‘Cleanup’ Category

Subscribe to this category's feed

Dredging Challenges Contribute to Spikes in Air and Water Monitoring

Friday, August 7th, 2009
go to EPA's Hudson cleanup site
In 2009 dredging began in the Upper Hudson River to remove sediments with PCBs. Read more.

Last week, media who routinely cover the Hudson dredging project ran several stories about increased PCB levels recorded by EPA for both water and air monitoring. Be assured, water and air quality are being closely monitored, and EPA is working with the New York State Department of Health to ensure there are no immediate risks to people’s health. People can track the monitoring at www.hudsondredgingdata.com. I thought I would take this edition of the blog to clarify what happened on the river last week and tell you what was done about it.

Since the beginning of the project, dredging has taken place around Roger’s Island, one of the most heavily contaminated areas of the river and one of the most complex areas to dredge, due to physical conditions such as shallow water depths and a river bottom of uneven bedrock. We’ve found sediment in this area contains very high levels of PCBs mixed with a tremendous amount of small debris (i.e. tree limbs, etc.). In addition, since May 15, more and more dredges have been added throughout the six-mile project location, and we are nearly operating at full capacity (12 dredges, 18 barges and 18 tugboats).

Last week, when GE staged several dredges in a particularly contaminated area, the monitoring numbers began to elevate. Levels of PCBs in the water were measured as high as 514 parts per trillion at the first monitoring station (located near Thompson Island) on Saturday, August 2, which is above the drinking water standard of 500 ppt. At the same time, the river had started to rise and the flows were starting to exceed the safety level of 10,000 cubic feet per second, so the dredging was halted.

If PCB levels reach the drinking water standard, and are confirmed by two subsequent lab samples, any dredging activities that may have caused the exceedance will be halted until EPA is satisfied that the proper changes have been put into place to lower the levels. The two follow-up water samples came back below the drinking water standard, so EPA determined there had been a spike in the PCB levels, and it was probably because of the combination of dredging and high river flows from recent rain events. After that determination, EPA told GE it was okay to dredge again, once the river flows decreased to less than 10,000 cubic feet per second. As of Monday evening, August 3, the dredging had resumed. Additional water samples have been taken at Thompson Island and are all below the drinking water standard, and samples taken further downriver are well below the standard. Those results can be found at www.hudsondredgingdata.com .

The air standards are equally protective. The standard for exposure for PCBs in the air in residential areas, for instance, is based on levels that would be acceptable for a child under the age of six to breathe 24 hours a day for 365 days a year for six years. If that standard is exceeded, EPA and New York State investigate, and GE is directed to take actions to decrease the levels and provide sampling results faster to help identify the cause of the spikes.

So what actions were taken - we determined the combination of too many dredges in a heavily contaminated area and the release of vapors from barges loaded with contaminated sediment drying out in the sun were key contributors to the monitoring spikes. As a corrective measure EPA has now required that dredging be scaled back in the highly contaminated area around Roger’s Island and that the barges with high concentrations of PCBs are loaded evenly, that they are kept wet to prevent PCBs from evaporating into the air, and that they are immediately off-loaded into an enclosed storage structure at the dewatering facility. These measures have worked to dramatically reduced levels of PCBs in the air and the water.
About the author: Kristen Skopeck is originally from Cedar Rapids, Iowa. She is an 11-year Air Force veteran and was stationed in California, Ohio, Texas, Portugal, and New York. After working for the USDA for three years, Kristen joined EPA in 2007 and moved to Glens Falls, NY to be a member of the Hudson River PCB dredging project team. She likes to spend her time reading, writing, watching movies, walking, and meeting new people.

What Is Happening With The Sediment Being Dredged From The Hudson River?

Friday, July 17th, 2009
go to EPA's Hudson cleanup site
In 2009 dredging began in the Upper Hudson River to remove sediments with PCBs. Read more.

I was viewing the dredging from the Fort Edward yacht basin with many curious onlookers recently, and people wanted to know what would become of the PCB-laden dirt and debris.

