This is the accessible text file for GAO report number GAO-09-779T 
entitled 'Environmental Contamination: Lessons Learned from the Cleanup 
of Formerly Used Defense and Military Munitions Sites' which was 
released on June 10, 2009. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Testimony: 

Before the Subcommittee on Federal Workforce, Postal Service, and the 
District of Columbia; Committee on Oversight and Government Reform: 

United States Government Accountability Office: 
GAO: 

For Release on Delivery: 
Expected at 2:00 p.m. EDT:
Wednesday, June 10, 2009: 

Environmental Contamination: 

Lessons Learned from the Cleanup of Formerly Used Defense and Military 
Munitions Sites: 

Statement of Anu Mittal, Director:
Natural Resources and Environment: 

GAO-09-779T: 

GAO Highlights: 

Highlights of GAO-09-779T, a testimony before the Subcommittee on 
Federal Workforce, Postal Service and the District of Columbia; 
Committee on Oversight and Government Reform. 

Why GAO Did This Study: 

Under the Defense Environmental Restoration Program (DERP), the 
Department of Defense (DOD) has charged the Army Corps of Engineers 
(the Corps) with cleaning up 4,700 formerly used defense sites (FUDS) 
and active sites that were under its jurisdiction when they were 
initially contaminated. The 661-acre Spring Valley site in Washington, 
D.C is one such site. Like many other FUDS, the U.S. Army used the 
Spring Valley site during World War I for research and testing of 
chemical agents, equipment, and munitions. Most of the site is now 
privately owned and includes private residences, a hospital, and 
several commercial properties. The primary threats at the site are 
buried munitions, elevated arsenic in site soils, and laboratory waste; 
perchlorate was also found onsite. 

This testimony discusses GAO’s past work relating to remediation 
efforts at FUDS and military munitions sites to provide context for 
issues at Spring Valley. Specifically, it addresses: (1) the impact 
that shortcomings in information and guidance can have on decision-
making; (2) the impact that incomplete data can have on cost estimates 
and schedules; (3) how funding for a particular site may be influenced 
by overall program goals; and (4) how better coordination can increase 
public confidence in cleanups and facilitate effective decision-making. 

GAO has made several prior recommendations that address these issues, 
with which, in most cases, the agency concurred. 

What GAO Found: 

GAO’s past work has found significant shortcomings in the Corps’ use of 
available information and guidance for making decisions relating to 
cleanup of FUDS. For example, in 2002, GAO found that the Army 
determined that there was no evidence of large–scale burials of hazards 
remaining at Spring Valley before it had received all technical input. 
This experience is not unique. In a 2002 national study, GAO reported 
that the Corps did not have a sound basis for determining that about 
1,468 of 3,840 FUDS properties––38 percent––did not need further study 
or cleanup action. GAO attributed these shortcomings to limitations in 
the Corps guidance that did not specify what documents or level of 
detail the agency should obtain to identify potential hazards at FUDS 
or how to assess the presence of potential hazards. 

GAO’s past work has also shown that incomplete data on site conditions 
and emerging contaminants can interfere with the development of 
accurate cost and schedule estimates. At Spring Valley, the Corps’ 
estimates of cleanup costs increased by about six fold, from about $21 
million to about $124 million from fiscal year 1997 through fiscal year 
2001. As assumptions about site conditions changed and new hazards were 
discovered, the estimates continued to rise and currently stand at 
about $174 million. Again, these problems are not unique. In 2004, GAO 
evaluated DOD’s cleanup of sites with military munitions and found 
several similar weaknesses in preliminary cost estimates for numerous 
sites across the country. 

GAO’s past work has shown that funding available for specific sites may 
be influenced by overall program goals and other priorities. Spring 
Valley has received priority funding due to its proximity to a major 
metropolitan area and high visibility; however, GAO’s past work shows 
that this is usually not the case with most FUDS sites. Over the past 
10 years DOD has invested nearly $42 billion in its environmental 
programs, but it typically requests and receives a relatively smaller 
amount of funding for environmental restoration activities at FUDS 
sites compared to funding available for active sites. 

GAO’s past work has found that better coordination and communication 
with regulators and property owners can increase public confidence and 
facilitate effective decision-making for contaminated sites. With 
regard to Spring Valley, GAO reported in 2002 that the Corps, the 
Environmental Protection Agency (EPA) and the District of Columbia had 
made progress because they had adopted a partnership approach to 
cleanup decisions. However, this kind of cooperation and coordination 
does not always occur nationwide. For example, in 2003, GAO reported 
that the Corps only informed states of upcoming work and requested 
input from them about half of the time. Similarly, GAO found that the 
Corps did not always communicate with property owners about the 
decisions it makes regarding contamination at FUDS sites and more often 
than not did not inform property owners about how to contact the Corps 
in the event that further hazardous substances were identified at the 
site. 

View [hyperlink, http://www.gao.gov/products/GAO-09-779T] or key 
components. For more information, contact Anu Mittal at (202) 512-
3841or mittala@gao.gov. 

