COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 27-Aug-2008

Four Mile Canal Terracing and Sediment Trapping

PROJECT DATA

PROJECT: Four Mile Canal Terracing and Sediment Trapping
PRIORITY LIST: 9 PROJECT NO: 0913 CWPPRA NO: XTV-30 DNR NO: TV-18
PROJECT TYPE: Terracing NET ACRES BENEFITTED: 167
REGION: 3 BASIN: Teche / Vermilion PARISH: Vermilion
LEAD AGENCY: NMFS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 25-Sep-2000 ( Actual )    
DESIGN COMPLETION: 1-Dec-2002 ( Actual )    
CONSTRUCTION START: 10-Jun-2003 ( Actual )    
CONSTRUCTION COMPLETION: 23-May-2004 ( Actual )    
ESCROW AMENDMENT 2-Mar-2001 ( Actual ) No: 78
MONITORING PLAN APPROVAL: 18-May-2003 ( Actual )    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 1/11/2000 ( Actual )    
Phase 2 Approval: 16-Jan-2003 ( Actual )    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 7 Charles W. Boustany
STATE SENATE DISTRICT: 26 "Nick" Gautreaux
STATE HOUSE DISTRICT: 49 Simone B. Champagne

Point of Contact:

DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE

John Foret

646 Cajundome Boulevard

Lafayette, LA 70506
PHONES:  
Office: (337) 291-2107
Fax: (337) 291-2106

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 27-Aug-2008

Four Mile Canal Terracing and Sediment Trapping

PROJECT LOCATION:

The project is located four miles south of Intracoastal City in Vermilion Parish, LA.

PROJECT DESCRIPTION:

This project will construct and plant 50,000 feet of terraces with smooth cordgrass (Spartina alterniflora) to create 214 acres of wetlands and protect an additional 113 acres in Vermilion Bay.

PROJECT STATUS: (Project Status Last Updated: 11-Jun-2007 )

An O&M inspection field trip was conducted in March 2007. The project is showing some signs of erosion along the 4-Mile canal side on the ends of the terraces. However, at this time an O&M event does not appear to be warranted.

FUND STATUS:

The current project estimate is $2,040,063 , which includes $1,939,796 for construction first costs, and $75,188 and $25,079 for 20 years of monitoring and operations and maintenance, respectively.

LaCoast.gov Project Managers' Technical Factsheet