I told them the barge in front of us was nearly filled to capacity and would soon be moved by tugboat to a processing facility. A 110-acre facility specially constructed on the Champlain Canal between Locks 7 and 8 in Fort Edward is the sole processing facility for the project’s dredged material. There, the sediment and debris is sorted to remove remaining sand, sticks, silt and rocks (anything larger than 5/8 of an inch in diameter is separated from smaller material). Water is added to the remaining PCB-laden dirt to create slurry and to help move the material through pipes to 12 specially manufactured filter presses housed inside a sediment dewatering building. The presses squeeze the slurry to remove the water, and the water goes to a water-treatment plant to be cleaned to drinking-water standards before being returned to the Champlain Canal. The material remaining is called “filter cake.” The cake is then placed inside impervious liners inside railcars that make up 81-car trains. These trains leave the area every few days on their way to a licensed disposal facility in Andrews, Texas.

Right now, as the flow of the river allows, dredging operations are taking place 24 hours a day, six days a week, (Sundays are reserved for contingencies and maintenance) and sediment and water treatment are taking place around the clock, seven days a week. The project has 450 dedicated railcars continuously looped between here and the disposal facility. More information about this project can be found at the following websites: www.epa.gov/hudson/ and www.hudsondredging.com/.

About the author: Kristen Skopeck is originally from Cedar Rapids, Iowa. She is an 11-year Air Force veteran and was stationed in California, Ohio, Texas, Portugal, and New York. After working for the USDA for three years, Kristen joined EPA in 2007 and moved to Glens Falls, NY to be a member of the Hudson River PCB dredging project team. She likes to spend her time reading, writing, watching movies, walking, and meeting new people.

Clamshell Buckets? Are they the Right Choice for the Project?

Friday, June 26th, 2009
go to EPA's Hudson cleanup site
In 2009 dredging began in the Upper Hudson River to remove sediments with PCBs. Read more.

I’ve had many people ask me why the dredging is being performed with environmental clamshell buckets instead of using the hydraulic (with a hose and suction) method. These people point to the fact the clamshells are encountering a large volume of logs, sticks and wood shavings, which prohibit the jaws of the buckets from closing tightly and cause water to spill out as the buckets are raised from the river bottom.

Interestingly, that copious river debris (a casualty of the Adirondack logging trade) is one of the main reasons hydraulic dredging wouldn’t work well for this project. That debris – and the rocky nature of the river bottom – would clog hoses and greatly hinder dredging progress. Furthermore, the project spans 40 miles, so using hydraulic dredges would require an extensive infrastructure of pipeline and pump stations up and down the river corridor. But the most important factor is that engineers determined the resuspension of sediment is nearly the same using either method of dredging. Resuspension occurs when the river bottom is disturbed and dirt (in this case dirt with PCBs clinging to it) gets churned up. When this happens, the water-born sediments float downstream, so keeping resuspension to a minimum is an important project goal.

It is important to remember that PCB-tainted sediment dropping out of the clamshells typically settles to the bottom in a relatively short distance and gets removed in subsequent passes of the dredge. Moreover, PCB levels during all dredging operations are closely and continuously monitored to ensure compliance with EPA’s resuspension standard. And, so far, the monitoring has shown the sediment resuspension hasn’t caused an the drinking water standard for PCBs to be exceeded, and the first monitor is only one mile downstream of the dredging. Information about the monitoring for the project can be found at this site: www.hudsondredgingdata.com/. All things considered, the decision to use clamshell buckets was the right one.

About the author: Kristen Skopeck is originally from Cedar Rapids, Iowa. She is an 11-year Air Force veteran and was stationed in California, Ohio, Texas, Portugal, and New York. After working for the USDA for three years, Kristen joined EPA in 2007 and moved to Glens Falls, NY to be a member of the Hudson River PCB dredging project team. She likes to spend her time reading, writing, watching movies, walking, and meeting new people.

Memories of the Cuyahoga River

Monday, June 22nd, 2009

This month is the 40th anniversary of the Cuyahoga River catching on fire. I was born and grew up in Cleveland on the east side. The 1969 river fire occurred between my junior and senior years of high school. I remember being embarrassed that this could happen in my home town. I remember the beaches near the city being closed and traveling all the way out to Mentor to go swimming. While in college, during the early 1970’s I worked on an ore boat that occasionally docked on the river and in the Republic Steel mill. The river was a place to work.