[End of section] 

Mr. Chairman and Members of the Subcommittee: 

I am pleased to be here today to discuss GAO's work relating to the 
Department of Defense's (DOD) remediation efforts at Formerly Used 
Defense sites (FUDS) and sites with military munitions around the 
country, which we believe will provide context for the issues faced by 
the Spring Valley site, in Washington D.C. Spring Valley is one of 
4,700 FUDS--properties that DOD owned or controlled and transferred to 
private parties or other government entities prior to October 1986. 
Under the Defense Environmental Restoration Program (DERP), DOD is 
required to identify, investigate, and clean up environmental 
contamination and other hazards at both active sites and FUDS that were 
under its jurisdiction when they were initially contaminated. The FUDS 
inventory includes sites with a variety of cleanup needs. These 
properties may contain hazardous, toxic, and radioactive wastes in the 
soil and water or in containers such as underground storage tanks. 
Other hazards, including unexploded ordnance and unsafe buildings may 
also be present. As you know, such hazards can contribute to deaths and 
serious illness or pose a threat to the environment. 

The Spring Valley site was originally known as the American University 
Experiment Station, and covers approximately 661 acres in the northwest 
section of Washington, D.C. Like many other FUDS, the U.S. Army used 
the Spring Valley site during World War I for research and testing of 
chemical agents, equipment, and munitions. After World War I, the 
majority of the site was returned to private ownership and developed 
for residential and other uses, becoming the Spring Valley 
neighborhood. The site now includes American University, about 1,200 
private residences, Sibley Hospital, numerous embassy properties, and 
several commercial properties. During the 1950s and again in the 1980s, 
American University and others raised concerns about buried munitions 
in the Spring Valley neighborhood. An Army investigation concluded in 
1986 that no large burials of ordnance remained on the site; however, 
in 1993, the site received a FUDS designation after a contractor 
unearthed buried military ordnance while digging a utility trench. 
Investigations of the site expanded, and in 1996, the Army again 
concluded there were no remaining large ordnance areas; however, follow-
on work found additional large-scale hazards, including more than 600 
pieces of ordnance, arsenic contaminated soil, and lab waste. More 
recently, perchlorate,[Footnote 1] an emerging contaminant--a term for 
chemicals or materials lacking a federal regulatory standard, with a 
potential threat to health or the environment--was also found on the 
site. Perchlorate is known to cause health problems in certain 
populations. The estimated total cost for completing the project was 
$173.7 million in fiscal year 2007, according to the latest Defense 
Environmental Program Annual Report to Congress. 

Although GAO last reviewed the progress of the Spring Valley Cleanup in 
2002, since that time we have conducted a number of reviews relating to 
the management and cleanup challenges that DOD faces when addressing 
contamination at FUDS and other sites with military munitions across 
the country. We also currently have two ongoing reviews related to 
FUDS--one addressing the management of FUDS broadly and one 
specifically addressing the munitions cleanup program--the latter study 
was mandated by the fiscal year 2009 National Defense Authorization 
Act. These reports are expected for release in fiscal year 2010. 

My testimony is based on this body of work and will address four main 
themes and lessons learned that we believe provide context for 
assessing the progress made at the Spring Valley site. The four themes 
that my statement addresses include: (1) the impacts that shortcomings 
in the use of available information and guidance can have on decision- 
making; (2) the impacts that incomplete data on site conditions and 
emerging contaminants can have on the development of accurate cost 
estimates and schedules; (3) how funding available for a particular 
site may be influenced by overall program goals and other priorities; 
and (4) how better coordination with regulators and property owners can 
increase public confidence in cleanups and facilitate effective 
decision-making. 

We conducted our work in accordance with GAO's Quality Assurance 
Framework, which requires that we plan and perform each engagement to 
obtain sufficient and appropriate evidence to meet our stated 
objectives and to discuss any limitations in our work. We believe that 
the information and data obtained, and the analyses conducted, provided 
a reasonable basis for the findings and conclusions in these reports. 

Background: 

Under the DERP, DOD is authorized to identify, investigate and clean up 
environmental contamination and other hazards at FUDS as well as active 
installations. To that end, DOD has established restoration goals and 
identified over 31,000 sites that are eligible for cleanup, including 
more than 21,000 sites on active installations, more than 5,000 sites 
on installations identified for Base Realignment and Closure (BRAC), 
and 4,700 FUDS. The DERP was established by section 211 of the 
Superfund Amendments and Reauthorization Act of 1986 (SARA) which 
amended the Comprehensive Environmental Response Compensation and 
Liability Act (CERCLA) of 1980. Under the DERP, DOD's activities 
addressing hazardous substances, pollutants or contaminants are 
required to be carried out consistent with section 120 of CERCLA. DOD 
delegated its authority for administering the cleanup of FUDS to the 
Army, which in turn delegated its execution to the Army Corps of 
Engineers (the Corps). Funding for cleanup activities comes from the 
Environmental Restoration and BRAC accounts. The Environmental 
Restoration account funds cleanup at active sites and FUDS properties 
and, of the $1.4 billion obligated in fiscal year 2007, FUDS property 
obligations totaled $116.5 million for addressing hazardous substances 
and $102.9 million for munitions response. 

