Joint Strike Fighter: Accelerating Procurement before Completing Development Increases the Government's Financial Risk

GAO-09-303 March 12, 2009
Highlights Page (PDF)   Full Report (PDF, 51 pages)   Accessible Text   Recommendations (HTML)

Summary

The Joint Strike Fighter (JSF) is the Department of Defense's (DOD) most complex and ambitious aircraft acquisition, seeking to simultaneously produce and field three different versions of the aircraft for the Air Force, Navy, Marine Corps, and eight international partners. The total investment required now exceeds $1 trillion--more than $300 billion to acquire 2,456 aircraft and $760 billion in life cycle operating and support costs, according to program estimates. The Ronald W. Reagan National Defense Authorization Act for Fiscal Year 2005 requires GAO to review the JSF program annually for 5 years. This is the fifth and final report under the mandate in which GAO (1) determines the program's progress in meeting cost, schedule, and performance goals; (2) assesses manufacturing results and schedule risks; and (3) evaluates development test plans, progress, and risks. GAO's work included analyses of a wide range of program documents, cost data and interviews with defense and contractor officials.

JSF development will cost more and take longer than reported to the Congress last year, and DOD wants to accelerate procurement. Two recent estimates project additional costs ranging from $2.4 billion to $7.4 billion and 1 to 3 more years to complete development. Despite cost and schedule troubles, DOD wants to accelerate JSF procurement by 169 aircraft from fiscal years 2010 through 2015; this could require up to $33.4 billion in additional procurement funding for those 6 years. DOD plans to procure hundreds of aircraft on cost-reimbursement contracts, magnifying the financial risk to the government. Ongoing manufacturing inefficiencies and parts problems have significantly delayed the delivery of test assets. The prime contractor has extended manufacturing schedules three times and delivered 2 of 13 test aircraft. The program is still recovering from earlier problems that resulted in design changes, late parts deliveries, and inefficient manufacturing. The contractor is taking positive steps to improve operations, the supplier base, and schedule management. Schedule risk analyses could further enhance management insight into problem areas and inform corrective actions. Officials expect to deliver all test aircraft and fix many problems by 2010. By then, DOD plans to have purchased 62 operational aircraft and will be ramping up procurement. Procuring large numbers of production jets while still working to deliver test jets and mature manufacturing processes does not seem prudent, and looming plans to accelerate procurement will be difficult to achieve cost effectively. DOD's revised test plan adds a year to the schedule, better aligns resources and availability dates, and lessens the overlap between development and operational testing, but it still allows little time for error discovery and rework. DOD's decision late in 2007 to reduce test aircraft and flight tests adds to risks while any additional delays in delivering test aircraft will further compress the schedule. The revised plan relies on state-of-the-art simulation labs, a flying test bed, and desk studies to verify nearly 83 percent of JSF capabilities. Only 17 percent is to be verified through flight testing. Despite advances, the ability to so extensively substitute for flight testing has not yet been demonstrated. Significant overlap of development, test, and procurement results in DOD making substantial investments before flight testing proves that the JSF will perform as expected. Under the accelerated procurement plan, DOD may procure 360 aircraft costing an estimated $57 billion before completing development flight testing.



Recommendations

Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Open," "Closed - implemented," or "Closed - not implemented" based on our follow up work.

Director:
Team:
Phone:
Michael J. Sullivan
Government Accountability Office: Acquisition and Sourcing Management
(937) 258-7915


Recommendations for Executive Action


Recommendation: To enhance congressional oversight, increase the likelihood of more successful program outcomes, and maintain confidence that the program is on track to meet planned cost, schedule, and performance goals, the Secretary of Defense should direct the Under Secretary of Defense for Acquisition, Technology and Logistics to report to the congressional defense committees by October 1, 2009. This report should include, at minimum (1) an explanation of the cost and other risks associated with a cost-reimbursable contract as compared to a fixed-price contract for JSF's future low-rate production quantities, (2) the program's strategy for managing and mitigating risks associated with the use of cost contracts, and (3) plans for transitioning to fixed-price contracts for production to include time frames and criteria.

Agency Affected: Department of Defense

Status: Open

Comments: In providing comments on this report, the agency generally concurred with this recommendation but has yet to take any actions necessary to implement it. However, in its letter to the Congress, OSD plans to provide a report to the Congressional Defense Committees by the fall of 2009 to address the requirements of this recommendation. As part of our 2010 review of the Joint Strike Fighter program, we will continue to monitor the program's contracting strategy for procurement and, if possible, obtain a copy of the October 2009 report to the committees.

Recommendation: To enhance congressional oversight, increase the likelihood of more successful program outcomes, and maintain confidence that the program is on track to meet planned cost, schedule, and performance goals, the Secretary of Defense should direct the JSF Program Office to ensure that the prime contractor performs periodic schedule risk analyses for the JSF program to provide better insight into management reserve, production efficiencies, and schedule completion to allow for corrections as early as possible.

Agency Affected: Department of Defense

Status: Open

Comments: In providing comments on this report, the agency concurred with this recommendation and, according to an official from the Office of the Undersecretary of Defense for Acquisition, Technology, and Logistics, the prime contractor has taken initial steps to implement it. We will continue to monitor the contractor's schedule risk analysis efforts as part of our 2010 review of the Joint Strike Fighter program.


Related Searches

Related terms: