1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 6041202 MGR.NO. 058 PAGE 001 CONT 6114 SEC 53 JOB 001 RES ENGR RANFT, GREGORY PROJ RMC - 611453001 HWY US290 14838 NW FRWY HOUSTON CNTY WALLER DIST 12 CONTRACT PRICE $ 161,375.00 REPORT DATE 07/05/2006 14.54.15 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD AUG 09,2004 TO JUL 31,2005 EST NO 013 & FINAL INC. 00644 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN AUG 09, 2004 TIME COMPUTED FROM AUG 09, 2004 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 357 357 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 05 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 07/31/05 3 1 DAYS CHARGED TO DATE = 357 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 388 388 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 6041202 MGR.NO. 058 PAGE 001 CONT 6114 SEC 53 JOB 001 RES ENGR RANFT, GREGORY PROJ RMC - 611453001 HWY US290 14838 NW FRWY HOUSTON CNTY WALLER DIST 12 CONTRACT PRICE $ 161,375.00 REPORT DATE 07/05/2006 14.54.16 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD AUG 09,2004 TO JUL 31,2005 EST NO 013 & FINAL INC. 00644 DIST. 12 COUNTY WALLER CONTROL 6114-53-001 PROJECT RMC - 611453001 HIGHWAY US290 0LIMITS- VARIOUS HIGHWAYS IN WALLER COUNTY VARIOUS HIGHWAYS IN WALLER COUNTY 0TYPE OF WORK- ASPHALT PAVEMENT REPAIR 0 0050 ASPHALT PAVEMENT REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY ERA PALMER 0 0075 0351 REPAIR EXIST FLEX PAV STRUCT (8 ") SY 1,750.000 1,754.722 40.500 71,066.24 0080 0351 REPAIR EXIST FLEX PAV STRUCT (6") SY 2,000.000 1,994.667 40.000 79,786.68 0085 0351 REPAIR EXIST FLEX PAV STRUCT (10") SY 250.000 249.486 42.000 10,478.41 0 SUBTOTAL BID ITEMS $ 161,331.33 0 TOTAL AMOUNT WORK DONE ASPHALT PAVEMENT REPAIR $ 161,331.33 0 TOTAL AMOUNT WORK DONE CONTROL 6114-53-001 $ 161,331.33 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 6041202 MGR.NO. 058 PAGE 001 CONT 6114 SEC 53 JOB 001 RES ENGR RANFT, GREGORY PROJ RMC - 611453001 HWY US290 14838 NW FRWY HOUSTON CNTY WALLER DIST 12 CONTRACT PRICE $ 161,375.00 REPORT DATE 07/05/2006 14.54.16 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD AUG 09,2004 TO JUL 31,2005 EST NO 013 & FINAL INC. 00644 0*********************************************************************************************************************************** -LIMITS - VARIOUS HIGHWAYS IN WALLER COUNTY 0 VARIOUS HIGHWAYS IN WALLER COUNTY DATE WORK BEGAN AUG 9 , 2004 WORKING DAYS USED 357 PERCENT COMPLETE 100.00 PERCENT TIME USED 97.80 DATE COMPLETED JUL 31 2005 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6114-53-001 RMC - 611453001 12 US290 WALLER - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0351 REPAIR EXIST FLEX PAV STRUCT (8 ") SY 1,750.000 1,754.722 40.500 71,066.24 0351 REPAIR EXIST FLEX PAV STRUCT (6") SY 2,000.000 1,994.667 40.000 79,786.68 0351 REPAIR EXIST FLEX PAV STRUCT (10") SY 250.000 249.486 42.000 10,478.41 0 SUBTOTAL BID ITEMS $ 161,331.33 0 CONTRACT TOTAL ALL ITEMS $ 161,331.33 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 6041202 MGR.NO. 058 PAGE 001 CONT 6114 SEC 53 JOB 001 RES ENGR RANFT, GREGORY PROJ RMC - 611453001 HWY US290 14838 NW FRWY HOUSTON CNTY WALLER DIST 12 CONTRACT PRICE $ 161,375.00 REPORT DATE 07/05/2006 14.54.16 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD AUG 09,2004 TO JUL 31,2005 EST NO 013 & FINAL INC. 00644 ******************************************************************************************************************* CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ******************************************************************************************************************* 237 RMC - 611453001 6114-53-001 161,331.33 .00 161,331.33 .00 .00 161,331.33 161,331.33 .00 ------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ******************************************************************************************************************* 161,331.33 .00 161,331.33 .00 .00 161,331.33 161,331.33 .00 ------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 6041202 MGR.NO. 058 PAGE 001 CONT 6114 SEC 53 JOB 001 RES ENGR RANFT, GREGORY PROJ RMC - 611453001 HWY US290 14838 NW FRWY HOUSTON CNTY WALLER DIST 12 CONTRACT PRICE $ 161,375.00 REPORT DATE 07/05/2006 14.54.16 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD AUG 09,2004 TO JUL 31,2005 EST NO 013 & FINAL INC. 00644 ********************************************************************************************************** - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6114-53-001 RMC - 611453001 12 US290 WALLER -LIMITS - VARIOUS HIGHWAYS IN WALLER COUNTY VARIOUS HIGHWAYS IN WALLER COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 161,331.33