Introduction and Background to the Oil
Pollution Prevention Regulation
USEPA Oil Program's Outreach to the Regulated Community
The United States Environmental Protection Agency (EPA), Oil Program has prepared a series of guides to help facilities gain an understanding of and compliance with the Federal Oil Pollution Prevention Regulation, Title 40 Code of Federal Regulations (CFR) Part 112, which includes the Spill Prevention Control and Countermeasure (SPCC) Plan requirements and the Facility Response Plan (FRP) requirements. Under the EPA Oil Program, a workgroup composed of representatives from each EPA regional office and EPA headquarters compiled these materials.
EPA has produced outreach materials for selected industries that demonstrate how the Federal Oil Pollution Prevention Regulation specifically applies to different industries. These guides are for bulk storage facilities, electrical utilities, marinas and other waterside fueling facilities, mines and quarries, farms and ranches, vehicle service facilities, and oil drilling and production facilities. To obtain copies of these publications, facilities should contact any one of the EPA offices listed at the end of this guide.
Oil discharges can have a severe impact
on human drinking water resources located in inland lakes and reservoirs.
Spills also create the potential for explosion and fires which, in turn,
may lead to more equipment failures, more spills, and endangerment to
humans and wildlife.
Moreover, oil pollution seriously damages the terrestrial and aquatic
environment and marine ecosystems. It does not take a spill of catastrophic
magnitude to have a serious impact on an aquatic habitat. The complex
food chain or web, from microorganisms and plants to shellfish, mammals
and birds, is affected by even small spills. In fact, a single pint
of oil released into the water can cover one acre of water
surface area. Ecosystems may take years to recover or may never recover
from spills.
The cost of doing business should not include the cost of responding to accidents after the fact, but rather should include instituting spill prevention through proper operations, maintenance, and training for employees and managers.
The regulations are in place primarily
to require that facilities implement measures that will prevent and
control oil spills that may result due to human operational error or
equipment failure. Facilities that are in full compliance reduce the
number and severity of discharges and do not face the high costs of
environmental cleanup or additional permitting requirements that could
be imposed in the event of a discharge.
Facilities that are not in compliance are
at greater risk to experience an oil spill that may result in a discharge
into a navigable waterway or adjoining shoreline. The cost of cleanup
would not only include repairing the damage to the facility (e.g., soil
removal or equipment repair) but could extend beyond the facility's
boundary to affected offsite areas. Regulators and permitting agencies
may require modifications to operations or revisions to plans.
Heavy fines and penalties are often associated with oil discharges,
especially when negligence can be proven.
Applicability
of the SPCC Requirements
EPA's SPCC requirements (40 CFR 112.1 through
112.7) apply to nontransportation-related fixed facilities that could
reasonably be expected to discharge oil into or upon the navigable waters
of the United States or adjoining shorelines, and that have (1) an aboveground
oil storage capacity of more than 660 gallons in a single container;
or (2) a total aboveground oil storage capacity of more than 1,320
gallons, or (3) a total underground buried storage capacity of more
than 42,000 gallons. The requirements apply specifically
to a facility's storage capacity, regardless of whether the tanks are
completely filled. Some transportation-related facilities or activities
may have components considered to be "fixed" under 40 CFR
Part 112 (e.g., certain tanks at a pipeline facility, trucks containing
product stationed within a fixed facility).
Other facilities may not be regulated if, due to their location, they
could not reasonably be expected to discharge oil into or upon the navigable
waters of the U.S. or adjoining shorelines. This determination is made
without consideration of man-made structures. The majority of facilities
in the U.S. have the potential to discharge to navigable waters.
The facilities subject to 40 CFR Parts 112.1 through 112.7 are required
to prepare an SPCC Plan and conduct an initial screening to determine
whether they are required to develop an FRP. SPCC-regulated facilities
must also comply with other federal, state, or local laws, some of which
may be more stringent.
Those facilities that could cause "substantial
harm" to the environment must prepare and submit an FRP to EPA
for review.
