MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 9071931 MGR.NO. 055 PAGE 001 CONT 6168 SEC 76 JOB 001 RES ENGR SMITH, SCOTT PROJ SUP - 616876001 HWY US0059 520 SOWELL LANE TEXARKANA CNTY BOWIE DIST 19 CONTRACT PRICE $ 142,761.74 REPORT DATE 11/13/2007 15.35.56 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2007 TO OCT 31,2007 EST NO 002 VOCATIONAL OPPORTUNITIES CENTER NORTHEAST TEXAS,INC 1078 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 01, 2007 TIME COMPUTED FROM SEP 01, 2007 SUMMARY INFORMATION DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 61 61 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 *** ESTIMATE ALREADY POSTED *** TOTAL DAYS ALLOWED = 365 DATE WORK COMPLETED DAYS CHARGED TO DATE = 61 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 0 LIQUIDATED DAMAGES 0 DAYS AT $ 0 PER DAY TOTAL = $ .00 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR ---------------------------- AREA/PROJECT ENGINEER ----- ----- ----- 61 61 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY ========================================================================================================= MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 9071931 MGR.NO. 055 PAGE 001 CONT 6168 SEC 76 JOB 001 RES ENGR SMITH, SCOTT PROJ SUP - 616876001 HWY US0059 520 SOWELL LANE TEXARKANA CNTY BOWIE DIST 19 CONTRACT PRICE $ 142,761.74 REPORT DATE 11/13/2007 15.53.03 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2007 TO OCT 31,2007 EST NO 002 VOCATIONAL OPPORTUNITIES CENTER NORTHEAST TEXAS,INC 1078 ********************************************************************************************************* LIMITS - VARIOUS . DATE WORK BEGAN SEP 1 , 2007 WORKING DAYS USED 61 PERCENT COMPLETE 14.76 PERCENT TIME USED 16.70 DATE COMPLETED CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6168-76-001 SUP - 616876001 19 US0059 BOWIE ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) 0734 LITTER REMOVAL - TRACT (1) CYC 4.000 1.000 5,303.430 5,303.43 0734 LITTER REMOVAL - TRACT (2) CYC 4.000 1.000 3,922.500 3,922.50 0734 LITTER REMOVAL - TRACT (3) CYC 2.000 1.000 11,849.390 11,849.39 SUBTOTAL BID ITEMS $ 21,075.32 CONTRACT TOTAL ALL ITEMS $ 21,075.3