To be eligible for FUDS cleanup, a property must have been owned by, 
leased to, possessed by, or otherwise controlled by DOD during the 
activities that led to the presence of hazards. These hazards may 
include unsafe buildings, structures, or debris, such as weakened load- 
bearing walls; hazardous, toxic, and radioactive substances, which 
includes contaminants such as arsenic, certain paints, some solvents, 
and petroleum; containerized hazardous, toxic, and radioactive waste, 
such as transformers and aboveground or underground storage tanks that 
contain petroleum, solvents, or other chemicals which have been 
released into the environment; and ordnance and explosive materials, 
such as military munitions and chemical warfare agents. To determine if 
a property is eligible for cleanup under the FUDS program, the Corps 
conducts a preliminary assessment of eligibility to determine whether 
the property was ever owned or controlled by DOD and if hazards caused 
by DOD's use may be present. If the Corps determines that the property 
was owned or controlled by DOD but does not find evidence of any 
hazards caused by DOD, it designates the property as "no DOD action 
indicated" (NDAI). If however, the Corps determines that a DOD-caused 
hazard may be present, the Corps begins to further study and/or clean 
up the hazard, consistent with CERCLA. The CERCLA process generally 
includes the following phases: preliminary assessment, site inspection, 
remedial investigation/feasibility study, remedial design/remedial 
action, and long-term monitoring. 

To address the release of hazardous substances, pollutants, or 
contaminants resulting from past practices that pose environmental 
health and safety risks on both active sites and FUDS, DOD established 
the Installation Restoration Program (IRP) in 1985 under the DERP. In 
fiscal year 2007, the Corps had 2,612 FUDS in the IRP.[Footnote 2] 
Performance metrics and comprehensive goals have been developed by DOD 
to assess progress toward the agency's IRP goals. These goals include 
progress in reaching a CERCLA cleanup phase at the site level, progress 
toward achieving a "remedy in place" or "response complete" status at 
the installation level, and progress in achieving overall relative-risk 
reduction. Specific targets are included in DOD's annual report to 
Congress. 

To better focus its munitions cleanup activities on both active sites 
and FUDS, DOD established the Military Munitions Response Program 
(MMRP) in September 2001, as part of the DERP, specifically to address 
potential explosive and environmental hazards associated with 
munitions. The objectives of the program include compiling a 
comprehensive inventory of military munitions sites, establishing a 
prioritization protocol for sequencing work at these sites, and 
establishing program goals and performance measures to evaluate 
progress. In December 2001, shortly after DOD established the program, 
the Congress passed the National Defense Authorization Act for fiscal 
year 2002, which, among other things, required DOD to develop an 
initial inventory of defense sites, other than military ranges still in 
operation, that are known or suspected to contain military munitions by 
May 31, 2003, and to provide annual updates thereafter. DOD provides 
these updates as part of its annual report to Congress on Defense 
environmental programs; in its 2007 report DOD had identified 3,537 
sites suspected or known to have munitions contamination, an increase 
of 221 sites from fiscal year 2006. Table 1 provides a summary of DOD 
performance goals for MMRP and IRP. 

Table 1: Summary of DOD Performance Goals for MMRP and IRP: 

Phase/priority: Preliminary assessment; 
Target year for completing cleanup phase for all sites: Installation 
restoration program (IRP): No goal established; 
Target year for completing cleanup phase for all sites: Military 
munitions response program (MMRP): 2007. 

Phase/priority: Site inspections; 
Target year for completing cleanup phase for all sites: Installation 
restoration program (IRP): No goal established; 
Target year for completing cleanup phase for all sites: Military 
munitions response program (MMRP): 2010. 

Phase/priority: For High Priority Sites: Remedy in Place or Response 
Complete (RIP/RC), or cleaned up to a lower risk level; 
Target year for completing cleanup phase for all sites: Installation 
restoration program (IRP): 2007; 
Target year for completing cleanup phase for all sites: Military 
munitions response program (MMRP): No goal established. 

Phase/priority: For Medium Priority Sites: RIP/RC (or cleaned up to a 
lower risk level); 
Target year for completing cleanup phase for all sites: Installation 
restoration program (IRP): 2011; 
Target year for completing cleanup phase for all sites: Military 
munitions response program (MMRP): No goal established. 

Phase/priority: For Low Priority Sites: RIP/RC (or cleaned up to a 
lower risk level); 
Target year for completing cleanup phase for all sites: Installation 
restoration program (IRP): 2014 - Active; 2020 - FUDS; 
Target year for completing cleanup phase for all sites: Military 
munitions response program (MMRP): No goal established. 

Source: Fiscal Year 2007 Annual Report to Congress, Department of 
Defense, Defense Environmental Programs. 

