John F. Kennedy Space Center Banner NASA Home Page

KSC Home

Site Search  Multimedia FAQ/Contact Us NASA Centers


Space Shuttle Facts & Statistics

*
Note: This section has been redesigned and is regularly updated.
Go to the current Shuttle Factoids
*


factoid.jpg (1883 bytes)

TOTAL SHUTTLE FLIGHTS

 With the completion of Space Shuttle Mission STS-81 on Jan. 22, 1997, a total  of 81 missions have been flown since the first flight in April 1981. Detailed information on each mission is provided in the Space Shuttle Mission Chronology.

Mission Shortcuts

factoid.jpg (1883 bytes)

FLIGHTS BY ORBITER*

*The orbiter Enterprise (OV-101) was a test vehicle not intended for spaceflight. It is on display at Dulles Airport outside Washington, D.C.

Columbia (OV-102)

Discovery (OV-103)

Challenger  (OV-99)
STS-1, 1981 STS-55, 1993
STS-2, 1981 STS-58, 1993
STS-3, 1982 STS-62, 1994
STS-4, 1982 STS-65, 1994
STS-5, 1982 STS-73, 1995
STS-9, 1983 STS-75, 1996
STS 61-C, 1986 STS-78, 1996
STS-28, 1989 STS-80, 1996
STS-32, 1990 STS-83, 1997
STS-35, 1990 STS-94, 1997
STS-40, 1991 STS-87, 1997
STS-50, 1992 STS-90, 1998
STS-52, 1992 STS-93, 1999
STS 41-D, 1984 STS-42, 1992
STS 51-A, 1984 STS-53, 1992
STS 51-C, 1985 STS-56, 1993
STS 51-D, 1985 STS-51, 1993
STS 51-G, 1985 STS-60, 1994
STS 51-I, 1985 STS-64, 1994
STS-26, 1988 STS-63, 1995
STS-29, 1989 STS-70, 1995
STS-33, 1989 STS-82, 1997
STS-31, 1990 STS-85, 1997
STS-41, 1990 STS-91, 1998
STS-39, 1991 STS-95, 1998
STS-48, 1991 STS-96, 1999

        STS-6, 1983

        STS-7, 1983

        STS-8, 1983

STS 41-B, 1984
STS 41-C, 1984
STS 41-G, 1984
STS 51-B, 1985
STS 51-F, 1985
STS 61-A, 1985
  STS 51-L, 1986**
**Challenger and crew were lost approximately 73 seconds after liftoff on STS 51-L.

Atlantis (OV-104)

Endeavour (OV-105)

STS 51-J, 1985 STS-45, 1992
STS 61-B, 1985 STS-46, 1992
STS-27, 1988 STS-66, 1994
STS-30, 1989 STS-71, 1995
STS-34, 1989 STS-74, 1995
STS-36, 1990 STS-76, 1996
STS-38, 1990 STS-79, 1996
STS-37, 1991 STS-81, 1997
STS-43, 1991 STS-84, 1997
STS-44, 1991 STS-86, 1997
STS-49, 1992 STS-67, 1995
STS-47, 1992 STS-69, 1995
STS-54, 1993 STS-72, 1995
STS-57, 1993 STS-77, 1996
STS-61, 1993 STS-89, 1998
STS-59, 1994 STS-88, 1998
STS-68, 1994

 

     factoid.jpg (1883 bytes)

SPACE SHUTTLE LAUNCHES

Night Launches - Per flight rules, a night launch is one that occurs no earlier than 15 minutes after sunset.
STS-8, 2:32:00 a.m. EDT, Aug. 30, 1983 STS-72, 4:41:00 a.m. EST, Jan. 11, 1996
STS 61-B, 7:29:00 p.m. EST, Nov. 26, 1985 STS-76, 3:13:04 a.m. EST, March 22, 1996.
STS-33, 7:23:30 p.m. EST, Nov. 22, 1989 STS-79, 4:54:49 a.m. EDT, Sept. 16, 1996
STS-36, 2:50:22 a.m. EST, Feb. 28, 1990 STS-81, 4:27:23 a.m. EST, Jan. 12, 1997.
STS-38, 6:48:15 p.m. EST, Nov. 15, 1990 STS-82, 3:55:17 a.m. EST, Feb. 11, 1997.
STS-35, 1:49:01 a.m. EST, Dec. 2, 1990 STS-84, 4:07:48 a.m. EDT, May 15, 1997
STS-44, 6:44:00 p.m. EST, Nov. 24, 1991 STS-86, 10:34:19 p.m. EDT, Sept. 25, 1997
STS-56, 1:29:00 a.m. EDT, April 8, 1983 STS-89, 9:48:15 p.m. EST, Jan. 22, 1998
STS-61, 4:27:00 a.m. EST, Dec. 2, 1993 STS-91, 6:06:24 p.m. EDT, June 2, 1998
STS-63, 12:22:04 a.m. EST, Feb. 3, 1995 STS-96, 06:49:42.080 a.m. EDT, May 27, 1999
STS-67, 1:38:13 a.m. EST, March 2, 1995 STS-93, 12:31:00 a.m. EDT, July 23, 1999
factoid.jpg (1883 bytes)
 