After working in Chicago briefly, I returned to Cleveland in 1976. I moved to the west side of Cleveland , which for an eastsider was another world. The Cuyahoga River and the Flats became a meeting area for me, as I traveled between the west side and my east side roots. In the later 1970’s and early 1980’s I remember the Flats became the entertainment hotspot. Outdoor concerts were held on Fridays after work and it seemed as though everyone was there. I meet my wife at Fagans, the old east side bar, when it still had that shot and a beer feel. The river still looked dirty but oil slicks were rare and it didn’t catch fire anymore.

image of boat that looks like a duck and is made from milk cartons. This milk carton boat was built and raced by some of the EPA staff here in the Cleveland office during the Krazy Kraft Race which was part of the Flats Fest in July 1991.

In the 1980’s and 1990’s I was busy working and raising a family. Although I had settled in Bay Village , my family and I continued to come to the river. Shooters, the Powerhouse, Goodtime cruises, river festivals with milk carton boat races and concerts brought my family and I back to the river. Upstream the Cuyahoga Valley National Park became a biking destination. Now the bike trails go from Akron to the lake.

I’ve noticed the river has begun to look scenic. When did it become a place to take people visiting from out of town instead of a punch line for a Cleveland joke? I don’t know, but I’m happy it did.

If you have photos or memories of the Cuyahoga River either today or way back when, please share them with the rest of us along with your stories either by commenting directly on our blog, or posting your photos to our Flickr page at http://www.flickr.com/groups/epa-cuyahoga40th/

Mark Moloney works in EPA’s Cleveland Office and is an environmental engineer who has been with the agency since 1974. He does multimedia investigations and other projects for the Enforcement Compliance Assurance Team and in the early 90s became the EPA’s to the Cuyahoga River RAP Organization.

A Tale of Two Phases

Friday, June 19th, 2009
go to EPA's Hudson cleanup site
In 2009 dredging began in the Upper Hudson River to remove sediments with PCBs. Read more.

Phase 1 of the Hudson River dredging project provides a chance to evaluate whether the equipment and methods being used are adequate to meet the project’s cleanup goals. This phase is underway and will continue until the beginning of November. So far, dredging has removed more than 16,000 cubic yards of the river bottom. You can follow the project’s productivity at the following website: www.hudsondredgingdata.com/

That website also provides information about the various types of monitoring being done to ensure the project is performed in a way that is protective of human health and the environment.

The design elements to be scrutinized during Phase 1 include the equipment selected for dredging sediment and transporting dredged materials to the sediment processing facility, PCB resuspension control and monitoring equipment, the processes and equipment used for dewatering and stabilizing the dredged material and for treating water generated during sediment processing, the rail infrastructure designed for transport of processed dredged materials to the final disposal location in Texas, and the methods and equipment used to backfill dredged areas and, in certain areas, to reconstruct habitat. EPA will be watching all of these project components closely.

At the end of Phase 1 dredging and prior to the start of Phase 2 dredging, EPA and an independent scientific panel will separately evaluate the project to determine whether the dredging design or dredging operations should be modified for the final phase. If all goes according to plan the entire project will be complete by November of 2015.

About the author: Kristen Skopeck is originally from Cedar Rapids, Iowa. She is an 11-year Air Force veteran and was stationed in California, Ohio, Texas, Portugal, and New York. After working for the USDA for three years, Kristen joined EPA in 2007 and moved to Glens Falls, NY to be a member of the Hudson River PCB dredging project team. She likes to spend her time reading, writing, watching movies, walking, and meeting new people.

You Can Still Enjoy the River During Dredging

Wednesday, June 17th, 2009
go to EPA's Hudson cleanup site
In 2009 dredging began in the Upper Hudson River to remove sediments with PCBs. Read more

With the formidable, 40-mile-long Hudson River dredging project underway, some people may have the idea that the river is off limits for recreation, but this isn’t the case. Granted there are a lot of project vessels on the water, especially around Rogers Island in Fort Edward, but by taking basic precautions for safety, people can use the river in all the ways they have in the past. As a matter of fact, the flurry of activity involves a lot of neat construction equipment, and people can visit the yacht basin in Fort Edward to see the dredging up close and personal.

