Diversions Build Hope for Wetlands

The expense of constructing and operating diversions is a fraction of the estimated cost should the nation fail to protect and restore the Louisiana wetlands. Over the next 20 years, these diversion projects are expected to stabilize or create over a million acres of wetlands.


Diversion Projects in Louisiana's Coastal Wetlands

Diversion Project Project # Description of Project Work Lead Agency Location Project Status Acres Benefited
Avoca Island Diversion & Land Building TE-49 Sediment diversion COE Terrebonne Basin Planning phase 143
Benney's Bay Sediment Diversion MR-13 Construction of conveyance channel, sediment retention devices, dikes, weirs; 50,000 cfs COE Mississippi River Delta Basin Construction scheduled March 2004 5,828
Caernarvon Freshwater Diversion* N/A Construction of five culverts and inflow and outflow channels COE; State of Louisiana Breton Sound Basin Construction completed 1991 77,000
Caernarvon Diversion Outfall Management BS-03a Construction of flow-through culverts with water controls at eight sites, three plug closures with armor; restoration of 13,000 feet of spoil bank NRCS Breton Sound Basin Construction completed 2002 1,132
Channel Armor Gap Crevasse MR-06 Enlargement of existing crevasse to allow additional flow and sediment deposition COE Mississippi River Delta Basin Construction completed 1997 936
Davis Pond Freshwater Diversion N/A Construction of four gated culverts, inflow and outflow channels, guide levees and rock weir COE; State of Louisiana Barataria Basin Construction completed 2002 777,000
Delta-Building Diversion at Myrtle Grove BA-33 Installation of five gated box culverts and a conveyance channel; construction of a pump station COE Barataria Basin Engineering and design phase 8,891
Delta-Building Diversion North of Fort St. Philip BS-10 Construction of new conveyance channel with cuts allowing fresh water to divert into adjacent open waters COE Breton Sound Basin Construction scheduled March 2004 2,473
Delta-wide Crevasses MR-09 Construction of five new crevasses; dredging of existing crevasses; installation of plug in Raphael Pass crevasse to force more water through splays NMFS Mississippi River Delta Basin In construction (1st dredging cycle completed; three more dredging cycles scheduled) 2,386
Freshwater Introduction South of Highway 82 ME-16 Installation of water control structures; plug removal, structure modification; canal enlargement FWS Mermentau Basin Construction scheduled spring 2004 296
Grand Bayou/GIWW Freshwater Diversion TE-10 Deepening existing channel and installation of weir to reduce saltwater intrusion and retain fresh water FWS Terrebonne Basin Construction scheduled April 2005 1,808
Lake Boudreaux Basin Freshwater Intro& Hydrologic Mgmt TE-32 Dredging and installation of sluice gates and outfall management structures for fresh water introduction FWS Terrebonne Basin Construction scheduled May 2004 619
Mississippi River Water Reintroduction into Bayou Lafourche BA-25b Installation of receiving intake structure/siphon system; 1,000 cfs EPA Barataria Basin Engineering and design phase 104,399
Central and East Terrebonne Basin Freshwater Delivery Enhancement* TE-42 Improve distribution of fresh water from the GIWW FWS Terrebonne Basin Proposed complex project To be determined
Myrtle Grove Siphon BA-24 Installation of six siphon pipes; construction of leveed outfall channel to facilitate distribution of fresh water and sediments; 2,100 cfs NMFS Barataria Basin Not scheduled 1,119
Naomi Siphon* BA-03 Installation of eight siphons State of Louisiana/ Plaquemines Parish Barataria Basin Construction completed 1993 Not measured
Naomi Outfall Management BA-03c Installation of two weirs to maximize sediment retention and nutrient uptake NRCS Barataria Basin Construction completed 2002 633
Opportunistic Use of the Bonnet Carre Spillway PO-26 Raising spillway pins to allow flow and reduce salinities COE Pontchartrain Basin Not scheduled 117
River Reintroduction into Maurepas Swamp PO-29 Installation of two culverts; construction of receiving pond; 1,500 cfs EPA Pontchartrain Basin Construction scheduled January 2005 36,121**
Small Freshwater Diversion to the Northwestern Barataria Basin BA-34 Installation of siphons; gapping of spoil banks and culverts EPA Barataria Basin Construction scheduled May 2005 5,134**
Small Sediment Diversions MR-01b Construction of conveyance channels State of Louisiana Mississippi River Delta Basin Construction completed 1993 6,719
South Lake DeCade Freshwater Introduction TE-39 Installation of water control structures on south shore and enlargement of canal NRCS Terrebonne Basin Construction scheduled September 2004 201
West Bay Sediment Diversion MR-03 Construction of a conveyance channel; 20,000 to 50,000 cfs COE Mississippi River Delta Basin Construction scheduled September 2003 9,831
West Point-a-la-Hache Siphon* BA-04 Installation of eight 27-inch tubes to siphon water State of Louisiana Barataria Basin Construction completed 1991 Not measured
West Point-a-la-Hache Outfall Management BA-04c Installation of three earthen plugs and three weirs; restoration of channel banks to enhance distribution and reduce saltwater intrusion NRCS Barataria Basin Hydrologic modeling phase 1,087

*Non-CWPPRA project
**Acres of swamp