SHUTTLE FLIGHTS BY MISSION DURATION

Extended Missions - a mission that lands after the originally scheduled date
STS-3 March 22-30, 1982. After landing site changed from Edwards Air Force Base, Calif.,  to Northrup Strip at White Sands, N.M., high winds at White Sands resulted in one-day extension of mission.
STS 41-C April 6-13, 1984. Mission extended one day when astronauts unable to grapple Solar Maximum Mission spacecraft.
STS 51-D April 12-19, 1985. Mission extended two days to allow crew to attempt fix on SYNCOM IV-3 satellite.
STS 51-F July 29-Aug. 6, 1985. Mission extended 17 revolutions for additional payload activities due to abort-to-orbit.
STS-38 Nov. 15-20, 1990. Mission extended one day due to unacceptable winds at original planned landing site, Edwards.
STS-37 April 5-11, 1991. Landing delayed one day due to weather conditions at landing sites in Florida and California.
STS-42 Jan. 22-30, 1992. Mission extended one day to allow continued scientific research with primary payload, International Microgravity Laboratory-1 (IML-1).
STS-45 March 24-April 2, 1992. Mission extended one day to allow continued scientific research with primary payload, Atmospheric Laboratory for Applications and Science-1 (ATLAS-1)
STS-49 May 7-16, 1992. Flight extended two days to complete mission objectives, including capture, repair and redeploy of INTELSAT VI satellite.
STS-50 June 25-July 9, 1992. Landing delayed one day due to rain at primary landing site, Edwards Air Force Base, Calif.
STS-46 July 31-Aug. 8, 1992. Mission extended one day to complete science objectives.
STS-47 Sept. 12-20, 1992. Mission extended one day to further science objectives.
STS-56 April 8-17, 1993. Landing delayed one day due to KSC weather.
STS-55 April 26-May 6, 1993. Flight extended one day to further science objectives.
STS-57 June 21-July 1, 1993. Landing attempts on June 29 and 30 waved off due to unacceptable cloud cover and rain showers at KSC
STS-51 Sept. 12-22, 1993. Landing delayed one day due to possibility of rain in KSC area.
STS-59 April 9-20, 1994. Landing delayed one day due to weather in KSC area.
STS-65 July 8-23, 1994. Landing delayed one day due to weather in KSC area.
STS-64 Sept. 9-20, 1994. Mission already extended one day was extended again after landing at KSC waved off on Sept. 19 due to weather.
STS-68 Sept. 30-Oct. 11, 1994. Mission extended one day to further science objectives.
STS-67 March 2-18, 1995. Landing delayed one day due to weather in Florida.
STS-70 July 13-22, 1995. First landing opportunities on July 21 at KSC waved off due to fog and low visibility. First opportunity on July 22 at KSC also waved off.
STS-75 March 9, 1996. Landing March 8 waved off due to unfavorable weather conditions. First opportunity at KSC on March 9 also waved off due to weather.
STS-76 March 31, 1996. Landing March 30 waved off due to unfavorable weather conditions. Opportunities at KSC on March 31 also waved off due to weather and orbiter diverted to Edwards.  

