment division to discuss the 
environmental review process and their interaction with applicants for 
financing. In addition, we interviewed representatives of nine U.S. 
companies, including a U.S. subsidiary overseas, to obtain their views 
and concerns about the impact of environmental guidelines on their 
exports. These businesses were responsible for 82 out of the 522 long-
term projects authorized between October 1995 and May 2003 and 19 of 
the 38 non-nuclear projects that underwent a full environmental review.

:

The information on foreign laws or regulations in this report does not 
reflect our independent legal analysis but is based on interviews and 
secondary sources.

We conducted our review from November 2002 through August 2003 in 
accordance with generally accepted government auditing standards.

[End of section]

Appendix II: OECD Members and Common Approaches Adherents:

Table 4 represents the membership of the OECD's ECG, and their 
respective positions on Common Approaches issues. There are 29 members 
of the ECG. With the United States declining to accept the Common 
Approaches in November 2001, 28 ECG members agreed to voluntarily 
adhere to the Common Approaches.

By March 2003, 24 countries had reported to the OECD on their category 
A and B projects for 2002 (that number includes the United States, 
although they do not have to report since they are not technically 
adhering to the Common Approaches). Four adherents to the Common 
Approaches had not reported anything as of March 2002--the Czech 
Republic, Mexico, the Slovak Republic, and Turkey.

Seventeen countries reported that during 2002 they had reviewed at 
least one category A or B project.

Table 4: OECD Members and Common Approaches Adherents:

ECG: members: (29): Australia; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): Yes; Members with A and 
B projects for 2002: (17): Yes.

ECG: members: (29): Austria; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): Yes; Members with A and 
B projects for 2002: (17): Yes.

ECG: members: (29): Belgium; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): Yes; Members with A and
B projects for 2002: (17): Yes.

ECG: members: (29): Canada; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): Yes; Members with A and 
B projects for 2002: (17): Yes.

ECG: members: (29): Czech Republic; Common Approaches adherents: (28): 
Yes; Members reporting on A and B projects: (24): No; Members with: 
A and B projects for 2002: (17): No.

ECG: members: (29): Denmark; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): Yes; Members with A and 
B projects for 2002: (17): Yes.

ECG: members: (29): Finland; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): Yes; Members with A and 
B projects for 2002: (17): Yes.

ECG: members: (29): France; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): Yes; Members with A and 
B projects for 2002: (17): Yes.

ECG: members: (29): Germany; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): Yes; Members with A and 
B projects for 2002: (17): Yes.

ECG: members: (29): Greece; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): Yes; Members with A and 
B projects for 2002: (17): No.

ECG: members: (29): Hungary; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): Yes; Members with A and 
B projects for 2002: (17): No.

ECG: members: (29): Ireland; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): No; Members with A 
and B projects for 2002: (17): No.

ECG: members: (29): Italy; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): Yes; Members with A and 
B projects for 2002: (17): Yes.

ECG: members: (29): Japan; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): Yes; Members with A and 
B projects for 2002: (17): Yes.

ECG: members: (29): Korea; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): Yes; Members with A and 
B projects for 2002: (17): Yes.

ECG: members: (29): Luxemburg; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): Yes; Members with A and 
B projects for 2002: (17): No.

ECG: members: (29): Mexico; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): No; Members with A 
and B projects for 2002: (17): No.

ECG: members: (29): Netherlands; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): Yes; Members with A and 
B projects for 2002: (17): Yes.

ECG: members: (29): New Zealand; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): Yes; Members with A and 
B projects for 2002: (17): No.

ECG: members: (29): Norway; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): Yes; Members with A and 
B projects for 2002: (17): No.

ECG: members: (29): Poland; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): Yes; Members with A and 
B projects for 2002: (17): No.

ECG: members: (29): Portugal; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): Yes; Members with A and 
B projects for 2002: (17): No.

ECG: members: (29): Slovak Republic (joined 5/27/02); Common Approaches 
adherents: (28): Yes; Members reporting on A and B projects: (24): 
No; Members with A and B projects for 2002: (17): No.

ECG: members: (29): Spain; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): Yes; Members with A and 
B projects for 2002: (17): Yes.

ECG: members: (29): Sweden; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): Yes; Members with A and 
B projects for 2002: (17): Yes.

ECG: members: (29): Switzerland; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): Yes; Members with A and 
B projects for 2002: (17): Yes.

ECG: members: (29): Turkey; Common Approaches adherents: (28): Yes; 
Members reporting on A and B projects: (24): No; Members with A 
and B projects for 2002: (17): No.

ECG: members: (29): United Kingdom; Common Approaches adherents: (28): 
Yes; Members reporting on A and B projects: (24): Yes; Members with 
A and B projects for 2002: (17): Yes.

ECG: members: (29): United States; Common Approaches adherents: (28): 
No; Members reporting on A and B projects: (24): Yes; Members with 
A and B projects for 2002: (17): Yes.

