DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

 
Notice of Application Tendered for Filing With the Commission, 
Establishing Procedures for Relicensing, and a Deadline for Submission 
of Final Amendments

January 30, 2001.
    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: New Major License.
    b. Project No.: P-271-062.
    c. Date Filed: December 18, 2000.
    d. Applicant: Entergy Arkansas, Inc.
    e. Name of Project: Carpenter-Remmel Hydroelectric Project.
    f. Location: Located on the Ouachita River in Garland and Hot 
Spring Counties, Arkansas, and immediately downstream from the U.S. 
Army Corps of Engineers Blakely Mountain Dam. The Carpenter-Remmel 
Hydroelectric Project includes the Carpenter

[[Page 8959]]

development at river mile 461 and the Remmel development at river mile 
450. There are 34.3 acres of federally owned lands within the project 
boundary around Lake Hamilton which are under the supervision of the 
U.S. Army Corps of Engineers.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. Secs. 791(a)-
825(r).
    h. Applicant Contact: Mr. W. Henry Jones, Relicensing Project 
Manager, Entergy Fossil Operations, P.O. Box 218, Jones Mills, AR 
72105, (501) 844-2148 or email: wjones7@Entergy.com.

    Mr. Hugh T. McDonald, President, Entergy Arkansas, Inc., 425 West 
Capitol Avenue, Little Rock, AR 72201, (501) 377-4372.
    i. FERC Contact: Ed Lee, (202) 219-2809 or E-Mail 
ed.lee@ferc.fed.us.
    All documents (original and eight copies) should be filed with: 
David P. Boergers, Secretary, Federal Energy Regulatory Commissions, 
888 First Street, NE, Washington, DC 20426. Comments and protests may 
be filed electronically via the internet in lieu of paper. See 18 CFR 
385.2001(a)(1)(iii) and the instructions on the Commission's web site 
at http://www.ferc.fed.us/efi/doorbell.htm.
    j. The existing Carpenter-Remmel Project consists of two 
developments: (1) the 56,000-kilowatt (kW) Carpenter Development 
located furthest upstream; and (2) the 9,300-kW Remmel Development 
located approximately 11.78 miles downstream. The project has a total 
installed capacity of 65,300-kW and an average annual generation of 
about 188,800 megawatt hours. All generated power is utilized within 
the applicant's electric utility system.
    k. A copy of the application is available for inspection and 
reproduction at the Commission's Public Reference Room, located at 888 
First Street, NE, Room 2-A, Washington, D.C. 20426, or by calling (202) 
208-1371. The application may be viewed on http://www.ferc.fed.us/
online/rims.htm (call (202) 208-2222 for assistance). A copy is also 
available for inspection and reproduction at the address in item h 
above.
    l. Procedural schedule and final amendments: The applicants will be 
processed according to the following milestones, some of which may be 
combined to expedite processing:

Notice of application has been accepted for filing
Notice soliciting final terms and conditions
Notice of the availability of the draft NEPA document
Notice of the availability of the final NEPA document
Order issuing the Commission's decision on the application

    Final amendments to the application must be filed with the 
Commission no later than 45 days from the issuance date of the notice 
soliciting final terms and conditions.