Extended Duration Missions

 Extended duration missions began in 1992 when the orbiter Columbia, outfitted with Extended Duration Orbiter (EDO) hardware, embarked on the  longest Shuttle flight to date at that time, Mission STS-50. Endeavour later became the second orbiter in the fleet to be outfitted with EDO  hardware for longer flights. Typical Shuttle flights last about 10 days; extended duration flights initially lasted up to about 13 days and now can be approximately 16 days in length.  Flights are listed by length, beginning with longest:

STS-78 Columbia, June 20-July 7, 1996. Mission duration 16 days, 21 hours, 47 minutes, 45 seconds.
STS-67 Endeavour, March 2-18, 1995. Mission duration 16 days, 15 hours, nine minutes, 46 seconds. STS-67 is first in a series of flights scheduled to last in the 16-day range, further advancing extended duration flights.
STS-75 Columbia, Feb. 22-March 9, 1996. Mission duration 15 days, 17 hours, 40 minutes, 21 seconds.
STS-65 Columbia, July 8-23, 1994. Mission duration 14 days, 17 hours, 55 minutes, one second.
STS-58 Columbia, Oct. 18-Nov. 1, 1993. Mission duration 14 days, 12 minutes, 32 seconds
STS-62 Columbia, March 4-18, 1994. Mission duration 13 days, 23 hours, 16 minutes, 41 seconds
STS-50 Columbia, June 25-July 9, 1992. Mission duration 13 days, 19 hours, 30 minutes, four seconds.

Shortened Missions  -  a mission that is complete on an earlier date than originally scheduled. 

STS-2 Nov. 12-14, 1981. Mission shortened by approximately three days due to failure of number one fuel cell.
51-I Aug. 27-Sept. 3, 1985. Mission shortened one day due to problem with one of payloads, the AUSSAT satellite, which resulted in its being deployed earlier than scheduled.
STS-35 Dec. 2-10, 1990. Mission cut short one day due to impending weather at primary landing site, Edwards Air Force Base, Calif.
STS-44 Nov. 24-Dec. 1, 1991. Mission originally scheduled for 10 days,but cut short due to on-orbit failure of one of three orbiter inertial measurement units.
STS-83 April 4-8, 1997.  16-day mission shortened after malfunction of fuel cell number two.
factoid.jpg (1883 bytes)
 
SHUTTLE END-OF-MISSION LANDINGS

Night landings  - a night landing occurs no later than 15 minutes before sunrise.

STS-8, 12:40:43 a.m. PDT, Sept. 5, 1983, Edwards STS-61, 12:25:37 a.m. EST, Dec. 13, 1993, Kennedy
STS 61-C, 5:58:51 a.m. PST, Jan. 18, 1986, Edwards STS-72, 2:41:41 a.m. EST, Jan. 20, 1996, Kennedy
STS-32, 1:3:36 a.m. PST, Jan. 20, 1990, Edwards STS-82, 3:32:26 a.m. EST, Feb. 21, 1997, Kennedy
STS-35,  9:54:09 p.m. PST, Dec. 10, 1990, Edwards STS-88, 10:53:29 p.m. EST, Dec. 15, 1998, Kennedy
STS-48, 12:38:42 a.m. PDT, Sept. 18, 1991, Edwards STS-96, 2:02:43 p.m. EST, June 6, 1999, Kennedy
STS-51, 3:5:11 a.m. EDT, Sept. 22, 1993, Kennedy STS-93, 11:20:37 p.m. EDT, July 27, 1999, Kennedy

NOTE:  41-C at 5:38 a.m. PDT on April 13, 1984, was in daylight conditions and is not considered a nighttime landing.

factoid.jpg (1883 bytes)

End-of-Mission Landings at Kennedy Space Center

 Initially, all end-of-mission Shuttle landings were conducted at Edwards Air Force Base, Calif. The first KSC landing occurred in 1984. After the 1986 Challenger accident and return-to-flight in September 1988, landings were again initially conducted at Edwards. The first scheduled landing at KSC in the post-Challenger period occurred in August 1991. Today, KSC is considered the prime landing site. Not included on this table or the table listing Edwards landings is STS-3 on March 30, 1982, the only flight to date to have landed at the Northrup Strip in White Sands, N.M., and 51-L, Jan. 28, 1986, the Challenger accident. See KSC Release No. 1-92,  Landing the Space Shuttle Orbiter at KSC, for more information on KSC landings.