Source: GAO analysis based on OECD documents.

[End of table]

[End of section]

Appendix III: Description of Five ECA-Supported Projects:

ECAs provide financial support for a wide array of goods and services. 
However, projects in certain areas, such as thermal power, hydropower, 
and oil and gas, have been the most likely to require environmental 
review under the Ex-Im Bank's or other export credit agencies' 
guidelines. In this appendix, we describe five recent projects that 
have been subject to environmental review and briefly discuss 
environmental concerns associated with the projects and ECAs' project 
involvement.

Batu Hijau Mine Project:

:

Project Description:

Batu Hijau is an open pit copper and gold mine located on Indonesia's 
Sumbawa Island. A consortium, comprised of U.S.-based Newmont Mining 
Corporation, Sumitomo (Japan), and PT Pukuafu Indah (Indonesia), 
operates the mine. Newmont holds majority ownership in the joint 
venture. Batu Hijau began operation in 2000 and is expected to continue 
operation for 20 years. When the mine is completely excavated, 3 
billion tons of rock will have been mined, creating a mine pit that 
will be 2,625 meters wide (8,612 feet) and 460 meters deep (1,509 
feet). As of January 2003, Batu Hijau employed approximately 6,700 
people, 95 percent of whom are Indonesian. In 2002, the mine as a whole 
contributed more than $171 million to the Indonesian economy. The mine 
produced 657.7 million pounds of copper and 492 thousand ounces of gold 
in 2002.

Environmental Concerns:

Batu Hijau is located primarily within a previously undisturbed 
tropical forest. Environmental concerns associated with Batu Hijau 
include:

* loss of vegetation, specifically loss of primary tropical forest and 
habitat associated with the protected yellow-crested cockatoo;

* impact on local water levels and water quality (pH and 
sedimentation);

* disposal of large amounts of excavated rock and tailings, waste rock 
created during the extraction process;

* impact of air emissions from mine infrastructure and equipment; and:

* maintenance of mine pit environmental programs following cessation of 
mine operation.

ECA Involvement:

In 1997, Ex-Im Bank provided $425 million in project financing to Batu 
Hijau project sponsors and developers. Japan's export credit agency 
also provided support for Batu Hijau.

Ex-Im required a number of environmental studies and project 
modifications designed to minimize the project's environmental and 
social impacts before providing financing. Project developers have 
attempted to mitigate environmental concerns through, among other 
efforts, development of a deep-sea tailings disposal system, operation 
of a revegetation program, and study of water seepage patterns.

Camisea Natural Gas Project:

:

Project Description:

The over $2 billion Camisea natural gas project, located near the Lower 
Urubamba River in the Echarte district in Peru, involves the extraction 
and processing of natural gas and natural gas liquids and the 
transportation of these products to markets in Lima and ports for 
export. Royal Dutch/Shell first discovered the Camisea gas fields in 
the mid-1980s, and Shell and Mobil Oil further explored the fields 
between 1996 and 1998. In July 1998, Shell and Mobil withdrew from the 
project, leading the government of Peru to pursue alternative 
developers. In December 2000, the government of Peru signed a series of 
contracts with PlusPetrol Corporation (Argentina) and with two 
consortiums, including Grana y Montero (Peru), Hidrocarburos Andinos 
(Argentina), Hunt Oil Company (USA), SK Corporation (Korea), Sonatrach 
(Algeria), Sucursal del Peru, Sucursal Peruana, and Techint 
(Argentina).

The Camisea project is expected to supply a substantial portion of 
Peru's energy needs and allow for natural gas export. Camisea requires 
construction of eight wells accessing the San Martin and Cashiriari 
natural gas fields; a liquid separation plant to separate water and 
liquid hydrocarbons; two pipelines (one for natural gas and one for 
natural gas liquids), one estimated to run 540 kilometers (336 miles) 
and the other 680 kilometers (423 miles); a coastal fractionation plant 
to separate liquids into commercial quality products, and an offshore 
loading facility. Construction of project components under the 
consortium contracts began in 2001 and was roughly 60 percent complete 
as of February 2003. The project is scheduled to begin commercial 
production in August 2004. The San Martin and Cashiriari gas fields 
together contain proven reserves[Footnote 25] of 8.7 trillion cubic 
feet of natural gas and 545 million barrels of natural gas liquids. 
Project officials estimate that project construction will employ an 
average of 1,700 people during the construction period.

Environmental Concerns:

The Camisea project is located within Peru's Amazon jungle in close 
proximity to several voluntarily isolated indigenous peoples. Two-
thirds of the project area, sometimes referred to as Block 88, lies 
within the Nahua-Kugapakori Indigenous Reserve and straddles the 
Camisea River. The coastal fractionation plant will be located in the 
buffer zone of the Paracas National Reserve, Peru's only coastal marine 
reserve. The project pipelines will traverse the rain forests between 
Camisea and the coast, passing over the Andes Mountains at an altitude 
of 4,500 meters (14,764 feet).