[End of table] 

The Spring Valley Site: 

The principal government entities involved in the Spring Valley cleanup 
include the Corps, the Environmental Protection Agency (EPA), and the 
District of Columbia. The Corps has led the effort of identifying, 
investigating, and cleaning up contamination at the site, whereas EPA 
primarily consulted with and provided technical assistance to the Corps 
and the District of Columbia. The District of Columbia's Department of 
Health has monitored the cleanup's status and adequacy, conducting such 
actions as, according to the Department, assessing the human health 
risks associated with any exposure to remaining hazards at Spring 
Valley. Additionally, advisory entities were created to further 
facilitate decision-making on technical topics. 

In 2002, we reported that cleanup progress included the identification 
and removal of a large number of hazards, including buried ordnance, 
chemical warfare agents in glass containers, and arsenic-contaminated 
soil.[Footnote 3] By April 2002 the Corps had identified and removed 
5,623 cubic yards of arsenic-contaminated soil from 3 properties and 
removed 667 pieces of ordnance--25 of which were chemical munitions-- 
and 101 bottles of chemicals. A March 2009 project overview report by 
the Corps indicated that, in 2004, the Corps excavated 474 drums of 
soil and recovered more than 800 items, such as construction debris, 
ordnance scrap, and laboratory glassware and ceramic pieces. The report 
also indicated that, by 2006, the Corps removed 5,500 cubic yards of 
soil, 117 munitions debris items, 6 intact munitions items, and 31 
intact containers; in addition, the excavation, backfilling, and 
restoration of the debris field that contained these materials was 
completed. 

We reported in 2002 that the primary health risks that influenced 
cleanup activities were (1) the possibility of injury or death from 
exploding or leaking ordnance and containers of chemical warfare 
agents; and (2) potential long-term health problems, such as cancers 
and other health conditions, from exposure to arsenic-contaminated 
soil. A study by the Department of Health and Human Services' Agency 
for Toxic Substances and Disease Registry found no evidence of 
significant exposure to arsenic in the individuals tested in 2002. In 
2003, the Corps discovered perchlorate in groundwater at the site, and 
installed at least 38 monitoring wells for sampling. Sampling results 
identified elevated levels of perchlorate in the project area. Further 
investigation is underway with more wells and sampling planned in 2009. 
In April 2002, the Army estimated that the remaining cleanup activities 
at Spring Valley would take 5 years to complete. Total costs for the 
project were estimated at $145.9 million in fiscal year 2002; by fiscal 
year 2007, the estimated total costs increased to $173.7 million. 
Figure 1 presents information on the annual cost to complete[Footnote 
4] and annual amounts spent to date from 2003 to the present at the 
Spring Valley site. 

Figure 1: Total Estimated Cost to Clean Up Spring Valley, Fiscal Years 
2003 through 2007: 

[Refer to PDF for image: stacked vertical bar graph] 

Fiscal year: 2003; 
Total cost incurred through FY: $79.9 million; 
Total cost to complete: $43.9 million. 

Fiscal year: 2004; 
Total cost incurred through FY: $92.1 million; 
Total cost to complete: $62.6 million. 

Fiscal year: 2005; 
Total cost incurred through FY: $112.4 million; 
Total cost to complete: $56.8 million. 

Fiscal year: 2006; 
Total cost incurred through FY: $123.5 million; 
Total cost to complete: $45.4 million. 

Fiscal year: 2007; 
Total cost incurred through FY: $137.3 million; 
Total cost to complete: $36.4 million. 

Sources: Defense Environmental Restoration Program Annual Report to 
Congress for Fiscal Year 2003. Defense Environmental Programs Annual 
Reports to Congress for Fiscal Years 2004 through 2007. 

[End of figure] 

Shortcomings in the Use of Available Information and Guidance Can Lead 
to Poor Decision-making: 

When we reviewed the Spring Valley cleanup in 2002, we found that the 
Army determined that there was no evidence of large-scale burials of 
hazards remaining at Spring Valley before it received all technical 
input.[Footnote 5] For example, while the Army's Toxic and Hazardous 
Materials Agency reviewed work done by American University and 
documentation from additional sources, it also contracted with EPA's 
Environmental Photographic Interpretation Center to review available 
aerial photographs of the site taken during the World War I era. 
However, the photographs were not received or reviewed prior to 1993, 
according to EPA officials. Despite never having received technical 
input from EPA on the aerial photographs, in 1986 the Army concluded 
that if any materials were buried in the vicinity of the university, 
the amounts were probably limited to small quantities and no further 
action was needed. However, as we now know, subsequent investigations 
by the Army discovered additional ordnance in large burial pits and 
widespread arsenic-contaminated soil. 

The experience at Spring Valley is by no means a unique occurrence. Our 
review of other FUDS nationwide found significant shortcomings in the 
Corps' use of available information and guidance for making decisions 
relating to cleanup of contamination at these sites. For example, in 
2002, we reported that the Corps did not have a sound basis for 
determining that about 1,468 of 3,840 FUDS properties--38 percent--did 
not need further study or cleanup action.[Footnote 6] Specifically, we 
found: 

* No evidence that the Corps reviewed or obtained information that 
would allow it to identify all the potential hazards at these 
properties or that it took sufficient steps to assess the presence of 
potential hazards. 