STS 41-B - Challenger, Feb. 11, 1984, at 7:15:55 a.m. STS-69 - Endeavour, September 18, 1995, at 7:37:56a
STS 41-G - Challenger, Oct. 13, 1984, at 12:26:38 p.m. STS-73 - Columbia, November 5, 1995, at 6:45:21 am
STS 51-A - Discovery, Nov. 16, 1984, at 6:59:56 a.m. STS-74 - Atlantis, November 20, 1995, at 12:01:27 p.m
STS 51-C - Discovery, Jan. 27, 1985, at 4:23:23 p.m. STS-72 - Endeavour, January 20, 1996, at 2:41:41 a.m
STS 51-D - Discovery, April 19, 1985, at 8:54:28 a.m. STS-75 - Columbia, March 9, 1996, at 8:58:21 a.m.
STS-38 - Atlantis, Nov. 20, 1990, at 4:42:46 p.m. STS-77 - Endeavour, May 29, 1996, at 7:09:18 a.m.
STS-39 - Discovery, May 6, 1991, at 2:55:37 p.m. STS-78 - Columbia, July 7, 1996, at 8:36:45 a.m.
STS-43 - Atlantis, Aug. 11, 1991, at 8:23:25 a.m. STS-79 - Atlantis, September 26, 1996, at 8:13:15 a.m.
STS-45 - Atlantis, April 2, 1992, at 6:23:08 a.m. STS-80 - Columbia, December 7, 1996, at 6:49:05 a.m.
STS-50 - Columbia, July 9, 1992, at 7:42:27 a.m. STS-81 - Atlantis, January 22, 1997, at 9:22:44 a.m.
STS-46 - Atlantis, Aug. 8, 1992, at 9:11:51 a.m. STS-82 - Discovery, February 21, 1997, at 3:32:26 a.m.
STS-47 - Endeavour, Sept. 20, 1992, at 8:53:23 a.m. STS-83 - Columbia, April 8, 1997, at 3:23:13 p.m.
STS-52 - Columbia, Nov. 1, 1992, at 9:05:52 a.m. STS-84 - Atlantis, May 24, 1997, at 9:27:44 a.m.
STS-54 - Endeavour, Jan. 19, 1993, at 8:37:49 a.m. STS-94 - Columbia, July 17, 1997, at 6:46:34 a.m.
STS-56 - Discovery, April 17, 1993, at 7:37:24 a.m. STS-85 - Discovery, August 19, 1997, at 7:07:59 a.m.
STS-57 - Endeavour, July 1, 1993, at 8:52:16 a.m. STS-86 - Atlantis, October 6, 1997, at 5:55:09 p.m.
STS-51 - Discovery, Sept. 22, 1993, at 3:56:11 a.m. STS-87 - Columbia, December 5, 1997, at 7:20:04 a.m.
STS-61 - Endeavour, Dec. 13, 1993, at 12:25:33 a.m. STS-89 - Endeavour, January 31, 1998, at 5:35:09 p.m.
STS-60 - Discovery, Feb. 11, 1994, at 2:19:22 p.m. STS-90 - Columbia, May 3, 1998, at 12:08:59 p.m.
STS-62 - Columbia, March 18, 1994, at 8:09:41 a.m. STS-91 - Discovery, June 12, 1998, at 2:00:18 p.m.
STS-65 - Columbia, July 23, 1994, at 6:38:01 a.m. STS-95 - Discovery, November 7, 1998, at 12:04 p.m.
STS-63 - Discovery, Feb. 11, 1995, at 6:50:19 a.m. STS-88 - Endeavour, December 15, 1998, at 10:53:29p
STS-71 - Atlantis, July 7, 1995, at 10:54:34 a.m. STS-96 - Discovery, June 6, 1999, at 2:02:43 a.m.
STS-70 - Discovery, July 22, 1995, at 8:02:00 a.m. STS-93 - Columbia, July 27, 1999, at 11:20:37 p.m.
factoid.jpg (1883 bytes)
 
