[DOE
LETTERHEAD]
March 2, 2004
The Honorable John T. Conway
Chairman
Defense Nuclear Facilities Safety Board
625 Indiana Avenue, NW, Suite 700
Washington, DC 20004-2901
Dear Mr. Chairman:
This letter transmits the Programmatic Risk
Assessment for the Savannah River Site (SRS) Salt Processing Program
(Commitment 2.12 of the Department of Energy’s Implementation Plan in response
to Recommendation 2001-l), provides information on the Low Curie Salt (LCS) Program
(Commitment 2.11), and gives notice that Commitment 2.9 (Process the first
batch of LCS in Saltstone) was not met as scheduled.
In accordance with Commitment 2.12, please
find enclosed the Programmatic Risk Assessment for the SRS Salt Processing
Program (Enclosure 1). The assessment
covers the risks and proposed mitigation actions for the key facilities and
activities required to execute all three phases of the SRS Salt Processing
Program: LCS processing, low curie-high
actinide processing, and high curie-high actinide processing. The Department plans to maintain this
assessment and update it as needed. It
will be used as a management tool to ensure that risks are identified, managed,
and mitigated to support our Accelerated Cleanup Program goals.
One of the identified risks in the
Programmatic Risk Assessment is how ongoing litigation may delay certain
aspects of the Salt Processing Program. On July 3, 2003, parts of DOE Order 435.1 dealing
with the authority for determining waste incidental to reprocessing were
declared invalid by the U.S. District Court for the District of Idaho. This ruling currently is on appeal to the U.S.
Court of Appeals for the Ninth Circuit. Accordingly, the Programmatic Risk Assessment
did not undertake a probability or consequence analysis of the litigation’s
outcome on the Salt Processing Program and rated this risk as “Uncertain.” Once this litigation is resolved, the Department
will provide you with an update on salt waste processing and disposal plans.
An evaluation of the LCS Program as outlined
in Commitment 2.11 has found that while the LCS Program plans and schedules
have not been fully achieved, several key technical milestones have been met. The most significant of these are:
Several issues have prevented the LCS
Program from meeting all of its objectives.
Should you or your staff have any questions
concerning these issues, please contact Jeffrey Allison at (803) 952-6337 or me
at (202) 586-0738.
Sincerely,
Dr. Inés Triay
Deputy Chief Operating Officer
Office of Environmental Management
cc w/o encl:
Jessie Hill Roberson, EM- 1
Mark Whitaker, DR-1
Jeffrey Allison, SR