* That for about 74 percent of all NDAI properties, the site assessment 
files were incomplete--i.e., the files lacked information such as site 
maps or photos that would show facilities, such as ammunition storage 
facilities, that could indicate the presence of hazards (e.g. 
unexploded ordnance). 

* That for about 60 percent of all NDAI properties the Corps may not 
have contacted all the current owners to obtain information about 
potential hazards present on the site. 

* The Corps appeared to have overlooked or dismissed information in its 
possession that indicated hazards might be present. For example, at a 
nearly 1,900 acre site previously used as an airfield by both the Army 
and the Navy, the file included a map showing bomb and fuse storage 
units on the site that would suggest the possible presence of ordnance- 
related hazards; however, we found no evidence that the Corps searched 
for such hazards. 

* The files contained no evidence that the Corps took sufficient steps 
to assess the presence of potential hazards. For example, although 
Corps guidance calls for a site visit to look for signs of potential 
hazards, we estimated that the Corps did not conduct the required site 
visit for 686 or about 18 percent of all NDAI properties. 

We found that these problems occurred in part because the Corps' 
guidance did not specify (1) what documents or level of detail the 
agency should obtain when looking for information on the prior uses of 
and the facilities located at FUDS properties to identify potential 
hazards or (2) how to assess the presence of potential hazards. For 
example, some Corps district staff stated that there was no guidance 
showing the types of hazard normally found at certain types of 
facilities. We concluded that, since many properties may have not been 
properly assessed, the Corps did not know the number of additional 
properties that may require cleanup, the hazards that were present at 
those properties, the risk associated with these hazards, the length of 
time needed for cleanup, or the cost to clean up the properties. 

To address these problems, we recommended that the Corps develop more 
specific guidelines and procedures for identifying and assessing 
potential hazards at FUDS and to use them to review NDAI files and 
determine which properties should be reassessed. DOD told us that it 
has implemented this recommendation; however, according to one major 
association of state regulators, problems persist in how the Corps 
makes NDAI determinations in many cases. In 2008, the association 
published a fact sheet indicating, among other things, that the 
evidence collected is not adequate for making determinations.[Footnote 
7] We will be reviewing some aspects of this decision making process as 
part of our ongoing work on FUDS and MMRP. 

Incomplete Data on Site Conditions and Emerging Contaminants Can 
Interfere With the Development of Accurate Cost Estimates and 
Schedules: 

At Spring Valley, the Corps' estimate of the cost to complete cleanup 
of the site increased by about six fold--from about $21 million to 
about $124 million--from fiscal year 1997 through 2001. Factors such as 
the future discovery of hazards made it inherently challenging for the 
Corps to estimate the costs for completing cleanup activities at the 
site. Future estimates of the cost to complete cleanup of the site also 
depend on assumptions about how many properties require the removal of 
arsenic-contaminated soil and how many properties need to be surveyed 
and excavated to remove possible buried hazards. As these assumptions 
have changed, the cost to cleanup Spring Valley has continued to rise 
where the most recent estimate for fiscal year 2007 is $173.7 million. 

The challenges of estimating the costs of the Spring Valley cleanup are 
common to many FUDS, and our past work has shown that incomplete data 
on site conditions and emerging contaminants can interfere with the 
development of accurate cost and schedule estimates. For example, in 
2004, we evaluated DOD's MMRP program and found several weaknesses in 
preliminary cost estimates for numerous sites.[Footnote 8] We found 
that a variety of factors, including the modeling tool used to compile 
cost estimates, contributed to these weaknesses. Specifically, when 
detailed, site-specific information was not available for all sites, we 
found that DOD used estimates, including assumptions about the amount 
of acreage known or suspected of containing military munitions when 
preparing its cost projections. As a result, the cost estimates varied 
widely during the life of some cleanup projects. For example, the Corps 
confirmed the presence of unexploded ordnance at Camp Maxey in Texas, 
and in 2000, estimated cleanup costs at $45 million. In its fiscal year 
2002 annual report, DOD reported that the estimated total cost had 
tripled and grown to $130 million, and then in June 2003, the estimate 
decreased to about $73 million--still 62 percent more than the original 
cost estimate. The main factors behind these shifting cost estimates, 
according to the project manager, were changes in the acreage requiring 
underground removal of ordnance and changes in the amount of ordnance 
found. 

To address the challenges of estimating costs, schedules, and other 
aspects of munitions response, we made a number of recommendations 
related to various elements of DOD's comprehensive plan for 
identifying, assessing and cleaning up military munitions at 
potentially contaminated sites. In its response to our 2004 report and 
recommendations, DOD said that it was working on developing better cost 
estimates, and that the Corps would designate 84 percent of its 
environmental restoration budget in fiscal year 2007 for investigations 
and cleanup actions. According to DOD, this funding would help the 
Corps gather more site specific information, which in turn could be 
used for better determining the expected cost to complete cleanup at 
FUDS. 