To scoop the 400,000 tons of sediment (more than 94 acres) targeted this year, GE has mobilized an armada of equipment, including 11 dredges, 17 tugboats, 20 barges, and more than 400 rail cars, as well as skiffs, cranes and other machinery. At peak dredging during July and August, as many as 80 to 90 vessels are expected to be in the river each day. That’s a lot of water traffic congestion in a relatively narrow section of the Upper Hudson, but the river remains navigable by commercial and recreational boaters and open to water skiers, kayakers, swimmers, and anglers.

Boaters traveling in areas where dredging is being performed are being asked to avoid work areas, which are marked by buoys. New York State Canal Corporation regularly posts project information for boaters on their website. EPA and the New York State Department of Health representatives have been telling people recreational activities such as swimming and water skiing are acceptable during dredging, but individuals should try to avoid the immediate areas where dredging is being performed to minimize the potential for exposure. Also, people are being reminded to wash off after going in the water, not just because of PCBs, but because unfiltered river water is known to contain bacteria, viruses and other “bugs” that can make people sick. People are surprised to learn that they can still swim in the river with the project going on, but the main risk of exposure to PCBs at dangerous levels is through eating contaminated fish — and, for now, fish are strictly for catch and release in the Upper Hudson.

About the author: Kristen Skopeck is originally from Cedar Rapids, Iowa. She is an 11-year Air Force veteran and was stationed in California, Ohio, Texas, Portugal, and New York. After working for the USDA for three years, Kristen joined EPA in 2007 and moved to Glens Falls, NY to be a member of the Hudson River PCB dredging project team. She likes to spend her time reading, writing, watching movies, walking, and meeting new people.

Remains of Historical Vessels at Rest in the River

Friday, June 5th, 2009

image of authorAbout the author: Kristen Skopeck is from Cedar Rapids, Iowa. She is an Air Force veteran who joined EPA in 2007 to be a member of the Hudson River PCB dredging project team. She likes to spend her time reading, writing, watching movies, walking, and meeting new people.

go to EPA's Hudson cleanup site
In 2009 dredging began in the Upper Hudson River to remove sediments with PCBs. Read more.

Last week, a team of archaeologists and divers evaluated the remains of a late-18th or early-19th Century boat long submerged in the eastern channel of Rogers Island. Enough of the boat was intact to see that it had a distinctive centerboard keel slot technology that was an important innovation in early American shipbuilding. Divers used a small hydraulic dredge (similar to a vacuum) to further expose the vessel, screened the dredged sediment, measured the vessel, and took photos and video of the work. Afterward, the vessel was exhumed in pieces and added to a collection of other large debris, like tree stumps, that will ultimately be disposed of at a permitted landfill. Unfortunately, the boat’s deterioration and its coating of PCB-contaminated sediment prevented it from being brought to the surface and restored.

The entire PCB-removal project has been done in accordance with the National Historic Preservation Act, which states federal agencies must take into account the effects of their actions on any district, site, building, structure or object listed in or eligible for inclusion in the National Register of Historic Places. So far, archeologists have found 10 sunken vessels that are being evaluated in the first phase of the project.

So, how did this boat end up submerged by Rogers Island? Fort Edward’s historian, Paul McCarty, said there is no way to know if the boat was put there for a reason or if it was a wreck, but the odds are that the boat was sunk in an accident and left underwater as a derelict. He hopes the underwater investigation and subsequent report will give some indication of what timeframe the boat met its demise and, maybe, help us understand why it happened.

An Historic Day for the Hudson

Friday, May 22nd, 2009

About the author: Kristen Skopeck is originally from Cedar Rapids, Iowa. She is an 11-year Air Force veteran and was stationed in California, Ohio, Texas, Portugal, and New York. After working for the USDA for three years, Kristen joined EPA in 2007 and moved to Glens Falls, NY to be a member of the Hudson River PCB dredging project team. She likes to spend her time reading, writing, watching movies, walking, and meeting new people.

go to EPA's Hudson cleanup site
In 2009 dredging began in the Upper Hudson River to remove sediments with PCBs. Read more.