As outlined in 40 CFR 112.20(f)(1), a facility has the potential to
cause substantial harm if:
- The facility transfers oil over water to or from
vessels and has a total oil storage capacity, including
both aboveground storage tanks (ASTs) and underground storage tanks
(USTs), greater than or equal to 42,000 gallons; or
- The facility's total oil storage capacity, including
both ASTs and USTs, is greater than or equal to one million gallons
and one of the following is true:
- The facility does not have secondary containment for each aboveground storage area sufficient to contain the capacity of the largest AST within each storage area plus freeboard to allow for precipitation;
- The facility is located at a distance such that
a discharge could cause injury to an environmentally sensitive area;
- The facility is located at a distance such that
a discharge would shut down a public drinking-water intake; or
- The facility has had a reportable spill greater than or equal to 10,000 gallons within the last five years.
Overview of the
SPCC and FRP Requirements
The SPCC requirements (40
CFR 112.1 through 112.7) apply to facilities that meet the minimum applicability
standards to prevent oil spills from reaching the navigable waters of
the U.S. or adjoining shorelines. The SPCC Plan must describe discharge
prevention structures such as secondary containment, proper operation
and maintenance at the facility, and adequate training of facility personnel.
In 1990, Congress passed the Oil Pollution Act which amended Section 311 of the Clean Water Act to require "substantial harm" facilities to develop and implement FRPs. Under the FRP requirements, codified at 40 CFR 112.20 and 112.21, owners and operators of facilities that could cause "substantial harm" to the environment by discharging oil into navigable water bodies or adjoining shorelines must prepare and implement plans, training, and drills for responding to a worst case discharge of oil, to a substantial threat of such a discharge, and to discharges smaller than worst case discharges.
EPA-regulated facilities are required to
submit their FRPs and certification of response resources to implement
the plan to EPA for review. The Agency reviews and approves plans from
facilities identified as having the potential to cause "significant
and substantial harm" to the environment from oil discharges. Other
regulated facilities that do not meet the "substantial harm"
criteria and are not required to prepare an FRP are required to document
their determination. This determination should be kept with the facility's
SPCC Plan.
General SPCC Requirements
The owner or operator of a regulated facility
is required to have an SPCC Plan, which is a written site-specific description
detailing how a facility's operation complies with 40 CFR Part 112.
In order to comply with 40 CFR Part 112, the SPCC Plan must be fully
prepared and implemented.
Regulated facilities in existence at the
time the regulation went into effect, on January 10, 1974, were
required to have a Plan prepared within six months of the effective
date of the regulation and to have fully implemented the Plan within
one year of the effective date of the regulation.
Currently, newly constructed facilities
must prepare an SPCC Plan within six months of the date they commence
operations and fully implement the Plan as soon thereafter as possible,
but not later than one year after the date operations commence. Facility
owners or operators who are unable to implement an SPCC Plan within
this time frame due to circumstances beyond their control may make a
written request for an extension from the EPA Regional Administrator
(RA) by following the procedure explained in 40 CFR 112.3(f).
Owners or operators of mobile or portable
facilities, such as drilling or workover rigs, may prepare a general
SPCC Plan that need not be site-specific. However, SPCC Plans for these
facilities must satisfy all other requirements of 40 CFR 112. When the
portable or mobile facility is moved, it must be located and installed
using the practices outlined in the SPCC Plan for the facility. The
SPCC Plan shall only apply while the facility is in a fixed, nontransportation
operating mode; however, no mobile or portable facility subject to this
regulation may operate in a fixed mode unless the SPCC Plan has been
implemented (40 CFR 112.3(c)).
While each SPCC Plan is unique, certain
elements must be included in order for the SPCC Plan to comply with
the provisions of 40 CFR Part 112. If a section does not apply to the
facility, this must be stated. These elements include, but are not limited
to, the following:
The SPCC Plan must be reviewed and certified
by a Registered Professional Engineer (PE) who is familiar with the
facility and with 40 CFR Part 112. The engineer's name, registration
number and state of registration must be included as part of the SPCC
Plan. The engineer's seal should be affixed to the Plan as part of the
certification.
By certifying the Plan, the engineer is
attesting that he or she is familiar with the facility, its SPCC Plan
and the SPCC requirements, and that the Plan has been prepared in accordance
with good engineering practices.
In order to satisfy the requirements of
40 CFR 112.5, all subsequent amendments must also be certified by a
Professional Engineer, as described above.