We found that these concerns are also not limited to just FUDS but also 
affect operational ranges as well.[Footnote 9] When we reviewed the 
development of DOD's cost estimates for addressing potential 
liabilities associated with unexploded ordnance, discarded military 
munitions, and munitions constituents on operational ranges, we found 
that DOD's cost estimates for cleanup were questionable because the 
estimates were based on inconsistent data and invalidated assumptions. 
[Footnote 10] 

The presence of newly identified contaminants at sites needing cleanup 
further complicates DOD's efforts to develop reliable cost estimates. 
In 2004, we found that DOD does not have a comprehensive policy 
requiring sampling or cleanup of the more than 200 chemical 
contaminants associated with military munitions on operational ranges. 
Of these 200 contaminants, 20 are of great concern to DOD due to their 
widespread use and potential environmental impact--including 
perchlorate. According to our 2005 report, perchlorate has been found 
in the drinking water, groundwater, surface water, or soil in 35 
states, the District of Columbia (including the Spring Valley site), 
and 2 commonwealths of the United States.[Footnote 11] In its 2007 
Annual Report to Congress, DOD indicated that new requirements to 
address emerging contaminants like perchlorate will drive its 
investments in cleanup, and require modifications in plans and 
programs, and adjustments to total cleanup and cost to complete 
estimates. However, there is limited information on the potential costs 
of addressing these emerging contaminants and how their cleanup may 
affect overall site cleanup schedules. This is partly because none of 
these munitions constituents are currently regulated by a federal 
drinking water standard under the Safe Drinking Water Act, although 
perchlorate, for example, is the subject of a federal interim health 
advisory and several state drinking water standards. Our 2004 report 
recommended that DOD provide specific funding for comprehensive 
sampling for perchlorate at sites where no sampling had been conducted; 
although DOD disagreed at the time, it recently took action to sample 
hundreds of locations nationwide. 

Funding Available for a Particular Site May Be Influenced by Overall 
Program Goals and Other Priorities: 

Spring Valley has received priority funding due to its proximity to the 
nation's capitol and high visibility; however, our past work shows that 
this is not the case with most FUDS. Over the past 10 years DOD has 
invested nearly $42 billion in its environmental programs, which 
include compliance, restoration, natural resources conservation, and 
pollution prevention activities. In fiscal year 2007, DOD obligated 
approximately $4 billion for environmental activities, but only $1.4 
billion of this total was utilized for DERP environmental restoration 
activities at active installations and FUDS. Of this amount, $1.2 
billion funded cleanup of hazardous substances, pollutants and 
contaminants from past DOD activities through the Installation 
Restoration Program (IRP) and $215.8 million funded activities to 
address unexploded ordnance, discarded military munitions and munitions 
constituents through the Military Munitions Response Program (MMRP). 
Figure 2 shows expenditures through fiscal year 2007, DOD's estimated 
costs to complete, and the fiscal year 2007 obligations for the IRP and 
MMRP at active sites and FUDS. 

Figure 2: Funding Summary for IRP and MMRP Programs: 

[Refer to PDF for image: vertical bar graph] 

Program: Expenditure through FY 2007; 	
IRP: $19.8 billion; 
MMRP: $0.9 billion. 

Program: Cost to complete as of 2007; 	
IRP: $10.2 billion; 
MMRP: $18.3 billion. 

Program: FY 2007 obligation; 	
IRP: $1.2 billion; 
MMRP: $0.2 billion. 

Source: Defense Environmental Programs Annual Report to Congress for 
Fiscal Year 2007. 

[End of figure] 

DOD requests separate funding amounts for active sites and FUDS cleanup 
programs based on specific DERP restoration goals and the total number 
of sites in each program's inventory. Goals are set separately for the 
IRP and MMRP; target dates for cleanup of high priority sites are 
different for these programs. Furthermore, while DOD has established 
Department-wide goals, each service has its own goals, which may 
differ, and determines the allocation of funds between IRP and MMRP. 
Specifically, for the IRP, the DOD goal is to have a remedy in place or 
response complete for all active sites and FUDS by fiscal year 2020. 
However, DOD has requested much greater budgets for active sites than 
for FUDS. For example, DOD requested $257.8 million for FUDS or only 
one-fifth of the amount requested for active sites for fiscal year 
2009. Similarly, obligations in fiscal year 2007 totaled $969.8 million 
for active sites, whereas FUDS obligations only totaled $219.4 million. 
According to the most recent annual report to Congress, DOD does not 
expect to complete the IRP goal for FUDS until fiscal year 2060. DOD is 
aiming to complete cleanup of IRP sites much earlier than MMRP sites, 
even if higher-risk MMRP sites have not yet been addressed. 

For MMRP, DOD's first goal was to complete preliminary assessments for 
FUDS as well as active sites, by the end of fiscal year 2007.[Footnote 
12] DOD reported that it has reached this goal for 96 percent of MMRP 
sites. However, it is not clear if this percentage includes sites 
recently added to the site inventory. DOD also has an MMRP goal of 
completing all site inspections by the end of fiscal year 2010, but has 
not yet set a goal for achieving remedy in place or response complete. 
Our ongoing reviews of the FUDS and MMRP programs will include more in- 
depth analyses of the prioritization processes used by DOD for active 
sites and FUDS. 

