MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4070701 MGR.NO. 055 PAGE 001 CONT 6156 SEC 89 JOB 001 RES ENGR RODARTE, HILARIO PROJ RMC - 615689001 HWY SH0163 US 277 NORTH SONORA CNTY IRION DIST 07 CONTRACT PRICE $ 153,495.00 REPORT DATE 11/13/2007 15.35.55 CONTRACTOR K-CONTRACTING, INC. 7532 EST PERIOD OCT 01,2007 TO OCT 31,2007 EST NO 005 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 13, 2007 TIME COMPUTED FROM JUN 13, 2007 SUMMARY INFORMATION DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 70 141 80 61 BROUGHT FORWARD ADDL DAYS GRANTED = 0 *** ESTIMATE ALREADY POSTED *** TOTAL DAYS ALLOWED = 70 DATE WORK COMPLETED DAYS CHARGED TO DATE = 80 ASSESSED LIQ DAMAGES = 10 LIQ DAMAGE RATE $ 450 LIQUIDATED DAMAGES 10 DAYS AT $ 450 PER DAY TOTAL = $ 4,500.00 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR ---------------------------- AREA/PROJECT ENGINEER ----- ----- ----- 141 80 61 0 SATURDAY 0 SUNDAY 0 HOLIDAY ========================================================================================================= MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4070701 MGR.NO. 055 PAGE 001 CONT 6156 SEC 89 JOB 001 RES ENGR RODARTE, HILARIO PROJ RMC - 615689001 HWY SH0163 US 277 NORTH SONORA CNTY IRION DIST 07 CONTRACT PRICE $ 153,495.00 REPORT DATE 11/13/2007 15.44.36 CONTRACTOR K-CONTRACTING, INC. 7532 EST PERIOD OCT 01,2007 TO OCT 31,2007 EST NO 005 ********************************************************************************************************* LIMITS - STA 312+31 NORTH OF US 67 STA 1145+75 NORTH OF US 67 DATE WORK BEGAN JUN 13, 2007 WORKING DAYS USED 80 PERCENT COMPLETE 0.00 PERCENT TIME USED 114.20 DATE COMPLETED CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6156-89-001 RMC - 615689001 07 SH0163 IRION ***** NO WORK TO DATE FOR CONTRACT *****