The location of the project has led to major concerns about Camisea's 
environmental and social impacts that include:

* increased contact between indigenous peoples and project employees 
and the associated risks of epidemic disease and cultural damage,

* improper use of project right-of-way by Peruvians seeking fertile 
land and erosion and loss of biodiversity along the right-of-way,

* loss of biodiversity in the Camisea River and related effects on 
indigenous peoples dependent on the river for fish and water,

* lack of sufficient information on alternative sites in the 
environmental assessment needed to justify construction of the 
project's marine terminal facility adjacent to the environmentally 
sensitive Paracas Bay Natural Reserve, and:

* loss of biodiversity in Paracas National Reserve.

ECA Involvement:

On August 28, 2003, Ex-Im Bank's Board, in a 2 to 1 vote, declined to 
support Camisea on environmental grounds.

Chad-Cameroon Petroleum Pipeline Project:

:

Project Description:

The Chad-Cameroon Petroleum Pipeline Project accesses the oil fields at 
Doba in southern Chad and transports the oil 1,070 kilometers (665 
miles) to an off-shore oil-loading facility on Cameroon's coast. 
Sponsors of the project, ExxonMobil (USA), Petronas (Malaysia), and 
ChevronTexaco (USA), estimate construction costs will be $3.5 billion. 
Estimates indicate that the government of Chad will receive a total of 
$2 billion in revenues from the project, while the government of 
Cameroon will receive $500 million, assuming reserves of 917 million 
barrels of oil. In Chad, revenues from the pipeline could increase 
total government revenues by 45 to 50 percent. In the fourth quarter of 
2002, wage payments of $12 million were made to the 9,643 workers from 
Chad and Cameroon that the project employs. As construction concludes, 
project developers are reducing the workforce; nonetheless, wage 
payments totaling $10.1 million were made to workers from Chad and 
Cameroon in the first quarter of 2003. Pipeline operation began July 
24, 2003, and full operation is expected to commence by the end of 
2003.

The World Bank Group has provided $92.9 million in direct loans to the 
governments of Chad and Cameroon to finance the governments' minority 
holdings in the project. Additionally, the International Finance 
Corporation, the World Bank Group institution that facilitates private 
sector projects, has provided $100 million in loans to the joint 
venture pipeline companies and has mobilized an additional $100 million 
from commercial lenders.

Environmental Concerns:

Project sponsors undertook some project modifications to meet project 
standards established by the World Bank and Ex-Im Bank, including 
alteration of the pipeline route and development of a community 
consultation process. Concerned NGOs, however, claim that project 
developers insufficiently addressed the concerns of local residents and 
that few changes resulted from environmental reviews.

Environmental and social issues raised by both World Bank and 
environmental NGOs include:

* possible oil spills occurring along the pipeline or at the offshore 
oil-loading facility;

* decreases in biodiversity along the pipeline right-of-way, 
particularly along the Sanaga River system, within Cameroon's Atlantic 
littoral rainforest, and in the Kribi coastal region;

* negative effects on indigenous Bakola pygmies living in the vicinity 
of the pipeline; and:

* governmental repression of opposition to the pipeline as seen in the 
imprisonment of a Member of Parliament as a result of his opposition to 
the project.

ECA Involvement:

Both Ex-Im Bank and France's ECA, Coface, have provided support to the 
Chad-Cameroon project. In 2000, Ex-Im Bank approved $200 million in 
export credit guarantees for a U.S.-based engineering firm contracted 
to build the pipeline portion of the project.

Olkaria III Geothermal Power Plant:

:

Project Description:

The Olkaria III geothermal power plant, located in the Olkaria Domes 
geothermal field near Lake Naivasha, is Kenya's first privately 
developed and owned geothermal power plant. Olkaria III is the third 
geothermal development project undertaken in the Olkaria region but the 
first under ORMAT, a U.S.-based geothermal developer. Olkaria I has 
been operational since 1981 under the governance of Kenya Electricity 
Generating Company Ltd. (KenGen), a Kenyan energy state-owned 
enterprise. KenGen is supervising the public sector development of 
Olkaria II, scheduled to begin operation in September 2003. Olkaria III 
began operation of an early production facility in August 2000 with 
scheduled expansion of production from 12 megawatts to 48 megawatts. 
ORMAT funded the entire $50 million first phase of the Olkaria III 
project.

Environmental Concerns:

In 1984, 3 years after Olkaria I began operation, but before the 
creation of Olkaria II and III, Kenya created Hell's Gate National 
Park, including in the park the tract of land upon which the Olkaria 
geothermal plants are located. Additionally, indigenous Maasai peoples 
have historically occupied the land surrounding Lake Naivasha. These 
two complicating factors have led to environmental and social concerns 
surrounding the Olkaria developments that include:

* possible emissions-related negative health impacts on local Maasai 
communities,

* Maasai loss of historically occupied lands, and:

* possible negative impacts on local flower growers and wildlife 
dependent upon Lake Naivasha water.

