|
|
VEHICLE |
Atlantis/OV-104/ |
LOCATION |
Orbiter
Processing Facility bay 3 |
TARGET KSC LAUNCH
DATE/TIME |
NET
April 17, 2000 at about 7:03 p.m. (under review) |
TARGET KSC LANDING
DATE/TIME |
April
28, 2000 at about 2:01 p.m. |
LAUNCH
WINDOW |
10 minutes |
MISSION
DURATION |
10 days, 18
hours and 56 minutes |
CREW |
Halsell,
Horowitz,
Weber,
Williams,
Voss,
Helms,
Usachev |
ORBITAL ALTITUDE and
INCLINATION |
160
nautical miles/51.6 degrees |
|
|
Shuttle
Processing Note |
Space Shuttle Atlantis is now scheduled to roll out
to Launch Pad 39A Saturday at about 7 a.m. This schedule change is not expected
to impact the target launch date. Managers had to adjust the VAB processing
schedule to accommodate Atlantis' delayed rollover from the OPF and a minor
delay with Shuttle umbilical connections.
Today, workers will remove main engine No. 1 and
the replacement engine will be installed tomorrow. Once at the launch pad, the
main engine heat shields will be installed and engine No. 1 leak checks will
follow. At about midnight last night, the SPACEHAB payload began its move to the
launch pad. The payload arrived at about 4 a.m. and will be transferred to the
payload changeout room later today.
|
MISSION:
STS-92
-- 5th ISS Flight (3A) -- Z-1 Truss, PMA-3 |
|
VEHICLE |
Discovery/OV-103 |
LOCATION |
OPF
bay 1 |
TARGET KSC LAUNCH
DATE/TIME |
TBD |
TARGET KSC LANDING
DATE/TIME |
TBD |
MISSION
DURATION |
11
days |
CREW |
Duffy,
Melroy, Wakata, Chiao, Wisoff, Lopez-Alegria, McArthur |
ORBITAL ALTITUDE and
INCLINATION |
160
nautical miles/51.6 degrees |
|
|
Shuttle
Processing Note |
Servicing of Discovery's robot
arm end effector is complete and payload bay stowage is
slated for later today. Orbiter voltage testing concluded
yesterday. Auxiliary power unit lubrication oil servicing
is ongoing. Replacement of Discovery's window No. 3 is
under way. At the Hypergol Maintenance Facility, the
right-hand orbiter maneuvering system pod is undergoing
additional check valve inspections this week.
|
|
MISSION:
STS-97
-- 6th ISS Flight (4A) -- PV Module P6 |
|
VEHICLE |
Endeavour/OV-105 |
LOCATION |
OPF bay 2 |
TARGET KSC LAUNCH
DATE/TIME |
TBA |
TARGET KSC LANDING
DATE/TIME |
TBA |
MISSION
DURATION |
9 days |
CREW |
Jett,
Bloomfield, Tanner, Noriega, Garneau |
ORBITAL ALTITUDE and
INCLINATION |
173
nautical miles/51.6 degrees |
|
Shuttle
Processing Note |
Orbiter
maneuvering system pod functional tests continue.
Preparations are in work to install a wireless video
system aboard Endeavour.
|