End-of-Mission Landings at Edwards Air Force Base
 
STS-1, April 14, 1981 STS 61-A, Nov. 6, 1985 STS-37, April 11, 1991
STS-2, Nov. 14, 1981 STS 61-B, Dec. 3, 1985 STS-40, June 14, 1991
STS-4, July 4, 1982 STS 61-C, Jan. 18, 1986 STS-48, Sept. 18, 1991
STS-5, Nov. 16, 1982 STS-26, Oct. 3, 1988 STS-44, Dec. 1, 1991
STS-6, April 9, 1983 STS-27, Dec. 6, 1988 STS-42, Jan. 30, 1992
STS-7, June 24, 1983 STS-29, March 18, 1989 STS-49, May 16, 1992
STS-8, Sept. 5, 1983 STS-30, May 8, 1989 STS-53, Dec. 9, 1992
STS-9, Dec. 8, 1983 STS-28, Aug. 13, 1989 STS-55, May 6, 1993
STS 41-C, Apr. 13, 1984 STS-34, Oct. 23, 1989 STS-58, Nov. 1, 1993
STS 41-D, Sept. 5, 1984 STS-33, Nov. 27, 1989 STS-59, April, 20, 1994
STS 51-B, May 6, 1985 STS-32, Jan. 20, 1990 STS-64, Sept. 20, 1994
STS 51-G, June 24, 1985 STS-36, March 4, 1990 STS-68, Oct. 11, 1994
STS 51-F, Aug. 6, 1985 STS-31, April 29, 1990 STS-66, Nov. 14, 1994
STS 51-I, Sept. 3, 1985 STS-41, Oct. 10, 1990 STS-67, March 18, 1995
STS 51-J, Oct. 7, 1985 STS-35, Dec. 10, 1990 STS-76, March 3l, 1996

factoid.jpg (1883 bytes)

Diverted Landings - a landing where the orbiter does not land at the originally scheduled landing strip.

STS-3 March 30, 1982. Landing site was changed from Edwards Air Force Base, Calif., to Northrup Strip at White Sands, N.M., due to wet conditions on Edwards dry lake bed.
STS-7 June 24, 1983. Planned landing at Kennedy scrubbed due to poor weather conditions in Florida; orbiter landed in California.
STS 41-C April 13, 1985. Scheduled end-of-mission landing in Florida diverted to Edwards due to bad weather in vicinity of Cape.
STS 61-C Jan. 18, 1986. Landing attempts at KSC on Jan. 16, 17 and 18 waved off due to unacceptable weather and orbiter diverted to California.
STS-38 Nov. 20, 1990. Mission extended one day due to unacceptable crosswinds at original planned landing site, Edwards. Continued adverse conditions at Edwards prompted decision to shift landing to KSC. First end-of-mission at KSC since April 1985.
STS-39 May 6, 1991. Landing diverted to KSC because of unacceptably high winds at planned landing site, Edwards.
STS-48 Sept. 18, 1991. Originally scheduled to be first orbiter night landing at KSC, but diverted to Edwards due to rapidly changing weather conditions and the possibility of rain showers in the KSC area.
STS-44 Dec. 1, 1991. Landing originally scheduled for KSC on Dec. 4, but ten-day mission shortened and landing shifted to Edwards due to on-orbit failure of one of three orbiter inertial measurement units (IMUs). Flight rules stipulate that a mission must be placed in a minimum duration status and the landing site switched to Edwards if even one IMU fails.
STS-50 July 9, 1992. Long-duration flight carrying Spacelab module was scheduled to land at Edwards on July 8, but rain postponed landing until next day. Continued inclement weather on west coast diverted orbiter to Florida.
STS-53 Dec. 9, 1992. Landing originally set for KSC, but diverted due to clouds in vicinity of landing strip
STS-55 May 6, 1993. Landing originally set for KSC switched to Edwards due to unacceptable cloud cover in Florida.
STS-59 April 20, 1994. Landing originally set for KSC on April 19, but waved off due to low clouds and possible thunderstorms in area. An early landing opportunity at KSC on April 20 also was waved off in favor of Edwards landing.
STS-64 Sept. 20, 1994. Mission already extended one day was extended again after first landing opportunities at KSC on Sept. 20 were waved off due to stormy weather. Two additional opportunities at KSC on Sept. 20 also waved off, and orbiter diverted to California.
STS-68 Oct. 11, 1994. Landing diverted to Edwards due to unacceptable weather at KSC.
STS-66 Nov. 14, 1994. Landing diverted to California due to high winds, rain and clouds in Florida caused by Tropical Storm Gordon.
STS-67 March 18, 1995. Orbiter diverted to Edwards on March 18 after landing opportunities in Florida on March 17 and 18 were waved off due to weather.
STS-76 March 31,1996. Orbiter diverted to Edwards on March 31 after landing opportunities in Florida on March 30 and 31 were waved off due to weather. First landing diverted to Edwards in about a year.

factoid.jpg (1883 bytes)

