The following is a list of the major projects approved by Ex-Im Bank's Board of Directors during 2004 that were categorized as either environmental Category A or B. The environmental factors associated with each project are summarized, as well as the time period for which the EIA was made available by Ex-Im Bank for each Category A project.

CATEGORY A TRANSACTIONS

CASE NO.
PROJECT COUNTRY
PROJECT NAME & LOCATION (Brief Description)
KEY ENVIRONMENTAL FACTORS CONSIDERED
AMOUNT FINANCED
PERIOD OF EIA AVAILABILITY
DATE APPROVED
AP079024
Ecuador
International Airport near Quito Air emissions, wastewater effluent levels, water supply, waste management, noise level, site characteristics (archaeological significance of site) $46.6 million
400 DAYS
9/30/2004
AP080947
Mexico
Development of 24 new oil & gas fields under the Pidiregas Program in the Gulf of Mexico, Bay of Campeche, and onshore in northwestern Tabasco Air emissions, waste discharge effluent levels, oil spill contingency plans, ecology protection (marine environment), compliance to MARPOL Convention for effluent levels from vessels & offshore platforms $400 million
56 DAYS
9/30/2004
AP080217
Qatar
Natural Gas Liquefaction Plant (LNG) in Ras Laffan Industrial City Air emissions (VOC, NOx), effluent levels of discharge, spill & release protection and contingency plan $405 million
249 DAYS
11/18/2004
AP079630
Romania
Bravaso-Oradia Motorway project Air emissions, site characteristics (ecology protection -fauna), noise levels, emergency spill contingency plan $181.2 million
111 DAYS
10/7/2004
AP081050
Turkey
One gas fired 200 MW combined-cycle power plant near Bursa Air emissions, cooling water discharge effluent levels, site characteristics $53.4 million
43 DAYS
12/16/2004
AP079686
Argentina
Veladero open-pit gold mining project in the high Andes of San Juan Province Mine effluent levels (cyanide, acid rock drainage), long term protection of water quality, protection of area vegetation (topsoil salvage), protection of archaeological site, mine reclamation & closure plan $80 million
114 DAYS
3/26/2004

CATEGORY B TRANSACTIONS

CASE NO.
PROJECT/ COUNTRY
PROJECT NAME & LOCATION (Brief Description)
KEY ENVIRONMENTAL FACTORS
AMOUNT FINANCED
DATE APPROVED
AP080105
Turkey
60 MW Combined Cycle Plant for Nuh Enerji located near Hereke Air emissions (NOx), cooling water discharge effluent levels $21.4 million 10/19/2004
AP080562
Singapore
Extension of Semiconductor Manufacturing Facility in the "Woodlands Wafer Fab Industrial Park" Effluent levels, water treatment facilities, waste management, project noise level $652.4 million 11/12/2004
AP080715
Russian Federation
Addition of 50,000 tonne/year polystyrene plant adjacent to existing plant in petrochemical complex located near Nizhnekamsk, Republic of Tatarstan Air emissions, water discharge effluent levels, and waste management $14.4 million 11/4/2004
AP080178
Turkey
One 154 MW gas-fired combined cycle power plant located in an industrial zone 14 km from Kayseri (Zorlu Plant) Air emissions (NOx), cooling water discharge effluent levels $44.6 million 7/13/2004
AP079957
Azerbaijan
Construction of an international business center at Baku to include shopping center, offices & high-end residential space Land & water useage and permitting, effluent levels and treatment facilities $19.6 million 3/11/2004
AP080074
Mexico
Modernization of the Sihil Block oil production wells in the Cantarell off-shore oil field in Bay of Campeche Air emissions, waste discharge effluent levels, waste management (disposal of drilling materials) $300.0 million 3/11/2004
AP079289
Egypt, Arab Rep.
One gas fired 750 MW combined cycle power plant to be located near Cairo (Cairo North II Plant) Air emissions (NOx), cooling water discharge effluent levels, site characteristics $69.3 million 4/22/2004
AP080231
Mexico
"PEG phase 2" gas field development and optimization project for numerous wells including reservoir studies, in onshore areas of Veracruz, Tabasco, Chiapas and offshore in Bay of Campeche Air emissions, water use, wastewater discharge effluent levels, solid waste disposal, site characteristics $200.0 million 5/13/2004
AP080012
Ghana
Cocoa bean processing plant in Accura Air emissions (particulates), recycling of waste bean shells, wastewater effluent levels, process water recycling $11.0 million 2/13/2004
AP080385
Mexico
Expansion of gas production in Burgos Basin area - Tamaulipas and Nuevo Lauredo States. Air emissions, waste water effluent levels, waste management, site characteristics and local ecological aspects $200.0 million 5/21/2004
AP079758
Nigeria
Petroleum Refinery having a capacity of 6,000 BBL/day near town of Eket in Akway Ibom State Air emissions, effluent levels, water use, waste management, site characteristics $10.3 million 1/20/2004



 