Olkaria III project developers have addressed some environmental 
concerns through use of air-cooled geothermal technology and 
reinjection of geothermal fluids produced by the plant, technologies 
not employed in Olkaria I or II.

ECA Involvement:

ORMAT's application for Ex-Im Bank support has been pending since 2001. 
No decision had been made as of August 28, 2003. Ex-Im officials stated 
that the project delay was not due to environmental concerns.

Three Gorges Dam:

:

Project Description:

The government-owned Three Gorges Dam, located on the Yangtze River in 
China's Hubei Province, will be the largest hydroelectric plant in the 
world when it is completed in 2009. Dam construction began in 1994, and 
the water sluice gates were first closed on June 1, 2003. Companies 
headquartered throughout the world have received construction 
contracts.

The Chinese government has undertaken construction of the dam, 
primarily to increase China's power generation capacity, control 
downstream flooding of the Yangtze, and improve river navigation for 
large vessels. The annual energy generating capacity of the dam's 26 
turbine generators will be 84.7 billion kilowatt hours, generated from 
a renewable energy source without creating pollution. The dam itself 
will stand 181 meters (594 feet) high and create a reservoir stretching 
over 600 kilometers (373 miles). The reservoir is expected to have a 
floodwater storage capacity of 28.97 billion cubic yards. A multistage 
ship lock and lift will provide upstream navigation to river vessels.

Environmental Concerns:

Throughout planning and construction of the Three Gorges Dam, the 
project has raised environmental and social concerns that include:

* inadequate treatment of water discharged above the dam and associated 
health risks for communities bordering the reservoir,

* relocation and provision of housing and employment for the up to 1.3 
million people residing in the plain of the reservoir,

* loss of historical and archeological artifacts located in the plain 
of the reservoir,

* possibility of sedimentation limiting the dam's ability to control 
flooding and increasing regional seismic activity, and:

* alterations in the Yangtze River's ecosystem and surrounding river 
basin.

The Chinese government has taken steps to address several of the above 
issues, including relocation of the 1.3 million people affected by the 
dam's construction beginning in 1995, efforts to remove historical and 
archeological artifacts from the reservoir area, and creation of water 
treatment plants upstream of the dam. The results of the government's 
efforts to improve the environmental impact of the dam have been 
subject to debate.

ECA Involvement:

In May 1996, Ex-Im Bank's Board of Directors declined to issue a letter 
of interest to exporters seeking a financing commitment for the Three 
Gorges Dam project. This action was based on a determination that the 
information made available to date indicated that the project as 
planned would not meet the Bank's environmental guidelines. The Ex-Im 
Bank sent a letter in July 1996 detailing the type and scope of 
information that it would need to identify and assess proposed 
mitigation measures that could be incorporated into the project in 
order to meet its guidelines. That information was never provided, and 
project developers eventually successfully sought support from other 
OECD export credit agencies.

[End of section]

Appendix IV: Comparison of ECA Environmental Policies for Seven Selected 
Countries:

Table 5 details the environmental review procedures and policies of the 
export credit agencies of six OECD countries that have agreed to 
voluntarily adhere to the Common approaches, and of Ex-Im Bank. The 
screening procedures, impact categories, and environmental review 
processes are generally similar for all of the ECAs. The main 
differences are in the ECAs' public disclosure policies and in their 
use of technical standards for environmental reviews.

Table 5: Comparison of Environmental Review Procedures and Policies for 
ECAs of Selected OECD Countries:

Date of policy introduction; Belgium: Office National du Ducroire: 
(OND): 2002; Canada: Export Development Canada: (EDC): 1999; (revised 
2001); France: Coface: 1999; (revised periodically since 2001); 
Germany: Hermes: 2001; (implemented Common Approaches 2002); Japan: 
Japan Bank for International Cooperation: (JBIC): 1999; (revised 2002); 
United Kingdom: Export Credit Guarantee Department: (ECGD): 2000; 
(revised 2003); United States: Export Import Bank: (Ex-Im Bank): 
1995; (revised 1998).

Cost thresholds; Belgium: Office National du Ducroire: (OND): 
Applications subject to environmental screening if requested coverage 
is for 10 million special drawing rights or more, unless project is in 
a sensitive location; Canada: Export Development Canada: (EDC): 
Applications subject to environmental screening if requested coverage 
is for 10 million SDR or more and repayment term is for 2 years or 
more; France: Coface: Applications subject to environmental 
screening if requested coverage is for 10 million euros or more; 
Germany: Hermes: Applications subject to environmental screening if 
requested coverage is at least 15 million euros or if project has 
potential to cause significant adverse impacts; Japan: Japan Bank for 
International Cooperation: (JBIC): All applications subject to 
environmental review. If requested coverage is for less than 10 million 
SDR, project is immediately classified as category C, and no further 
environmental review is required, unless project has sensitive 
characteristics or is in a sensitive location; United Kingdom: Export 
Credit Guarantee Department: (ECGD): All applications screened for 
environmental impact; United States: Export Import Bank: (Ex-Im 
Bank): Application subject to environmental screening if requested 
coverage is for $10 million or greater, or repayment term exceeds 7 
years.