Better Coordination and Communication with Regulators and Property 
Owners Can Increase Public Confidence and Facilitate Effective Decision-
making: 

In our 2002 report on Spring Valley, we reported that the Corps, EPA 
and the District of Columbia had made progress on site cleanup by 
adopting a partnership approach for making cleanup decisions.[Footnote 
13] Importantly, they established a systematic means of communicating 
information to, and receiving input from, the residents of Spring 
Valley and other interested members of the public. While the entities 
did not agree on all cleanup decisions, officials of all three 
entities--the Corps, the District of Columbia, and EPA--stated that the 
partnership had been working effectively. However, we have found that 
this kind of cooperation and coordination does not always occur at 
other sites nationwide. For example: 

* In 2003, we conducted a survey to determine how the Corps coordinates 
with state regulators during the assessment and cleanup of FUDS. We 
found that the Corps did not involve the states consistently, and that 
EPA had little involvement in the cleanup of most FUDS.[Footnote 14] We 
found that the Corps informed states of upcoming work at hazardous 
waste projects 53 percent of the time and requested states' input and 
participation 50 percent of the time. We reported that federal and 
state regulators believed that better coordination with the Corps 
regarding cleanup at FUDS would increase public confidence in the 
cleanups and improve their effectiveness. 

* Some state regulators told us that inadequate Corps coordination has 
made it more difficult for them to carry out their regulatory 
responsibilities at FUDS properties and that, because of their lack of 
involvement, they have frequently questioned Corps cleanup decisions at 
FUDS. Conversely, when Corps coordination has occurred, states have 
been more likely to agree with Corps decisions. Several states also 
told us that they would like to see EPA become more involved in the 
cleanup process, for example, by participating in preliminary 
assessments of eligibility or providing states with funds to review 
Corps work. EPA also believed that a better-coordinated effort among 
all parties would improve the effectiveness of cleanup at FUDS and 
increase public confidence in the actions taken at these sites, but 
emphasized it did not expect its involvement to be consistent across 
all phases of work; rather, that it would increase its involvement at a 
site when conditions warranted--for example, if there were "imminent 
and substantial endangerment" or if it had concerns about the 
appropriateness of the cleanup. 

We also found that EPA and DOD disagreed on EPA's role in the FUDS 
program. Although EPA is the primary regulator for the FUDS that are on 
the National Priorities List, the states are typically the primary 
regulatory agency involved for all other FUDS. EPA told us that its 
role at some of these unlisted FUDS should be greater because it 
believes it can help improve the effectiveness of the cleanups and 
increase public confidence in the program. DOD and some states 
disagreed with this position because they do not believe there is a 
need for additional EPA oversight of DOD's work at unlisted FUDS 
properties where the state is the lead regulator. We concluded in 2003 
that the lack of a good working relationship between two federal 
cleanup agencies may hamper efforts to properly assess properties for 
cleanup and may, in some cases, result in some duplication of effort. 

We also concluded in this 2003 report that a factor behind the 
historical lack of consistency in the Corps coordination with 
regulators could be that DOD and Corps guidance does not offer specific 
requirements that describe exactly how the Corps should involve 
regulators. To address these shortcomings, we recommended that DOD and 
the Corps develop clear and specific guidance that explicitly includes, 
among other things, what coordination should take place during 
preliminary assessments of eligibility on projects involving ordnance 
and explosive waste. We also recommended that DOD and the Corps assess 
recent efforts to improve coordination at the national as well as 
district level and promote wider distribution of best practices; and 
work with EPA to clarify their respective roles in the cleanup of 
former defense sites that are not on the National Priorities List. DOD, 
representing the Corps and DOD, generally agreed with our 
recommendations and has since implemented additional changes to improve 
its coordination with regulators, including revising its guidance to 
include step-by-step procedures for regulatory coordination at each 
phase of FUDS cleanup. However, we have not reassessed DOD's efforts or 
reviewed its coordination efforts since our 2003 report. 

In addition to better coordination with regulators, our past work has 
shown that the Corps frequently did not notify property owners of its 
determinations that the properties did not need further action, as 
called for in its guidance, or instruct the owners to contact the Corps 
if evidence of DOD-caused hazards was found later. In 2002, we 
estimated that the Corps failed to notify current owners of its 
determinations for about 72 percent of the properties that the Corps 
determined did not need further study or cleanup action.[Footnote 15] 
Even when the Corps notified the owners of its determinations, we 
estimated that for 91 percent of these properties it did not instruct 
the owners to contact the Corps if evidence of potential hazards was 
found later. In some cases, several years elapsed before the Corps 
notified owners of its determinations. We concluded that this lack of 
communication with property owners hindered the Corps' ability to 
reconsider, when appropriate, its determinations that no further study 
or cleanup action was necessary. 