Thousands of hours of planning and investigation culminated in the first dredge bucket being lowered into the Upper Hudson River on May 15, 2009. I was there to watch a diverse crowd, many with Cheshire Cat grins and some more dubious, take in the scene, as a bright blue dredge bucket slowly lowered into the water and pulled up a bucketful of PCB-laden muck. Also watching were reporters from many media outlets, and even a group of journalism students, all armed with cameras and itching for interviews. Everyone there was reminded of the 30-plus years of wrangling between EPA, General Electric, environmental groups, and citizens that led up to this historic day.

The 40-miles of the Upper Hudson between Fort Edward and Troy, New York contain thousands of pounds of a potentially cancer-causing chemical called polychlorinated biphenyls, or PCBs. The entire dredging project targets the removal of about 248,600 pounds of PCBs that EPA scientists know are situated in the river in a way that is having a toxic impact on fish. They know because they have studied more than 50,000 sediment samples taken in a polka dot pattern across the 40 miles. Incidentally, they found some pockets of PCBs are buried deeply and shouldn’t be disturbed, but the places being targeted are relatively shallow (many between six inches and three feet) and have to come out.

As the Community Involvement Coordinator on the project, I am the affected peoples’ advocate. It is important to me that people understand how the project is being orchestrated and that EPA’s oversight will ensure it is done in a safe and efficient manner. One of the tools I’ll be using to do so is this blog. I’ll update it regularly, and I’ll invite other project members to join in the dialogue, so we can relate what is happening on the project in a timely, unfiltered way. If you have any specific questions please email me at skopeck.kristen@epa.gov.

Brown 2 Green

Friday, January 9th, 2009

About the author: Rob Lawrence joined EPA in 1990 and is Senior Policy Advisor on Energy Issues in the Dallas, TX regional office. As an economist, he works to insure that both supply and demand components are addressed as the Region develops its Clean Energy and Climate Change Strategy.

I want to relate an exciting initiative upon which EPA Region 6 has embarked. We are working with state and federal agencies, land owners, renewable energy financiers and developers to advocate the use of previously contaminated sites as potential locations for renewable energy production. Together with the New Mexico Energy, Minerals and Natural Resources and the New Mexico Environment departments, Region 6 hosted the conference - Brown to Green: Make the Connection to Renewable Energy.

What might be a previously contaminated site? It could be a Brownfields designated property, a former military installation, a closed municipal landfill or a previously worked mining site. Really, almost any industrial facility could be prepared for a renewable energy use.

What are the merits of these types of sites? In most cases, the properties are less expensive to acquire than a greenfield development. The basic infrastructure – power grid access, water availability and highway arteries are nearby. In some cases, the costs associated in developing a greenfield site, including adding transmission lines could run into the millions of dollars. From an economic standpoint, reuse of a property means that it will be returned to local and state tax rolls for future assessments. And by using a previously developed property, acres of undisturbed lands will remain in their virgin state.

What type of renewable energy is applicable to these sites? As with most real estate developments, the answer to that question is “Location, Location, Location!” EPA and the Department of Energy’s National Renewable Energy Laboratory have mapped the thousands of locations of closed facilities and cross-referenced them with solar and wind capabilities. In the near future, geothermal production capabilities will be added. To get an idea of the potential for properties in your state, and see the state financial incentives for renewable energy, check out: http://www.epa.gov/renewableenergyland/ for more information.

What has EPA done to facilitate this initiative? For the last 6 months, I have led a group working with the City of Houston to assess the regulatory, technical and economic considerations for the development of a 10 MWatt solar farm on a portion of the closed Holmes Road Landfill. With the abundance of sunshine in the Houston area year-round, it would be feasible to use about 100 acres of the 300 acres at the closed landfill for a solar farm. The City is examining its contract options and hopes to make a decision in early 2009 about using the site.

International Coastal Cleanup Day

Thursday, October 9th, 2008

About the author: Brenda Reyes Tomassini joined EPA in 2002. She is a public affairs specialist in the San Juan, Puerto Rico office and also handles community relations for the Caribbean Environmental Protection Division.