SHUTTLE PAYLOADS AND RELATED INFORMATION

Spacelab Flights  - Flights that carry either the Spacelab module, Spacelab pallet or Spacelab Multipurpose Experiment Support Structure (MPESS) in the orbiter payload bay:
 
STS-9 Columbia, Nov. 28-Dec. 8, 1983. First Spacelab module flight, Spacelab-1.
STS 51-B Challenger, April 29-May 6, 1985. Considered to be first operational flight of Spacelab module. Spacelab-3 covered five basic fields of investigation. Spacelab-3 flown out of sequence ahead of Spacelab-2, listed below.
STS 51-F Challenger, July 29-Aug. 6, 1985. Spacelab-2 primary payload.  Instead of laboratory module, featured three-pallet train holding instruments exposed to space environment. Second and final Spacelab verification flight.
STS 61-A Challenger, Oct. 30-Nov. 6, 1985. Dedicated German Spacelab (Spacelab D-1) mission featuring Spacelab module.
STS-35 Columbia, Dec. 2-10, 1990. First flight of astronomical observatory, ASTRO-1, a collection of instruments mounted atop Spacelab Instrument Pointing System and pallets in orbiter payload bay.
STS-40 Columbia, June 5-14, 1991. Fifth dedicated Spacelab mission carried Spacelab Life Sciences-1 (SLS-1), first Spacelab flight dedicated to single discipline, the life sciences.
STS-42 Discovery, Jan. 22- 30, 1992. First flight of International Microgravity Laboratory-1 (IML-1), featuring Spacelab module.
STS-45 Atlantis, March 24-April 2, 1992. First flight of Atmospheric Laboratory for Applications and Science-1 (ATLAS-1), mounted on nondeployable Spacelab pallets.
STS-50 Columbia, June 25-July 9, 1992. First flight of U.S.  Microgravity Laboratory-1 (USML-1) in Spacelab module.
STS-47 Endeavour, Sept. 12-20, 1992. Spacelab flight jointly sponsored by United States and Japan, designated as Spacelab-J (SL-J), featuring Spacelab module.
STS-52 Columbia, Oct. 22-Nov. 1, 1992. First flight of U.S. Microgravity Payload-1 (USMP-1), a complement of three experiments mounted on two connected Spacelab Multipurpose Experiment Support Structures (MPESSs) in cargo bay of Columbia.
STS-56 Discovery, April 8-17, 1993. Second flight of Atmospheric Laboratory for Applications and Science, ATLAS-2, mounted on Spacelab pallet.
STS-55 Columbia, April 26-May 6, 1993. Second dedicated German Spacelab flight, Spacelab D-2, featuring Spacelab laboratory module. 
STS-58 Columbia, Oct. 18-Nov. 1, 1993. Second dedicated Spacelab Life Sciences mission (SLS-2) using Spacelab module.
STS-62 Columbia, March 4-18, 1994. Second flight of U.S. Microgravity Payload-2 (USMP-2) mounted on two connected Spacelab Multipurpose Experiment Support Structures (MPESSs) in orbiter payload bay.
STS-65 Columbia, July 8-23, 1994. Second flight of International Microgravity Payload (IML-2) with Spacelab module.
STS-66 Atlantis, Nov. 3-14, 1994. Third flight of Atmospheric Laboratory for Applications and Science (ATLAS-3) on Spacelab pallet in payload bay.
STS-67 Endeavour, March 2-18, 1995. Second flight of astronomical observatory (ASTRO-2), mounted on Spacelab Instrument Pointing System and pallets in orbiter payload bay.
STS-73 Columbia, Oct. 20-Nov. 5, 1995. Second flight of U.S. Microgravity Laboratory (USML-2) in Spacelab module.
STS-75 Columbia, Feb. 22-March 9, 1996. Third flight of U.S. Microgravity Payload (USMP-3) on Spacelab pallet.
STS-78 Columbia, June 20-July 7, 1996. Life and Microgravity Spacelab (LMS) on longest Shuttle flight to date.
STS-83 Columbia, April 4-8, 1997.  Microgravity Science Laboratory-1. Planned 16-day mission cut short after fuel cell malfunction.
STS-94 Columbia, July 1-17, 1997.  Microgravity Science Laboratory-1 reflight.
factoid.jpg (1883 bytes)
 
Tracking and Data Relay Satellite (TDRS) System Missions -  Shuttle flights carrying deployable TDRS spacecraft and attached Inertial Upper Stage booster as primary payload:
STS-6 April 4-9, 1983. TDRS-A deployed, became TDRS-1 once on orbit.
STS 51-L Jan. 28, 1986.  TDRS-B, slated to become TDRS-2 on orbit, lost in Challenger accident. Its designation not re-assigned to subsequent TDRS spacecraft.
STS-26 Sept. 29-Oct. 3, 1988. TDRS-C deployed to become TDRS-3 on orbit.
STS-29 March 13-18, 1989. TDRS-D deployed to become TDRS-4 on orbit.
STS-43 Aug. 2-11, 1991. TDRS-E deployed to become TDRS-5 on orbit.
STS-54 Jan. 13-19, 1993. TDRS-F deployed to become TDRS-6 on orbit.
STS-70 July 13-22, 1995. TDRS-G deployed to become TDRS-7 on orbit.

factoid.jpg (1883 bytes)

Interplanetary Explorer Missions  -  Shuttle missions that an interplanetary explorer spacecraft was deployed.

STS-30 May 4-8, 1989. Magellan/Venus radar mapper attached to Inertial Upper Stage booster deployed on quest to complete radar mapping of Earth's nearest neighbor.
STS-34 Oct. 18-23, 1989. Galileo/Jupiter spacecraft, attached to Inertial Upper Stage booster, deployed on trajectory toward Jupiter.
STS-41 Oct. 6-10, 1990. European Space Agency-sponsored Ulysses spacecraft deployed, attach to two upper stages, Inertial Upper Stage and Payload Assist-Module-S boosters, on mission to explore polar regions of sun.

factoid.jpg (1883 bytes)

Great Observatory Missions - Shuttle missions during which one of NASA's great observatories for studying the solar system was deployed.

STS-31 April 24-29, 1990. First of NASA's great observatories, Hubble Space Telescope (HST), deployed.
STS-37 April 5-11, 1991. Second great observatory, Gamma Ray Observatory (GRO) deployed. Since renamed Compton Gamma Ray Observatory in honor of Arthur Holly Compton.
STS-93 July 23-27, 1999. Third great observatory, Chandra X-ray Observatory.

factoid.jpg (1883 bytes)

Hubble Space Telescope Missions

STS-31 Discovery, April 24-29, 1990. Hubble Space Telescope deployed to 380-statute-mile (612-kilometer) orbit
STS-61 Endeavour, Dec. 2-13, 1993. First mission to service and repair telescope.
STS-82 Discovery, Feb. 1997.  Second mission to service and repair telescope.  Additional servicing flights are planned over course of telescope's 15-year life expectancy.
STS-103 Discovery, Dec. 14, 1999.  Third mission to service and repair telescope.

factoid.jpg (1883 bytes)

U.S./Russian Missions  - Cooperative missions between NASA and the Russian Space Agency, being conducted as part of Phase I of the international space station program.

STS-60 Feb. 3-Feb. 11, 1994. First flight of Russian cosmonaut (Sergei Krikalev) on U.S. Space Shuttle.
STS-63 Feb. 3-Feb. 11, 1995. Second flight of a Russian cosmonaut (Vladimir Titov) on U.S. Space Shuttle. First approach and rendezvous with Russian Space Station Mir, serving as dress rehearsal for planned series of dockings between Shuttle and Mir.
STS-71 June 27-July 7, 1995. Third flight with Russian cosmonauts aboard: two aboard at launch (Solovyev and Budarin) transferred to Mir and two aboard Mir (Dezhurov and Strekalov) transferred to Shuttle for return flight to Earth.  First in a series of planned dockings between Shuttle and Mir.
STS-74 Nov. 12-20, 1995. Third rendezvous and second docking with Russian Space Station Mir. Russian-built Docking Module (DM) installed on Mir's Kristall module docking port to become a permanent extension to the station complex.
STS-76 March 22-31, 1996. Fourth rendezvous and third docking with Russian Space Station Mir. U.S. astronaut Shannon Lucid transferred to Mir to become first American woman on station.
STS-79 September 16-26, 1996. Fifth rendezvous and fourth docking with Russian Space Station Mir. U.S. astronaut John Blaha transferred to Mir; U.S. astronaut Shannon Lucid returned to Earth.  With STS-79 launch delays, Lucid remained in orbit 188 days, the longest spaceflight of an American to date.
STS-81 January 12, 1997.  Sixth rendezvous and fifth docking with Russian Space Station Mir.  U.S. astronaut Jerry Linenger transferred to Mir; U.S. astronaut John Blaha returned to Earth.
STS-84 May 15, 1997.  Seventh rendezvous and sixth docking with Russian Space Station Mir.  U.S. astronaut Michael Foale transferred to Mir; U.S. astronaut Jerry Linenger returned to Earth.
STS-86 September 25, 1997.  Eighth rendezvous and seventh docking with Russian Space Station Mir.  U.S. astronaut David Wolf transferred to Mir; U.S. astronaut Michael Foale returned to Earth.
STS-89 January 22, 1998.  Ninth rendezvous and eighth docking with Russian Space Station Mir.  U.S. astronaut Andrew Thomas transferred to Mir; U. S. astronaut David Wolf returned to Earth.
STS-91 June 2, 1998.  Tenth rendezvous, and ninth and final docking with Russian Space Station Mir.  U.S. astronaut Andrew Thomas returned to Earth.  Cosmonaut Valery Ryumin was a mission specialist on the crew.