As a result of our findings, we recommended that the Corps consistently 
implement procedures to ensure that owners are notified of NDAI 
determinations and its policy of reconsidering its determinations if 
evidence of DOD-caused hazards is found later. DOD has implemented this 
recommendation although we have not reviewed its implementation. 

In conclusion, Mr. Chairman, as we move forward on the cleanup of the 
Spring Valley site, we believe that the lessons learned from DOD's 
national environmental cleanup programs provides valuable insights that 
could guide decision-making and also inform the oversight process. The 
experience at the national level tells us that while not all the 
information that DOD needs is always available, it is imperative that 
the information that is available should be duly considered when 
developing cleanup plans and estimates. Moreover, involving regulators 
and property owners can also better ensure that DOD has the best 
information on which to make its decisions. Finally, it is important to 
recognize that emerging and unexpected situations can cause significant 
changes in both cost and time schedules and this could have funding 
implications as well for specific cleanup sites. 

This concludes my prepared statement. I will be happy to respond to any 
questions from you or other Members of the Subcommittee. 

Contact and Staff Acknowledgments: 

Contact points for our Offices of Congressional Relations and Public 
Affairs may be found on the last page of this statement. For further 
information about this testimony, please contact Anu Mittal at (202) 
512-3841 or mittala@gao.gov. Key contributors to this testimony were 
Diane Raynes, Elizabeth Beardsley, Alison O'Neill, Justin Mausel, and 
Amanda Leisoo. 

[End of section] 

Footnotes: 

[1] Perchlorate is the primary oxidizer in propellants, present in 
varying amounts in explosives, and is highly soluble. Exposure to 
perchlorate affects the human thyroid, and certain levels of exposure 
may result in hyperthyroidism in adults and developmental delays in 
children. 

[2] There are also 422 Building Demolition/Debris Removal category 
sites in the FUDS IRP program. 

[3] GAO, Environmental Contamination: Many Uncertainties Affect the 
Progress of the Spring Valley Cleanup, [hyperlink, 
http://www.gao.gov/products/GAO-02-556] (Washington D.C.: June 6, 
2002). 

[4] DOD periodically estimates the remaining costs necessary to 
complete restoration based on data about contamination and cleanup 
requirements at each site; these estimates are known as "costs to 
complete." 

[5] GAO, Environmental Contamination: Many Uncertainties Affect the 
Progress of the Spring Valley Cleanup, [hyperlink, 
http://www.gao.gov/products/GAO-02-556] (Washington D.C.: June 6, 
2002). 

[6] GAO, Environmental Contamination: Corps Needs to Reassess Its 
Determinations That Many Former Defense Sites Do Not Need Cleanup, 
[hyperlink, http://www.gao.gov/products/GAO-02-658] (Washington D.C.: 
Aug. 23, 2002). 

[7] Military Munitions Response Program Preliminary Assessment/Site 
Investigation Fact Sheet, a report prepared by the Association of State 
and Territorial Solid Waste Management Officials, (Washington, D.C.: 
September 2008). 

[8] GAO, Military Munitions: DOD Needs to Develop a Comprehensive 
Approach for Cleaning Up Contaminated Sites, [hyperlink, 
http://www.gao.gov/products/GAO-04-147] (Washington, D.C.: Dec. 19, 
2004). 

[9] Operational ranges are areas used to conduct research, develop and 
test military munitions, or train military personnel. 

[10] GAO, DOD Operational Ranges: More Reliable Cleanup Cost Estimates 
and a Proactive Approach to Identifying Contamination Are Needed, 
[hyperlink, http://www.gao.gov/products/GAO-04-601] (Washington D.C.: 
May 2004). 

[11] [hyperlink, http://www.gao.gov/products/GAO-04-601]. 

[12] The John Warner National Defense Authorization Act for Fiscal Year 
2007 required the Secretary of Defense to set four goals for the MMRP: 
(1) to complete preliminary assessments for active sites, other than 
operational ranges, and FUDS by September 30, 2007; (2) to complete 
site assessments at such sites by September 30, 2010; (3) to achieve 
remedy in place or response complete at pre-2005 BRAC sites by 
September 30, 2009; and (4) to achieve remedy in place or response 
complete at active sites, FUDS, and 2005 BRAC sites by a date to be 
established by the Secretary. 

[13] GAO, Environmental Contamination: Many Uncertainties Affect the 
Progress of the Spring Valley Cleanup, [hyperlink, 
http://www.gao.gov/products/GAO-02-556] (Washington D.C.: June 6, 
2002). 

[14] GAO, Environmental Protection: DOD Has Taken Steps to Improve 
Cleanup Coordination at Former Defense Sites but Clearer Guidance Is 
Needed to Ensure Consistency, [hyperlink, 
http://www.gao.gov/products/GAO-03-146], (Washington, D.C.: March 
2003). 

[15] GAO, Environmental Contamination: Corps Needs to Reassess Its 
Determinations That Many Former Defense Sites Do Not Need Cleanup, 
[hyperlink, http://www.gao.gov/products/GAO-02-658], (Washington, D.C.: 
Aug. 23, 2002). 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: