The use of Liquidated Damages (LD’s) as an enforcement tool for work completion is not a success. For some projects, the reliance on LD’S is simply a path to failure for timely performance. I/D’s are designed to enhance the project LD’s and encourage contractors to view the project with high importance to the completion schedule.
Objectives of this Site
Evaluate the project need for an I/D
Organize the process for developing I/D's
Calculate the dollar range of I/D values
Assist the selection of the best I/D amount
Document the project team decisions
Use this link to learn more about the "Background" of this program and the "Concept of Timely Completion of Work."
The DAP Review form is provided to help document prequalification requirements and estimates for projects. The form is prepared as a MS Word document with check boxes to answers prerequisite questions and a text holder to copy and paste data from the ID Analysis Spreadsheet.
Information needed:
Total biddable dollars
Estimated % of bid $ in I/D
Estimated bid date
Estimated completion date
Highway ADT
Posted preconstruction speed
Project length in miles
If a crossover detour is needed