High Flux Beam Reactor Surveillance & Maintenance and Monitoring
 

Surveillance & Maintenance

The High Flux Beam Reactor (HFBR) at Brookhaven National Laboratory (BNL) is being decommissioned.  BNL will deploy a surveillance and maintenance (S&M) program to manage the inventory of radioisotopes remaining at the HFBR complex and to ensure that the complex is maintained in a safe condition.  The complex includes the HFBR confinement building, ancillary buildings, and associated systems.

Residual radioactive contamination at the HFBR will be maintained in a safe condition under the S&M program and future human exposure pathways will be prevented.  The program will cover the period of time specified by the cleanup alternative selected under the HFBR Proposed Remedial Action Plan and detailed in the Record of Decision (ROD).

Routine S&M activities will include:

  • Continued groundwater monitoring and response actions in accordance with the Operable Unit (OU) III Record of Decision (ROD).
  • Continued air effluent monitoring
  • Routine inspections of the reactor complex, including the maintenance and periodic refurbishment of structures, systems, and components throughout the period of radioactive decay
  • Routine inspections and maintenance of the yard area, including periodic refurbishment of ground cover to prevent soil erosion
  • Periodic reporting to the U.S. Environmental Protection Agency (EPA) and the New York State Department of Environmental Conservation (NYSDEC)

Surveillance activities will be performed by various BNL organizations.  The activities will be scheduled and tracked.  In addition to the routine S&M activities outlined above, there will also be operations and maintenance activities performed at the HFBR.  These activities will be limited to those necessary to support the S&M activities.  Housekeeping will be limited to pick-up and deliveries, garbage collection, and vacuuming and mopping of floors.  Grounds keeping activities will include debris removal, lawn mowing, weed whacking, and removal of leaves, snow and ice.  Preventive maintenance to minimize potential failure of systems and components such as buildng ventilation exhaust systems.

The HFBR S&M plan will be developed by the Department of Energy (DOE) in consultation with the EPA and NYSDEC.

Groundwater Monitoring

The Long Term Response Action (LTRA) Group was formed as part of the Environmental & Waste Management Services Division (EWMSD) in 2004.  The LTRA Group was assigned the responsibility for the long-term surveillance, monitoring, maintenance, operating, reporting, and community involvement activities that are required to complete federal Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) environmental cleanup activities at Brookhaven National Laboratory (BNL).

The LTRA Group conducts groundwater monitoring on the BNL site of the HFBR tritium plume, which resulted from the spent fuel pool leak, in accordance with the OU III ROD.  The monitoring program includes a network of 111 permanent wells sampled at frequencies ranging from monthly to annually.   The well network is supplemented with temporary wells that are installed on a semi-annual basis to address any data gaps in the permanent well network that may be created by changes in the location of the tritium plume.  Groundwater monitoring data is reported to the regulatory agencies - EPA, NYSDEC, the New York State Department of Health and the Suffolk County Department of Health Services - quarterly, and is summarized in an annual report.  Any unexpected data results are communicated to the regulators during weekly conference calls, or immediately, if warranted.

Definitions
 

Operable Units (OUs) are groups of areas within a site that contain the same or similar contamination.  The areas within one OU are not necessarily adjacent.  Six OUs have been designated at BNL.  The plans for remediating an OU are developed in accordance with an Interagency Agreement among EPA, NYSDEC, and DOE and are detailed in a ROD.   A Record of Decision (ROD) documents the final remedy selected for the sites, and includes a responsiveness summary, which addresses comments received on the Proposed Plan during the public comment period.  When the ROD is finalized, remedial design and remedial action begin.