Southern Nevada Public Land Management Act (SNPLMA)
Home |
SNPLMA | Round 5
SNPLMA Round 5
How the Lake Tahoe Round 5 Proposed Project List Was Created
The Lake Tahoe Federal Advisory Committee (LTFAC) Budget Subcommittee
- Tahoe
Working Group met on March 23, 2004 with the federal agencies and developed a
list of priority projects called the "Primary Projects" and an alternate list of
projects called the "Secondary Projects."
Lake Tahoe projects considered for funding had to meet the following minimum criteria:
- Be the responsibility of the federal government in the Environmental Improvement Program (EIP); or
- Have a willing and ready federal sponsor.
The
LTFAC met on April 7, 2004 to review the subcommittee's recommendations
and to hear public comments on the funding proposals. The committee formed a
funding recommendation for Primary and Secondary projects. This recommendation
and all public comments received during a 30-day public comment period were forwarded to the Tahoe Regional Executives.
Follow this link to read their letter:
The Tahoe Regional Executive Committee (TREX) reviewed the
LTFAC
recommendations and public comments. The TREX then sent their
recommendations to the SNPLMA Executive Committee.
Follow this link to read their letter:
Finally, the SNPLMA Executive Committee sent the project lists
and recommendations forward to the Secretary of the Interior, Gale Norton, for final approval and
funding in Round 5.
Proposed Funding
Projects originally submitted for funding totaled $51,658.400. After
prioritization, the requested funding for projects on the Primary List totaled
$47,778.400. This amount was still more than the $37.5 million
allowed. The final recommendation was reduced
to $37,084,900 for all Primary projects. Projects on the Secondary list
totaled $3.88 million and would be funded if funding became available.
Approved Funding and Projects
Secretary of the Interior, Gale Norton, approved the proposed funding and
project lists on August 5, 2004. The final approved funding
amount is $37,084,900. All the projects on the Primary list are approved
and funded. All the projects on the secondary list are approved but
unfunded. Follow this link to view the Secretary of the Interior's
approval document for the Round 5 Lake Tahoe Restoration Projects (PDF 42 KB).
Project Lists
Use this list guide to help you locate the appropriate list of
SNPLMA
Projects:
Please be aware some of these documents are in a PDF format.
Larger files can take several minutes to open. If you have difficulty accessing any of these documents please
Contact Us. The PDF format
requires the Adobe Acrobat Reader to view. If you need the Acrobat Reader, please select the link provided below.
Selecting this link will take you to Adobe's web site. From there, you can download your free copy of the Acrobat Reader
program. Once you've downloaded the Acrobat Reader you will need to use the "back" button on your browser to return to this page.
Get Acrobat Reader
|