Construction Update

Photo of construction activity on the Rsearch Support Facilities.

View of the formwork for the basement-level stair tower and elevator shaft, located on the north side of the connector between the two building wings.
Credit: Carl Cox

NREL's South Table Mountain campus will be busy with construction activity for the foreseeable future. This page has been created to keep you informed about our expansion, including construction activity updates, information on new facilities and where to find additional information. Updates will be provided weekly and also are available by calling the NREL Construction Hotline at 303-275-4087.

Updated: May 2, 2009

Construction for the the new Research Support Facilities (RSF) continues. Elevator/stair walls are being formed and placed. An additional 190-ton crane is now on site to speed up this work. Basement walls are being formed in the west half of the south wing, underground electrical conduits in the basement area have been installed and sanitary sewer installation continues. Learn more about the RSF building.

For additional information, contact NREL's Public Relations Office at 303-275-4090.


Research Support Facilities

The 218,000 square-foot Research Support Facilities (RSF) are designed to be a model for sustainable, high-performance building design, and will provide DOE-owned work space for administrative staff who currently occupy leased space in the nearby Denver West Office Park. It will make substantial use of daylighting, dramatically reducing energy use and providing a pleasant and productive working environment. The RSF is planned to be designated to achieve a LEED® (Leadership in Environmental and Energy Design) Platinum designation — the highest benchmark awarded by the U.S. Green Building Council. Construction on the RSF is expected to be completed in summer 2010.

Integrated Biorefinery Research Facility

The Integrated Biorefinery Research Facility (IBRF), to be built adjacent to the Process Development Unit in the Alternative Fuel Users Facility, will expand NREL's capabilities to develop new cellulosic ethanol technologies. The IBRF will allow the Laboratory to work simultaneously on multiple research projects with multiple research partners. Construction is scheduled to be completed in 2010.

Energy Systems Integration Facility

The 130,000-square-foot building, to be located southeast of the existing Science & Technology Facility, will house a variety of research that aims to overcome technical barriers to adding new renewable energy generation systems to the electrical grid. As planned, the Energy Systems Integration Facility (ESIF) will be a multi-story building that will provide laboratory and office space for approximately 150 NREL researchers and support staff. Employees could occupy the ESIF as early as 2012.

Renewable Fuel Heating Plant

Construction on the Renewable Fuel Heating Plant (RFHP) is now complete. The boiler started November 20 and is expected to run continuously until spring 2009. The RFHP is located behind the Field Test Laboratory Building and will use wood waste and forest thinnings from Colorado's Front Range for fuel. The plant is expected to displace up to 80 percent of NREL's South Table Mountain natural gas use.

Mesa Top PV Project

The Mesa Top PV Project is a 5-acre field of solar panels built near the NREL Solar Radiation Research Laboratory on top of South Table Mesa. It will produce an estimated 750 kilowatt hours of clean, renewable electric power from solar energy that will be used to power NREL buildings. It was completed in December 2008.