Screening procedures; Belgium: Office National du Ducroire: (OND): All 
applicants submit completed environmental questionnaire with 
application, which is used for categorizing potential projects; 
Canada: Export Development Canada: (EDC): EDC may rely on past agency 
experience, applicable outside resources, and/or completed 
environmental screening questionnaires to screen potential projects and 
categorize them; France: Coface: All applications are prescreened, 
based on amount of requested coverage and sensitivity of project 
location. Applications that meet the cost threshold then complete a 
screening questionnaire, which is used for categorizing potential 
projects; Germany: Hermes: Projects that meet the cost thresholds 
undergo a preliminary examination, and the applicant must submit 
information on environmental impact. Underwriters evaluate each project 
based on cost and sector; Japan: Japan Bank for International 
Cooperation: (JBIC): All applicants submit a completed environmental 
questionnaire, which is used for categorizing potential projects; 
United Kingdom: Export Credit Guarantee Department: (ECGD): ECGD 
screens applications to determine need for further environmental 
information. Applicants for high impact projects must submit a full 
Environmental Impact Assessment (EIA). Applicants for medium impact 
projects must complete an impact questionnaire. Applicants for low 
impact projects have no further requirements; United States: Export 
Import Bank: (Ex-Im Bank): Applications for projects above the 
threshold(s) must include a screening document, which allows Ex-Im to 
determine if an environmental review is necessary, and if so, the scope 
of that review. Applications for projects below the threshold(s) are 
screened internally to determine if a review is necessary.

Impact categories; Belgium: Office National du Ducroire: (OND): High 
impact (Category A) Project has a definitive negative impact on the 
environment, and requested coverage is for more than 10 million SDR; 
Medium impact (Category B) Project has an uncertain impact on the 
environment or has a definitive negative impact on the environment but 
requested coverage is less than or equal to 10 million SDR; Low impact 
(Category C) Project has no impact on the environment, or the impact is 
positive; Canada: Export Development Canada: (EDC): High impact 
(Category A) Project is likely to have significant adverse impacts that 
are sensitive, diverse, or unprecedented and may affect an area broader 
than the sites subject to physical works; Medium impact (Category B) 
Project has potential adverse impacts that are less adverse than those 
of category A projects and are site-specific and rarely irreversible. 
Mitigation measures are more readily available; Low impact (Category 
C) Project is likely to have minimal or no adverse impacts; France: 
Coface: High impact (Category A) Project has potentially significant 
adverse impact; Medium impact (Category B) Project has potentially 
adverse impacts, which may require additional review; Low impact 
(Category C) Project has little or no impacts; Germany: Hermes: High 
impact (Category A) Project is assumed to have strong ecological, 
social, or developmental impacts, which in most cases appear to be not 
locally limited and/or reversible; Medium impact (Category B) Project 
is assumed to have limited ecological, social, or developmental 
impacts, which usually appear to be locally limited and reversible; 
Low impact (Category C) Project is expected to have no or only 
insignificant ecological, social, or developmental impacts; Japan: 
Japan Bank for International Cooperation: (JBIC): High impact (Category 
A) Project is likely to have significant, complicated, and/or 
unprecedented adverse impacts that are sensitive and may affect an area 
broader than the sites subject to physical works; Medium impact 
(Category B) Project has potential adverse impacts that are less 
adverse than those of category A projects and are site specific and 
rarely irreversible. Mitigation measures are more readily available; 
Low impact (Category C) Project has little or no adverse environmental 
impacts; United Kingdom: Export Credit Guarantee Department: (ECGD): 
High impact (Category A) Project has potential for major adverse 
impacts on environment, workforce, immediate dependents, or community 
that may not be predictable and are usually irreversible, diverse, or 
sensitive; Medium impact (Category B) Project could cause adverse 
impacts but are unlikely to be as diverse or sensitive as those for 
high impact projects. Remedial measures can be implemented more 
easily; Low impact (Category C) Project is unlikely to cause material 
adverse impacts; United States: Export Import Bank: (Ex-Im Bank): 
High impact (Category B) Project has potential for significant impact 
and/or is a project finance transaction, is associated with a 
hydroelectric or forestry project, or is in or near a sensitive 
location; Medium impact (Category C) Project has potential for some 
impact; Low impact (Category A) Project has little or no potential 
impact. The export is a product not identified with a particular 
project or the project it is identified with is in one of several 
exempt sectors.