If the facility is manned at least eight
hours a day, the owner or operator is required to maintain a complete
copy of the SPCC Plan onsite. If the facility is not manned at least
eight hours a day, the Plan must be kept at the nearest field office
that is.
The Plan must be made available for review
by the EPA Regional Administrator (RA) or his or her representative
during normal business hours.
The SPCC Plan should be approved by a level
of management with the authority to commit those resources necessary
to implement the Plan. The appropriate manager's signature should be
included in the SPCC Plan.
The SPCC Plan must include a complete discussion
of the facility's conformance with all applicable SPCC requirements
and shall follow the sequence of 40 CFR 112.7. To help facilities in
preparing and reviewing SPCC Plans, the EPA Oil Program developed a
sample Plan, which can be obtained from any one of the EPA offices listed
at the end of this guide.
All spill prevention practices used at
a facility must be addressed and a complete and accurate description
of them must be included in the Plan. It is possible that some items
in 40 CFR Part 112 are not applicable to a facility. For example, under
facility transfer operations, the first item requires that buried piping
be protectively wrapped or cathodically protected. Some facilities may
not have any buried piping. For these cases, the SPCC Plan should indicate
that there is no buried piping at the facility. Every item must be addressed
in the Plan, even though probably not every item will apply to a facility.
A facility that has experienced one or
more spill events since January 10, 1974, should include in the SPCC
Plan a written description of each spill, corrective actions taken,
and plans for preventing recurrence.
Where industry experience indicates a reasonable
potential for equipment failure, the SPCC Plan should include a prediction
of direction, rate of flow, and total quantity of oil that could be
discharged from the facility as a result of each major
type of failure mode.
Examples of major failure modes to be discussed
in the Plan include, but are not limited to, tank failure due to overflow,
rupture or leakage; pipeline failure due to rupture or corrosion; leaking
flanges, gaskets, expansion joints, valves, or catch pans; spills from
bulk oil loading or unloading operations; and leaks due to other causes,
such as failure of wastewater or stormwater treatment or disposal systems.
Topographic maps are often useful for predicting
and illustrating the direction of flow and bodies of water which might
be affected by a spill.
The SPCC Plan must be amended whenever
there is a change in facility design, construction, operation or maintenance
which materially affects the facility's potential to discharge oil into
or upon navigable waters.
In addition, owners or operators of regulated facilities are required to review and evaluate the SPCC Plan at least once every three years from the time the facility becomes subject to the SPCC requirements. Within six months after this review and evaluation, the owner or operator must amend the SPCC Plan to include more effective prevention and control technology
- If such technology will significantly reduce the likelihood of a spill event from the facility, and
- If the technology has been field-proven at the
time of the review.
In order to satisfy the requirements of 40 CFR 112.5, all such amendments must be certified by a Professional Engineer, as described earlier in this section.
After review of the SPCC Plan and any other
information submitted, the RA may require the owner or operator to amend
the SPCC Plan if it does not meet the SPCC requirements or if such amendment
is necessary to prevent or contain future discharges from the facility.
The RA will consider any recommendations made by the state agency in
charge of water pollution control during this process.
If the RA proposes that the SPCC Plan be amended, the Administrator shall provide written notification specifying the terms of the proposed amendment to the facility owner or operator. Upon receipt of this notification, the facility owner or operator will then have 30 days in which to respond, in writing, to the proposal, and offer any additional information, arguments or counterproposals.
The RA will then review all available information and notify the facility
owner or operator of any amendment required or rescind the original
notice. Usually, if an amendment is required, it must be made part of
the SPCC Plan within 30 days after the final notice and implemented
as soon as possible, but not later than six months after the amendment
becomes part of the Plan, unless the RA specifies another date.
The owner or operator may appeal a decision
made by the RA regarding an amendment. Such an appeal must be made in
writing to the Administrator of the EPA within 30 days of receipt of
the final notice from the RA. A copy of the appeal must also be sent
to the RA.
The owner or operator of a facility is required to install appropriate containment and diversionary structures or equipment, such as dikes, berms, and retaining walls, as described in 40 CFR 112.7, to prevent discharged oil from reaching navigable water, unless it can be clearly demonstrated that installation of such structures or equipment is not practical or practicable.
Impracticability pertains primarily to
those cases where severe space limitations or other physical constraints
may preclude installation of structures or equipment to prevent oil
from reaching navigable water. Demonstrating impracticability on the
basis of economic considerations alone is not acceptable.
In the event that such impracticability
can be demonstrated, the owner or operator must provide the following
in place of containment structures or equipment:
- A strong oil spill contingency plan following
the provisions of 40 CFR Part 109, and
- A written commitment of manpower, equipment and materials required to expeditiously control and remove any harmful quantity of oil discharged.
Whenever a regulated facility experiences a single discharge of more than 1,000 gallons of oil or discharges oil in harmful quantities into or upon navigable waters in two reportable spill events during any twelve-month period, the owner or operator must submit in writing the following information to the RA within 60 days:
- Name of the facility;
- Name(s) of the owner or operator of the facility;
- Location of the facility;
- Date and year of initial facility operation;
- Maximum storage or handling capacity of the facility and normal daily throughput;
- Description of the facility, including maps, flow diagrams and topographical maps;
- The cause(s) of such spill(s), including a failure analysis of the system or subsystem in which the failure occurred;
- Corrective actions and/or countermeasures taken, including a complete description of equipment repairs or replacements; and
- Copy of the SPCC Plan and any other information pertinent to the Plan or the spill(s).
A complete copy of all information sent
to the RA must also be sent to the state agency in charge of water pollution
control activities.
In addition to general requirements, the SPCC rule also has performance-based requirements in 40 CFR 112.7 for drainage control, bulk storage tanks, transfer operations (e.g., intrafacility piping), tank car and truck loading and unloading racks, various onshore and offshore production facility operations, onshore and offshore oil drilling, production and workover facilities, security and training. These specific requirements are discussed in detail for the operations at bulk oil storage facilities and other regulated facilities in separate guides (refer to the list at the end of this guide).
General FRP Requirements
SPCC-regulated facilities that could cause "substantial harm" to the environment must prepare and submit response plans to the appropriate EPA Regional Office.
Owners or operators of all facilities subject
to the Oil Pollution Prevention Regulation must familiarize themselves
with the rule to determine whether their facility meets the "substantial
harm" criteria described at the beginning of this guide. Under
40 CFR 112.20(e), facilities that do not meet the "substantial
harm" criteria (i.e., answer "no" to all five questions)
must document this determination by completing the "Certification
of the Applicability of the Substantial Harm Criteria Checklist,"
provided as Attachment C-II in Appendix C of 40 CFR 112. This certification
should be maintained with the facility's SPCC Plan. Facilities that
meet the "substantial harm" criteria must submit this certification
to EPA with their FRP. These "substantial harm" facilities
must certify to EPA that they have a contractor or other means to implement
their response plan.
The 1994 FRP rule added more specific requirements for oil spill response training and response drills and exercises for facilities, which are codified at 40 CFR 112.21. Under Sec. 112.20(h)(8), Facility Response Plans must include information about self-inspection, drills, exercises, and response training, including descriptions and logs of training and drill or exercise programs and documentation of tank inspections, equipment inspections, response training meetings, response training sessions, and drills and exercises. Consequently, Facility Response Plans may be revised based on evaluations of the drills and exercises. A program that follows the National Preparedness for Response Exercise Program (PREP) will meet EPA's exercise requirements.
EPA has developed an outreach guide, titled
Facility Response Planning, which contains more specific information
regarding the FRP requirements and
response training, drills and exercises.
Other Compliance Assistance
Guides
EPA has prepared several guides, including industry-specific guides,
for compliance assistance with the Federal Oil Pollution Prevention
Regulation:
- SPCC Requirements and Oil Pollution Prevention Practices for Bulk Oil Storage Facilities
- SPCC Requirements and Oil Pollution Prevention Practices for Oil Production, Drilling, and Workover Facilities
- SPCC Requirements and Oil Pollution Prevention Practices for Farms and Ranches
- SPCC Requirements and Oil Pollution Prevention Practices for Mines and Quarries
- SPCC Requirements and Oil Pollution Prevention Practices for Electrical Utilities
- SPCC Requirements and Oil Pollution Prevention Practices for Vehicle Service Facilities
- Spill Prevention Requirements for Facilities Conducting Large Volume Transfer Operations
- Sample SPCC Plan and Sample Containment Volume Calculations
- Facility Response Planning
- Oil Spill Notification, Response, and Recovery
- Other Regulatory Programs Relating to Oil Pollution Prevention
- Who's Who: Federal Agency Roles and Responsibilities for Oil Spill Prevention and Response
- What to Expect During an SPCC/FRP Inspection
- List of Acronyms and Glossary Relating to Oil Pollution Prevention
http://www.epa.gov/oilspill To report oil and chemical spills, call 1-800-424-8802 |
Federal Agency Contact Information |
EPA's Oil Pollution Prevention Regulation
David Lopez, MS 5203G, U.S. EPA 401 M Street, SW, Washington, DC 20460 (703) 603-8707 or EPCRA/RCRA/Superfund Hotline at (800) 424-9346. U.S. Coast Guard's Facility Response Plan Regulation LCDR Mark Hamilton, U.S. Coast Guard, Commandant (G-MOR), 2100 2nd Street, SW, Washington, DC 20593, (202) 267-1983 (E-mail M.Hamilton/G-M03@CGSMTP.uscg.mil) DOT/RSPA's Pipeline Response Plan Regulation Jim Taylor, U.S. Department of Transportation, Room 2335, 400 7th Street, SW, Washington, DC 20590 (202) 366-8860 (E-mail OPATEAM@RSPA.DOT.GOV) OSHA Regulations Contact either your Regional or Area OSHA office by calling directory service or the OSHA National Information Line at (800) 326-2577 DOI/MMS Facility Response Plan Regulation Larry Ake, U.S. Department of the Interior-- Minerals Management Service, MS 4700, 381 Elden Street, Herndon, VA 22070-4817 (703) 787-1567 (E-mail Larry__ Ake@SMTP.MMS.GOV) |
U.S. EPA Headquarters
David Lopez (703) 603-8707
Dan Chadwick (202) 564-7054
401 M St. SW
Washington, D.C. 20460
Region 1 Connecticut, Maine, Massachusetts, New Hampshire, Rhode Island, and Vermont
Dennisses Valdes (617) 573-5715
Dave Tordoff (617) 573-9693
JFK Federal Bldg.
Boston, MA 02114
Region 2 New Jersey, New York, Puerto Rico, and the U.S. Virgin Islands
Matthew Garamone (908) 906-6838
Christopher Jimenez (908) 906-6847
2890 Woodbridge Ave. (MS-221)
Edison, NJ 08837-3679
Region 3 Delaware, Maryland, Pennsylvania, Virginia, and West Virginia
Linda Ziegler (215) 566-3277
Jean Starkey (215) 566-3292
841 Chestnut Building, 9th Fl.
Philadelphia, PA 19107-4431
Region 4 Alabama, Florida, Georgia, Kentucky, Mississippi, North Carolina, South Carolina, and Tennessee
Bob Rosen (404) 562-8761
George Starr (404) 562-8768
61 Forsyth St.
Atlanta, GA 30303-3415
Region 5 Illinois, Indiana, Ohio, Michigan, Minnesota, and Wisconsin
Barbara Carr (312) 886-7187
77 W. Jackson Blvd.
Chicago, IL 60604-3507Region 6 Arkansas, Louisiana, New Mexico, Oklahoma, and Texas
Richard Franklin (214) 665-6489
1445 Ross Avenue
Dallas, TX 75202-2733
Region 7 Iowa, Kansas, Missouri, and Nebraska
Robert W. Jackson (913) 551-7952
726 Minnesota Ave.
Kansas City, KS 66101
Region 8 Colorado, Montana, North Dakota, South Dakota, Utah, and Wyoming
Martha Wolf (303) 312-6839
999 18th Street, Suite 500
Denver, CO 80202-2466
Region 9 Arizona, California, Hawaii, Nevada, Guam, and American Samoa
Trust Territories of the Pacific
Steve Calanog (415) 744-2327
75 Hawthorne Street
San Francisco, CA 94105
Region 10 Alaska, Idaho, Oregon, and Washington
Carl G. Kitz (206) 553-1671
1200 Sixth Ave.
Seattle, WA 98101
Donald L. Marson (907) 271-3433
222 West 7th Ave. #9
Anchorage, AK 99513-7588