factoid.jpg (1883 bytes)

SHUTTLE FUN FACTS

It takes only about eight minutes for the Space Shuttle to accelerate to a speed of more than 17,000 miles (27,358 kilometers) per hour.

The Space Shuttle main engine weighs 1/7th as much as a train engine but delivers as much horsepower as 39 locomotives.

The turbopump on the Space Shuttle main engine is so powerful it could drain an average family-sized swimming pool in 25 seconds.

The Space Shuttle's three main engines and two solid rocket boosters generate some 7.3 million pounds (3.3 million kilograms) of thrust at liftoff. Compare that with America's first two manned launch vehicles, the Redstone which produced 78,000 pounds (35,381 kilograms) of thrust, and the Atlas, which produced 360,000 pounds (163, 926 kilograms).

The liquid hydrogen in the Space Shuttle main engine is -423 degrees Fahrenheit (-253 degrees Centigrade), the second coldest liquid on Earth, and when burned with liquid oxygen, the temperature in the engine's combustion chamber reaches +6,000 degrees F. (+3,316 degrees C.)

The energy released by the three Space Shuttle main engines is equivalent to the output of 23 Hoover Dams.

Each of the Shuttle's solid rocket motors burns 5 tons (5,080 kilograms) of propellant per second, a total of 1.1 million pounds (500,000 kilograms) in 120 seconds. The speed of the gases exiting the nozzle is more than 6,000 miles (9,656 kilometers) per hour, about five times the speed of sound or three times the speed of a high-powered rifle bullet. The plume of flame ranges up to 500 feet (152 meters) long.

The combustion gases in a solid rocket motor are at a temperature of 6,100 degrees Fahrenheit (3,371 degrees Centigrade), two-thirds the temperature of the surface of the sun. While that temperature is hot enough to boil steel, special insulation inside the motor protects the steel case so well that the outside of the case reaches only about 130 degrees F. (54 degrees C.).

A stacked booster is the same height as the Statue of Liberty (not including pedestal) -- 151 feet (46 meters) -- but weighs almost three times as much.

The four engines of a Boeing 747 jet produce 188,000 pounds (85,277 kilograms) of thrust, while just one SRM produces more than 17 times as much thrust -- 3.3 million pounds (1.5 million kilograms). A pair of SRM's are more powerful than 35 jumbo jets at takeoff.

If their heat energy could be converted to electric power, two SRMs firing for two minutes would produce 2.2 million kilowatt hours of power, enough to supply the entire power demand of 87,000 homes for a full day.

The Shuttle's Remote Manipulator System (RMS), or robot arm, provided by the Canadian Space Agency, weighs about 905 pounds (411 kilograms) on Earth but can move cargo in space weighing 66,000 pounds (29,938 kilograms), objects about the size of a Greyhound bus.

Go to the Media Resources Home Page
factoid.jpg (1883 bytes)
 
Page Last Revised Page & Curator Information
November 12, 2002
Curator: Anna Heiney (anna.heiney@jbosc.ksc.nasa.gov) / InDyne, Inc.
NASA Official: Dennis W. Armstrong  (Dennis.Armstrong-1@ksc.nasa.gov)
Web Development: JBOSC Web Development Team
A service of the NASA/Kennedy Space Center External Relations and Business
Development Directorate: JoAnn H. Morgan, Director