Environmental review process; Belgium: Office National du Ducroire: 
(OND): High impact Environmental impact assessment is requested and 
then assessed using OND's internal checklist ; Medium impact Exporter 
must complete extensive questionnaire, analyzed by the underwriter 
according to an objective scoring method. If the questionnaire 
indicates an acceptable impact on the environment, the review is 
complete. If an important impact on the environment is indicated, OND 
refuses the project unless mitigation measures are put in place or an 
EIA is submitted; Low impact; No further review required; Canada: 
Export Development Canada: (EDC): High impact Environmental impact 
assessment (or comparable report) must be carried out by an independent 
expert not affiliated with the project; Medium impact; Scope and form 
of environmental review may vary from project to project; Low impact; 
No environmental review is required beyond such information as may be 
required for project categorization; France: Coface: High impact 
Environmental review is based on the EIA submitted by the applicant. 
The review assesses the potential environmental impact of the project 
and the results are checked against the environmental regulations of 
the host country and international standards; Medium impact 
Environmental review is based on additional environmental provided by 
the applicant and consultation with the project stakeholders, including 
sponsor, exporter, and other sources; Low impact; No environmental 
review required beyond screening; Germany: Hermes: High impact 
Applicant submits an exhaustive description of all relevant 
environmental aspects; Medium impact Plausible criteria for 
environmental relevance or generally acceptable information is 
sufficient; Low impact No further information required; Japan: Japan 
Bank for International Cooperation: (JBIC): High impact Environmental 
impact assessment is required and JBIC will likely visit the project 
site. If the project results in large-scale resettlement, applicants 
must submit a resettlement plan. JBIC's environmental review is based 
on the EIA and other reports prepared by project proponents and 
submitted through the borrower; Medium impact; Scope and form of 
environmental review may vary from project to project but will examine 
potential positive and negative effects and mitigation options. JBIC's 
environmental review is based on information; United Kingdom: Export 
Credit Guarantee Department: (ECGD): High impact EIA (or other 
comparable assessment) must be carried out, with inputs from experts; 
Medium impact; Full review of application forms and impact 
questionnaire undertaken; Low impact Initial screening of the 
application forms with no further review of the project; United 
States: Export Import Bank: (Ex-Im Bank): High impact Applicant 
required to submit an EIA, on which Engineering and Environment 
Department bases its evaluation of the project; Medium impact 
Applicant must submit sufficient information for Engineering and 
Environment Department to determine if the project adheres to Ex-Im 
guidelines; Low impact No further review is required.

Japan: Japan Bank for International Cooperation: (JBIC): Public 
disclosure of environmental information: provided by borrowers and 
related parties; Low impact; No environmental review is required 
beyond such information as may be required for project categorization; 
United Kingdom: Export Credit Guarantee Department: (ECGD): Public 
disclosure of environmental information: No; United States: 
Export Import Bank: (Ex-Im Bank): Public disclosure of environmental 
information: No.

Public disclosure of environmental information; Belgium: Office 
National du Ducroire: (OND): No commitment to providing public with 
project information before or after making a financing decision, due to 
national regulations; Canada: Export Development Canada: (EDC): No 
commitment to providing public with project information before making a 
financing decision, but encourages project sponsors to make information 
available; makes limited project information available after export 
credit agreement is signed; France: Coface: No commitment to 
providing public with project information before making a financing 
decision; publishes some projects' environmental assessments after 
making financing decision; Germany: Hermes: No commitment to 
providing public with project information before making a financing 
decision, but says will publish information about large and sensitive 
projects, after making a financing decision, with consent from 
exporter; Japan: Japan Bank for International Cooperation: (JBIC): 
Commitment to providing public with project information before making a 
financing decision, with consent of exporter; will publish information 
on its Web site prior to making financing decision; encourages public 
input; United Kingdom: Export Credit Guarantee Department: (ECGD): 
Commitment to providing public with project information before making a 
financing decision, with consent from exporter; will publish 
information on its Web site, prior to making financing decision; 
United States: Export Import Bank: (Ex-Im Bank): Commitment to 
providing public with project information before making a financing 
decision, requiring exporter to permit release of its project's EIA. 
Will publish information on high and medium impact projects on its Web 
site prior to making financing decision, as well as information on how 
to obtain a project's EIA. Encourage public comments on potential 
projects.

Technical standards used; Belgium: Office National du Ducroire: (OND): 
Use both host country and international standards; Canada: Export 
Development Canada: (EDC): No single set of standards; benchmarking 
based on standards from World Bank, regional development banks, Canada, 
World Health Organization; France: Coface: Developed own standards 
for three industry sectors, using World Bank standards, and industry 
best practices as benchmarks; Germany: Hermes: No single set of 
standards; projects have to meet host country standards or applicants 
can explain why they do not; host country standards are then compared 
with international standards; Japan: Japan Bank for International 
Cooperation: (JBIC): Benchmarking based on standards from host country 
and international organizations; JBIC will consult with stakeholders 
for projects that do not meet either of these standards; United 
Kingdom: Export Credit Guarantee Department: (ECGD): Benchmarking based 
on standards from several sources: World Bank Group, UK/EU standards, 
industry best practices, regional development banks; United States: 
Export Import Bank: (Ex-Im Bank): All projects must meet Ex-Im's own 
standards, as adapted from World Bank standards, and host country 
standards.

