Filing Fees
» Annual Update of Filing Fees
Effective June 2, 2008
Petitions for Rate Approval pursuant to
Section 284.123(b)(2)
18 C.F.R. Section 381.403 |
$10,440.00 |
Petitions for issuance of declaratory orders
(except under Part 1 of the FPA)
18 C.F.R. Section 381.302(a) |
$20,970.00 |
Requests for Written Legal Interpretations
by the Office of General Counsel
(except requests that solely concern matters under Part 1
of the Federal Power Act) 18 C.F.R. Section 381.305(a) |
$6,010.00 |
Application for Pipeline Certificate Authorization pursuant to Section 284.224
18 C.F.R. Section 381.207(b)
|
$1,000.00 |
Application of Qualifying Status as a Small
Power Production Facility
18 C.F.R. Section 381.505(a) |
$18,030.00 |
Application of Qualifying Status as a Cogeneration
Facility
18 C.F.R Section 381.505(a) |
$20,410.00 |
Review of Department of Energy Remedial Order
18 C.F.R. Section 381.303
Amount in controversy |
$0 - 9,999 |
$100.00 |
$10,000 - 29,999 |
$600.00 |
$30,000 or more |
$30,620.00 |
Review of Department of Energy Denial of Adjustment
18 C.F.R. Section 381.304
Amount in controversy |
$0 - 9,999 |
$100.00 |
$10,000 - 29,999 |
$600.00 |
$30,000 or more |
$16,050.00 |
|
|
|