Lea la versión en español a continuación de esta entrada en inglés.
Some links exit EPA or have Spanish content. Exit EPA Disclaimer

Just recently, my two eldest daughters and I participated in the Ocean Conservency’s yearly International Coastal Cleanup Day, an effort established by a woman in Texas in 1986. On our Caribbean shores, the Scuba Dogs organization has been coordinating this event for the last 7 years. Thousands participate cleaning up one of our most treasured resource: our beautiful coastline.

As a veteran at these events due to the nature of my job at EPA and my love for a clean environment, I joined my daughters’ team, all students from the environmental club at Colegio Marista. On our early morning drive to Vacía Talega beach on the town of Loíza, I saw dozens of groups ready for a few hours of hard work picking up the abandoned trash. Covering a ten mile stretch of coastal roads, brigades worked retrieving plastic, food wrappers and construction materials, to name a few.

Our group included around 200 students and parents, who worked in various crews from 8AM until 11AM. Those three hours made a difference and taught these young citizens some valuable lessons in environmental stewardship. Not only did they learn about protecting our marine habitats, but how clean beaches contribute towards Puerto Rico’s economy since our beautiful beaches attract tourists from all over the world. Mosquito bites aside, this was a great way to teach an environmental lesson outside the classroom!

I am happy to report that 135 beaches, 23 rivers, 9 lakes, 4 estuaries, and 6 coastal areas were cleaned in Puerto Rico by 11,500 volunteers who picked 235,683 pounds of trash. Did you participate in the International Day Coastal Cleanup? If not, I invite you to take part of this event. If you did, what was your most unusual find?

Día Internacional de Limpieza de Costas

Sobre la autor: Brenda Reyes Tomassini se unió a la EPA en el 2002. Labora como especialista de relaciones públicas en la oficina de EPA en San Juan, Puerto Rico donde también maneja asuntos comunitarios para la División de Protección Ambiental del Caribe.

Recientemente participé junto a mis dos hijas mayores del Día Internacional de Limpieza de Costas. Este día comenzó cuando una dama del estado de Texas coordinó un esfuerzo en 1986 para limpiar las playas de su estado. En Puerto Rico, la organización Scuba Dogs es el coordinador oficial del evento hace 7 años . Este año miles participaron limpiando nuestro más preciado tesoro: nuestras costas.

Aunque ya soy una veterana en estos eventos de limpieza de playas (no importa la época del año) por mi trabajo en la EPA, no desperdicio una oportunidad para unirme a estos esfuerzos y este año no fue la excepción. El club ambiental del Colegio Marista, a dónde asisten mi hijos, adoptó una costa en el área de Vacía Talega en el pueblo de Loíza. Durante nuestro recorrido, y desde temprano en la mañana, pude observar cómo decenas de brigadas, trabajaban recogiendo basura, plástico, materiales de construcción y empaques de comida, entre otras cosas, por un trecho de diez millas bajo el candente sol caribeño.

Nuestro grupo incluyó a cerca de 200 estudiantes y padres que trabajaron arduamente en grupos desde las 8AM y por espacio de 3 horas. Este breve periodo de tiempo sirvió para enseñar a estos jóvenes ciudadanos una lección que no se aprende en un salón de clases: la protección del medioambiente está en manos de cada uno de nosotros y las consecuencias de no hacerlo pueden afectar no solo los hábitats marinos, si no también nuestra economía, ya que nuestra isla depende grandemente del turismo. Aparte de las picadas de mosquito, disfrutamos todos de esta actividad, la cual terminó con un chapuzón en la playa para algunos de los participantes!

El resultado de este esfuerzo fue que 135 playas, 23 ríos, 9 lagos, 4 estuarios y 6 áreas costeras se limpiaron en Puerto Rico por 11,500 voluntarios que recogieron 235, 683 libras de basura. ¿Participó usted del Día Internacional de Limpieza de Costas? Si nunca lo ha hecho, le invito a que participe de este evento. Si participó, ¿cuál fue el artículo más extraño que encontró?