Source: GAO analysis based on OECD and county documents.

[End of table]

[End of section]

Appendix V: Comments from the Department of the Treasury:

DEPARTMENT OF THE TREASURY WASHINGTON, D.C. 20220:

August 28, 2003:

Loren Yager:

Director, International Affairs and Trade U.S. General Accounting 
Office:

441 G Street, N. W. Washington, D.C. 20548:

Dear Mr. Yager:

Thank you for providing the opportunity to comment on GAO's draft 
report entitled, "Export Credit Agencies: Movement Toward Common 
Environmental Guidelines, but National Differences Remain" (GAO-03-
1093).

We were glad to assist your staff in understanding the fairly complex 
negotiating history of this subject. Since your review began in late 
2002, I hope that the meetings and other communications between our 
organizations have been helpful to GAO's task.

We find your report to be a thorough and thoughtful analysis of the 
OECD process and effort to develop common environmental guidelines for 
export credit agencies. It was a difficult task to convince export 
credit agencies to introduce entirely new considerations into their 
analyses, when those analyses have historically been purely financial 
in nature. Despite the fact that a formal OECD agreement has not yet 
been reached, we believe that U.S. leadership on this issue has had a 
significant impact on highlighting the environmental issue among export 
credit agencies generally. We consider this to be a positive outcome in 
any event.

We look forward to the upcoming OECD negotiations and hope that they 
will be an opportunity to further improve upon the draft OECD agreement 
known as "Common Approaches.":

Thank you again for a well-balanced report.

Sincerely,

Clay Lowery:

Deputy Assistant Secretary:

Debt, Development and Quantitative Policy:

Signed by Clay Lowery:

[End of section]

Appendix VI: Comments from the Export-Import Bank:

EXPORT-IMPORT BANK OF THE UNITED STATES:

September 8, 2003:

Dear Mr. Yager:

Thank you for providing the Draft GAO report entitled "Export Credit 
Agencies: Movement toward Common Environmental Guidelines, but National 
Differences Remain".

The Export-Import Bank of the United States ("Ex-Im Bank") believes 
that the draft provides a thorough analysis of the events and positions 
that have led to the present level of ECA environmental review 
procedures. Moreover, Ex-In Bank agrees with the GAO's observations 
that, despite real progress over the past couple of years in a number 
of national ECA review procedures (including the introduction of World 
Bank standards and information sharing regimes), the broad nature of 
the Common Approaches framework does not yet contain the provisions 
necessary to level the playing field for U.S. exporters. Ex-Im Bank's 
objective has always been to provide a transparent process and clear, 
predictable procedures to ensure that U.S. exporters' competitiveness 
is not impaired by the flexible implementation of environmental review 
procedures by other ECAs.

Ex-Im Bank appreciates the opportunity to comment on the draft report.

Sincerely,

James C. Cruse 
Senior Vice President - Policy:

Signed by James C. Cruse: 

[End of section]

Appendix VII: GAO Contacts and Staff Acknowledgments:

GAO Contacts:

Celia Thomas, (202) 512-8987 Anthony Moran (202) 512-8645:

Acknowledgments:

In addition to the persons named above, Stephanie Robinson, Ming Chen, 
Laura Yannayon, Sarah Ellis Peed, Rona Mendelsohn and Jane-yu Li made 
key contributions to this report.

:

(320158):

:

:

FOOTNOTES

[1] Export credit agencies are public institutions that provide 
official assistance in the form of government-backed loans, guarantees, 
and insurance to private corporations that do business abroad, 
particularly in the developing world. 

[2] The OECD is an organization of 30 industrialized countries, 
operating by consensus, that fosters dialogue among members to discuss, 
develop, and refine economic and social policies and provides an arena 
for setting rules when multilateral agreements are necessary. 

[3] Turkey agreed to adhere to all provisions of the Common Approaches 
with the exception of a provision in Annex I of the Common Approaches 
dealing with locations significant to ethnic groups.

[4] The G-8 is a group of industrialized countries whose heads of state 
meet annually to discuss economic and political issues.

[5] Twenty-nine of the 30 OECD members participate in the ECG, a forum 
to review export credit issues; this is the setting in which the 
negotiations on environmental standards for ECAs took place. 

[6] The World Bank Group is made up of the original "World Bank"--the 
International Bank for Reconstruction and Development--as well as the 
International Development Association, the International Finance 
Corporation, the Multilateral Investment Guarantee Agency, and the 
International Center for Settlement of Investment Disputes. 

