MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7071839 MGR.NO. 009 PAGE 001 CONT 6166 SEC 04 JOB 001 RES ENGR CAMPBELL, HANK PROJ SUP - 616604001 HWY IH0035E 124 FM 876 WAXAHACHIE CNTY ELLIS DIST 18 CONTRACT PRICE $ 112,844.02 REPORT DATE 11/13/2007 15.35.56 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2007 TO OCT 31,2007 EST NO 004 PRECIOUS GEMS CHILD CARE SERVICES, INC. 1215 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 24, 2007 TIME COMPUTED FROM JUL 24, 2007 SUMMARY INFORMATION DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 100 100 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 *** ESTIMATE ALREADY POSTED *** TOTAL DAYS ALLOWED = 365 DATE WORK COMPLETED DAYS CHARGED TO DATE = 100 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 400 LIQUIDATED DAMAGES 0 DAYS AT $ 400 PER DAY TOTAL = $ .00 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR ---------------------------- AREA/PROJECT ENGINEER ----- ----- ----- 100 100 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY ========================================================================================================= MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7071839 MGR.NO. 009 PAGE 001 CONT 6166 SEC 04 JOB 001 RES ENGR CAMPBELL, HANK PROJ SUP - 616604001 HWY IH0035E 124 FM 876 WAXAHACHIE CNTY ELLIS DIST 18 CONTRACT PRICE $ 112,844.02 REPORT DATE 11/13/2007 15.53.02 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2007 TO OCT 31,2007 EST NO 004 PRECIOUS GEMS CHILD CARE SERVICES, INC. 1215 ********************************************************************************************************* LIMITS - VARIOUS ROADWAYS IN ELLIS COUNTY MAINTENANCE SECTION DATE WORK BEGAN JUL 24, 2007 WORKING DAYS USED 100 PERCENT COMPLETE 40.61 PERCENT TIME USED 27.30 DATE COMPLETED CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6166-04-001 SUP - 616604001 18 IH0035E ELLIS ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) 0734 LITTER REMOVAL - TRACT (1) CYC 5.000 3.000 3,065.040 9,195.12 0734 LITTER REMOVAL - TRACT (2) CYC 4.000 1.000 644.500 644.50 0734 LITTER REMOVAL - TRACT (3) CYC 4.000 3.000 2,072.300 6,216.90 0734 LITTER REMOVAL - TRACT (4) CYC 2.000 1.000 1,857.600 1,857.60 0734 LITTER REMOVAL - TRACT (5) CYC 3.000 2.000 3,205.550 6,411.10 0734 LITTER REMOVAL - TRACT (6) CYC 3.000 1.000 1,527.600 1,527.60 0734 LITTER REMOVAL - TRACT (7) CYC 2.000 1.000 747.760 747.76 0734 LITTER REMOVAL - TRACT (8) CYC 4.000 1.000 1,573.200 1,573.20 0734 LITTER REMOVAL - TRACT (10) CYC 4.000 1.000 877.680 877.68 0734 LITTER REMOVAL - TRACT (12) CYC 11.000 1.000 35.490 35.49 0734 LITTER REMOVAL - TRACT (14) CYC 5.000 1.000 101.520 101.52 0734 LITTER REMOVAL - TRACT (15) CYC 3.000 1.000 378.360 378.36 0734 LITTER REMOVAL - TRACT (16) CYC 3.000 1.000 1,112.020 1,112.02 0734 LITTER REMOVAL - TRACT (17) CYC 4.000 2.000 673.120 1,346.24 0734 LITTER REMOVAL - TRACT (18) CYC 2.000 1.000 3,175.040 3,175.04 0734 LITTER REMOVAL - TRACT (21) CYC 6.000 1.000 91.200 91.20 0734 LITTER REMOVAL - TRACT (23) CYC 4.000 1.000 412.480 412.48 0734 LITTER REMOVAL - TRACT (25) CYC 2.000 1.000 1,133.600 1,133.60 0734 LITTER REMOVAL - TRACT (31) CYC 2.000 1.000 4,320.000 4,320.00 0734 LITTER REMOVAL - TRACT (32) CYC 4.000 1.000 285.000 285.00 0734 LITTER REMOVAL - TRACT (35) CYC 2.000 1.000 4,390.000 4,390.00 SUBTOTAL BID ITEMS $ 45,832.41 CONTRACT TOTAL ALL ITEMS $ 45,832.4