[7] Ex-Im Bank's environmental guidelines were last revised in April 
1998. The current guidelines will remain in effect until March 31, 
2004, having been extended several times. According to Ex-Im Bank 
officials, some aspects of the guidelines need to be updated, although 
a specific time frame for that has not been announced due to 
uncertainty with regard to the final outcome of negotiations on the 
Common Approaches. 

[8] For more information about this campaign, see http://www.eca-
watch.org/.

[9] The Ex-Im Bank's environmental tables address the following areas: 
air quality; water use and quality; waste management; natural hazards; 
ecology; socioeconomic and sociocultural framework; and noise.

[10] An environmental impact assessment is a report that evaluates a 
project's potential environmental risks and impacts, examines project 
alternatives, identifies potential project improvements that could 
minimize or mitigate any adverse impacts, and suggests mitigation and 
management measures that should be put in place to address potential 
impacts. Generally, the applicant contracts with independent experts to 
carry out the environmental impact assessment.

[11] Ex-Im Bank officials emphasize that the Bank does not release 
confidential business information. Its ex ante disclosure includes 
project description and location for medium review projects, and the 
project's environmental impact assessment for full review projects, 
with any confidential information removed.

[12] "Greenfield site" generally refers to an area of land on which 
there previously has not been any commercial development beyond that of 
agriculture. 

[13] The subgroups are hydroelectricity, oil and gas, power, and pulp 
and paper.

[14] The 15 banks that have signed on to the Equator Principles are ABN 
AMRO Bank NV, Barclays Bank PLC, Citigroup Inc., Credit Lyonnais, 
Credit Suisse Group, Dresdner Bank, HSBC Group, HVB Group, ING Group, 
MCC, Rabobank, Royal Bank of Canada, Royal Bank of Scotland, WestLB AG, 
and Westpac Banking Corporation.

[15] Four of the 42 transactions were nuclear projects, which are 
subject to separate environmental procedures and guidelines.

[16] Ex-Im Bank's Vice President for Engineering and Environment can 
determine that those applications receive an environmental review in 
certain cases.

[17] For medium review projects, 62 out of 181 were in the energy 
sector, accounting for 52 percent of long-term authorized financing.

[18] These are projects that do not have the same degree of financial 
backing of host governments, financial institutions, or established 
corporations, and thus present greater financial risk to Ex-Im Bank. 
Ex-Im Bank defines the term "project finance" as the financing of 
projects that are dependent on project cash flows for repayment, as 
defined by the contractual relationships within each project. 

[19] Thirty four of the 38 non-nuclear projects undergoing full 
environmental review were project finance transactions.

[20] For a description of Ex-Im Bank's energy sector financing over the 
past decade, see U.S. General Accounting Office, Export-Import Bank: 
Energy Financing Trends Affected by Various Factors, GAO-02-1024 
(Washington, D.C. 2002).

[21] A gigawatt is a unit of electric generation capacity. According to 
the U.S. Department of Energy, U.S. total installed electric generating 
capacity was 813 gigawatts as of 2001.

[22] The Ex-Im Bank Board of Directors reviews the environmental 
effects of projects on a case-by-case basis, and may approve a project 
that does not meet all Ex-Im Bank environmental guidelines, considering 
significant mitigating effects and circumstances. Financing may be 
conditioned on the implementation of mitigating measures.

[23] Ex-Im Bank maintains limitations on the level of foreign content 
that may be included in an Ex-Im Bank financing package. To be eligible 
for Ex-Im Bank financing, goods and services in a U.S. supply contract 
must be shipped from the United States to a foreign buyer. Ex-Im Bank 
will finance goods and services at the lesser amount of either 85 
percent of the value of all eligible goods and services in the U.S. 
supply contract; or 100 percent of the U.S. content in all eligible 
goods and services in the U.S. supply contract.

[24] Ex-Im Bank guidelines require that for its projects in its full 
environmental review category, Ex-Im Bank will make available to 
interested parties a copy of the project's environmental impact 
assessment during the application review process. 

[25] Proven reserves are mineral reserves considered economically 
viable for extraction and that have been explored sufficiently to make 
reliable estimates of the reserve volume, tonnage, and quality.

GAO's Mission:

The General Accounting Office, the investigative arm of Congress, 
exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability.

Obtaining Copies of GAO Reports and Testimony:

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics.

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading.

Order by Mail or Phone:

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to:

U.S. General Accounting Office

441 G Street NW,

Room LM Washington,

D.C. 20548:

To order by Phone: 

Voice: (202) 512-6000:

TDD: (202) 512-2537:

Fax: (202) 512-6061:

To Report Fraud, Waste, and Abuse in Federal Programs:

Contact:

Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov

Automated answering system: (800) 424-5454 or (202) 512-7470:

Public Affairs:

Jeff Nelligan, managing director, NelliganJ@gao.gov (202) 512-4800 U.S.

General Accounting Office, 441 G Street NW, Room 7149 Washington, D.C.

20548: