This is the accessible text file for GAO report number GAO-09-552 
entitled 'Army Corps Of Engineers: Recent Changes Have Reduced the Use 
of Continuing Contracts, but Management Processes Need to Be Improved' 
which was released on June 22, 2009. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Congressional Committees: 

United States Government Accountability Office: 
GAO: 

June 2009: 

Army Corps Of Engineers: 

Recent Changes Have Reduced the Use of Continuing Contracts, but 
Management Processes Need to Be Improved: 

GAO-09-552: 

GAO Highlights: 

Highlights of GAO-09-552, a report to congressional committees. 

Why GAO Did This Study: 

The U.S. Army Corps of Engineers (Corps) has had the authority to award 
multiyear contracts—continuing contracts—without having received 
appropriations to cover the full contract amount. In 2006, Congress 
limited the Corps’ use of such contracts by prohibiting obligations 
made in advance of appropriations. In response, the Corps developed a 
new clause that stopped work once funding for a fiscal year was 
expended. GAO was mandated to examine (1) the accuracy of the Corps’ 
fiscal years 2007 and 2008 quarterly reports to Congress about 
continuing contracts that included the new clause, (2) the extent to 
which the Corps’ use of continuing contacts with the new clause may 
have affected its execution of the Civil Works program during this 
time, and (3) the extent to which the Corps followed legal procedures 
in implementing the new clause. To conduct this work, GAO reviewed 
Corps documents, such as its quarterly reports and bid protests, 
federal procurement laws, and interviewed officials. 

What GAO Found: 

The Corps’ quarterly reports to Congress for fiscal years 2007 and 2008 
about continuing contracts with the new clause were inaccurate. 
According to the reports, the Corps awarded 21 new continuing contracts 
during fiscal years 2007 to 2008: 9 for construction and 12 for 
operations and maintenance, ranging in value from $2.1 million to 
$341.5 million, for a total value of about $811 million. However, GAO 
found that some continuing contracts were double-counted, while others 
were missing from the reports. GAO also found other types of errors, 
such as a fully funded contract that was incorrectly included in the 
quarterly report as a continuing contract. These errors raise questions 
about the accuracy of the reports. GAO identified similar inaccuracies 
in the Corps’ quarterly reports during its 2006 review and at that time 
recommended that the Corps develop a tracking system to monitor its use 
of these contracts. While the Corps believes its system of asking 
divisions to provide information on a quarterly basis is sufficient for 
tracking continuing contracts, GAO disagrees. Without a tracking system 
supported by sufficient internal controls to ensure accuracy, errors 
can persist in the information provided to Congress. 

The Corps’ use of the new clause has generally not affected the agency’
s ability to execute its Civil Works program. The Corps decreased its 
use of continuing contracts beginning around the time that the new 
clause was initiated. However, while acknowledging that the transition 
to the new clause created some initial difficulties that have since 
been overcome, Corp officials did not provide any examples of work 
being stopped on a project because funds were not available. 

The Corps did not comply with a legal requirement in implementing the 
new clause, resulting in some districts’ reluctance to use it. Section 
22 of the Office of Federal Procurement Policy Act (OFPP Act) generally 
provides that no procurement regulation that has a significant effect 
beyond the internal operating procedures of the agency or a significant 
cost on contractors or offerors may take effect until 60 days after the 
procurement regulation is published for comment in the Federal 
Register. This requirement may be waived in urgent and compelling 
circumstances; however, the regulation must still be published in the 
Federal Register stating that it is temporary and providing for a 
public comment period of 30 days. Although the Corps has requested 
approval since 2006 from the Department of the Army and the Department 
of Defense, as it is required to, the clause has never been published 
and the Corps has continued to use it. GAO believes that the Corps’ 
argument that its pursuit of publication satisfies the statute is 
unpersuasive. Moreover, GAO spoke with Corps officials from districts 
and divisions who expressed concern about using the clause prior to its 
publication. Specifically, they are concerned that using the clause 
could subject the Corps to legal challenges, such as bid protests, and 
that such potential challenges could delay projects and increase their 
costs. 

What GAO Recommends: 

GAO recommends that the Corps (1) establish adequate internal controls 
to track continuing contracts and (2) suspend its use of the new clause 
until it has been published in the Federal Register. The agency 
disagreed with the latter recommendation because it anticipates 
publication within 60 days. GAO continues to believe the recommendation 
is appropriate because use of the clause would be in violation of the 
OFPP Act. 

View [hyperlink, http://www.gao.gov/products/GAO-09-552] or key 
components. For more information, contact Anu K. Mittal at (202) 512-
3841 or mittala@gao.gov. 

[End of section] 

Contents: 

Letter: 

Background: 

The Corps' Quarterly Reports to Congress Contained Inaccurate 
Information on the Use of Continuing Contracts with the New Clause: 

Overall, the Use of the New Continuing Contracts Clause Has Not 
Affected Execution of the Civil Works Program: 

The Corps Did Not Comply with a Legal Requirement in Implementing the 
New Continuing Contracts Clause: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments: 

Appendix I: Scope and Methodology: 

Appendix II: Summary of Bid Protests Regarding the New Clause for 
Continuing Contracts: 

Appendix III: Comments from the Department of Defense: 

Appendix IV: GAO Contact and Staff Acknowledgments: 

Table: 

Table 1: Description of Projects Subject to Bid Protests because of the 
New Clause: 

Figure: 

Figure 1: Locations of the Corps' Civil Works Divisions and Districts: 

Abbreviations: 

Corps: U.S. Army Corps of Engineers: 

DOD: Department of Defense: 

OFPP Act: Office of Federal Procurement Policy Act: 

[End of section] 

United States Government Accountability Office: 
Washington, DC 20548: 

June 22, 2009: 

The Honorable Byron Dorgan: 
Chairman: 
The Honorable Robert Bennett: 
Ranking Member: 
Subcommittee on Energy and Water Development: 
Committee on Appropriations: 
United States Senate: 

The Honorable Peter J. Visclosky: 
Chairman: 
The Honorable Rodney P. Frelinghuysen: 
Ranking Member: 
Subcommittee on Energy and Water Development: 
Committee on Appropriations: 
House of Representatives: 

Congress provides the U.S. Army Corps of Engineers' (Corps) Civil Works 
program with funding each year to plan, construct, operate, and 
maintain a wide range of water resource projects.[Footnote 1] Congress 
appropriated over $5 billion for such projects in fiscal year 2007 and 
again in fiscal year 2008. The Corps relies on contractors to construct 
many of these projects, which often take more than 1 fiscal year to 
complete. Generally, federal agencies are required to obligate 
appropriations for the full cost of a contract at the time of award 
(i.e., they must fully fund the contract).[Footnote 2] However, from 
1922 to 2005, an Army policy allowed the Corps to enter into, and 
commit the federal government for the full amount of, contracts that 
spanned more than 1 fiscal year (called "continuing contracts"), even 
though the Corps may not have received appropriations to cover the full 
contract amount at the time the contracts were awarded.[Footnote 3] 
More specifically, since 1977, these continuing contracts contained a 
clause that allowed contractors to continue working even when 
appropriated funds were not available. In such cases, the Corps would 
be committed to pay the contractor, with interest, when funding became 
available--in effect, obligating Congress to fully fund a project even 
though sufficient funds had not been appropriated for it. During fiscal 
years 2003 through 2005, the Corps' routine practice was to use 
continuing contracts for most of the contracts it awarded, in part, 
because of the Corps' interpretation of a provision in the Water 
Resources Development Act of 1999 that required the Corps to use 
continuing contracts for certain projects if sufficient funding was not 
available to complete the project. As a result, as we reported in 2006, 
the Corps was frequently awarding continuing contracts for short-term, 
low-dollar-value contracts that could have been fully funded.[Footnote 
4] For example, we found in 2006 that 39 continuing contracts in fiscal 
years 2003 through 2005 had been awarded for work that lasted 6 months 
or less, and 34 continuing contracts had been awarded during this time 
that had a value of less than $1 million. 

In our 2006 report, we also reported that the Corps' quarterly reports 
to Congress on the agency's use of continuing contracts frequently 
contained inaccuracies and that the Corps lacked a system for tracking 
these contracts. As a result, we recommended that the Corps develop a 
tracking system to monitor the use of its continuing contracts. The 
Corps agreed with our recommendation and told us that it would, among 
other things, establish an automated tracking system and implement it 
in fiscal year 2007. Also, at the time of our review, the Energy and 
Water Development Appropriations Act of 2006 restricted the way the 
Corps could use continuing contracts by prohibiting it from awarding or 
modifying existing continuing contracts when doing so would commit an 
amount in excess of the amount provided to a project. To ensure 
compliance with this restriction, the Corps developed a new clause for 
continuing contracts that specifically requires contractors to stop 
work once they have expended the funding set aside for the fiscal year. 

A joint explanatory statement accompanying the fiscal year 2008 
Consolidated Appropriations Act directed us to review the continuing 
contracts that the Corps has awarded using the new clause. In response, 
this report examines (1) the accuracy of the information in the Corps' 
fiscal years 2007 and 2008 quarterly reports to Congress about 
continuing contracts that included the new clause, (2) the extent to 
which the Corps' use of continuing contracts with the new clause may 
have affected its execution of the Civil Works program during this 
time, and (3) the extent to which the Corps followed legal procedures 
in implementing the new clause. 

To determine the accuracy of the information the Corps reported to 
Congress, we reviewed the agency's quarterly reports to Congress for 
fiscal years 2007 and 2008. We compared the information on the number, 
type, and dollar value of continuing contracts in the reports with 
information from a Corps database and the results of interviews with 
officials from a nonprobability sample of 6 of the 38 districts and two 
of the eight divisions. To obtain information about the extent to which 
the Corps' use of continuing contracts that included the new clause may 
have affected its Civil Works program, we interviewed district and 
division officials at these same locations, as well as Corps 
headquarters officials. To assess the Corps' process for implementing 
the new continuing contracts clause, we reviewed federal procurement 
laws related to the Corps' issuance and use of the new continuing 
contract clause. In addition, we interviewed selected district and 
division officials to understand the process that the Corps used to 
develop and implement the new continuing contracts clause and obtain 
their views on the issue. We also contacted the Corps' Office of the 
Chief Counsel to obtain the Corps' legal position on the extent to 
which the Corps has met the requirements of federal procurement law, 
and reviewed its response and supporting documentation. Finally, we 
examined three bid protests, and the Corps' responses to these 
protests, concerning solicitations issued from fiscal years 2006 
through 2008, that alleged, among other things, that the new clause was 
not published in the Federal Register as required by law. Appendix I 
contains a more detailed discussion of our scope and methodology. We 
conducted this performance audit from September 2008 to June 2009 in 
accordance with generally accepted government auditing standards. Those 
standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe that 
the evidence obtained provides a reasonable basis for our findings and 
conclusions based on our audit objectives. 

Background: 

Under its Civil Works program, the Department of Defense's (DOD) U.S. 
Army Corps of Engineers plans, constructs, operates, and maintains a 
wide range of water resources projects. In addition to its headquarters 
in Washington, D.C., the Corps has eight regional divisions and 38 
districts that carry out its domestic civil works responsibilities (see 
figure 1). 

Figure 1: Locations of the Corps' Civil Works Divisions and Districts: 

[Refer to PDF for image: map of the United States] 

The map contains the boundary lines of Division, Districts, and states, 
as well as the location of Division and District headquarters. 

District: North Atlantic; 
Division headquarters: New York City; 
District headquarters: New England; Baltimore, MD; Philadelphia PA, 
Norfolk, VA. 

District: South Atlantic; 
Division headquarters: Atlanta; 
District headquarters: Wilmington, NC; Charleston, SC; Savannah GA; 
Jacksonville; Mobile, AL. 

District: Great Lakes and Ohio River; 
Division headquarters: Cincinnati, OH; 
District headquarters: Pittsburgh, PA; Huntington, WV; Nashville, YN; 
Louisville, KY; Detroit, MI; Chicago; IL. 

District: Mississippi Valley; 
Division headquarters: Vicksburg, MS; 
District headquarters: Vicksburg, MS; New Orleans, LA; Memphis, TN; St. 
Louis, MO; Rock Island, IL; St. Paul, MN. 

District: Southwestern; 
Division headquarters: Dallas, TX; 
District headquarters: Fort Worth, TX; Galveston, TX; Tulsa, OK; Little 
Rock, AR. 

District: Northwestern; 
Division headquarters: Portland, OR; 
District headquarters: Kansas City, MO; Omaha, NE; Walla Walla, WA; 
Seattle, WA. 

District: South Pacific; 
Division headquarters: San Francisco, CA; 
District headquarters: San Francisco, CA; Albuquerque, NM; Sacramento, 
CA; Los Angeles, CA. 

District: Pacific Ocean; 
Division headquarters: Honolulu, HA; 
District headquarters: Honolulu, HA; Alaska. 

Source: GAO representation of U.S. Army Corps of Engineers data. 

[End of figure] 

Corps headquarters primarily develops policies and plans the future 
direction of the organization; divisions coordinate the districts' 
projects; and the districts plan and implement the projects, which are 
approved by the divisions and headquarters. Water resource projects are 
generally very large undertakings that often take more than a single 
fiscal year to complete. Moreover, the timing of these projects is 
often dictated by weather conditions or environmental concerns. For 
example, many dredging projects take place during the winter months 
because environmental concerns limit dredging operations during the 
spring and summer (March through September) to protect various species, 
such as threatened and endangered turtles. 

Congress appropriates about $5 billion annually to the Corps to carry 
out its Civil Works program. Federal agencies generally receive annual 
appropriations (also called fiscal year or 1-year appropriations) that 
are made for a specified fiscal year. These appropriations are 
available for obligation--legal commitment by the government for the 
payment of goods and services ordered or received--only for the bona 
fide needs of the fiscal year for which they were appropriated. If an 
agency fails to obligate its annual funds by the end of the fiscal year 
for which they were appropriated, the funds cease to be available to 
the agency for new obligations. They are referred to as "expired" and, 
after 5 years, are returned to the U.S. Treasury. In contrast, the 
Corps receives "no-year" appropriations through the Energy and Water 
Development Appropriations Act--that is, there are no time limits on 
when the funds may be obligated or expended, and the funds remain 
available for their original purposes until expended. The majority of 
the Corps' Civil Works appropriations are generally directed to two 
types of activities: (1) operations and maintenance and (2) 
construction.[Footnote 5] Operations and maintenance activities include 
the preservation, operation, and maintenance of existing rivers and 
harbors. Construction activities include construction and major 
rehabilitation projects related to navigation, flood control, water 
supply, hydroelectric power, and environmental restoration. 

The Corps' Quarterly Reports to Congress Contained Inaccurate 
Information on the Use of Continuing Contracts with the New Clause: 

The Corps' fiscal years 2007 and 2008 quarterly reports to Congress on 
continuing contracts awarded with the new clause contained inaccurate 
information. According to these reports, the Corps awarded 21 new 
continuing contracts during this time: 9 for construction and 12 for 
operations and maintenance, ranging in value from $2.1 million to 
$341.5 million, for a total of about $811 million. However, we found 
that some continuing contracts were double-counted, while others were 
omitted from the reports. For example, two contracts were first 
reported to Congress as new continuing contracts at the end of fiscal 
year 2007. The Corps then reported the same two contracts in the first 
quarter of fiscal year 2008, marking them as "not reported" in the 
prior fiscal year. In addition, we identified two continuing contracts 
totaling approximately $48 million that should have been included as 
new awards in the Corps' quarterly reports but were omitted. Corps 
officials confirmed that these were indeed new continuing contracts 
that should have been included in the reports. Both types of errors 
impacted the total number and value of the continuing contracts with 
the new clause that were reported to Congress as having been awarded 
during this 2-year period. We also identified other types of errors 
that did not affect the overall totals of new contracts or their value 
but, nevertheless, raise questions about the accuracy of the 
information that the Corps is providing to Congress. For example, when 
we asked Corps officials in one district to verify information about 
the continuing contracts they had awarded in fiscal years 2007 and 
2008, they provided us with documentation that showed that one contract 
that had been incorrectly included in the Corps' quarterly report to 
Congress as a continuing contract was actually a fully funded contract. 
In addition, four new continuing contracts were not initially reported 
as new in the quarterly reports covering their award periods; instead, 
three were reported in a later quarterly report and one was reported 
earlier. Similarly, we found that two fully funded contracts were 
incorrectly included in the 2007 quarterly reports as existing 
continuing contracts. 

The Corps' failure to accurately report to Congress the number of 
continuing contracts it awards is a problem that we previously 
identified in 2006, and at that time, we recommended that the Corps 
develop an appropriate tracking system for these contracts. Although 
the Corps concurred at the time, Corps officials told us that the 
agency had not developed a tracking system as we had recommended 
because it believed its system of asking divisions to provide 
information on a quarterly basis was sufficient for tracking the use of 
continuing contracts. These officials also told us that the agency had 
issued a 2007 guidance document that provided instructions to the 
districts for making submissions for the quarterly reports to Congress. 
In light of the inaccuracies we identified in the quarterly reports to 
Congress, we do not believe that the Corps quarterly data calls 
constitute a systematic tracking system for continuing contracts that 
we recommended in 2006; therefore, we believe that our 2006 
recommendation has not yet been implemented by the agency. According to 
our Standards for Internal Control in the Federal Government, managers 
are to "complete, within established time frames, all actions that 
correct or otherwise resolve the matters brought to management's 
attention."[Footnote 6] We believe that the Corps' inaction on our 
recommendation has led to a lack of internal controls that has 
contributed to persistent errors on the part of the agency in reporting 
to Congress on its use of continuing contracts. 

Overall, the Use of the New Continuing Contracts Clause Has Not 
Affected Execution of the Civil Works Program: 

As a result of the limits that Congress has placed on the Corps' use of 
continuing contracts in recent years, the Corps has issued guidance and 
made several modifications to its policies that govern the Civil Works 
program. While these changes, taken together, have resulted in a 
decrease in the number of continuing contracts that the Corps has 
awarded, they have not significantly affected the agency's ability to 
execute its Civil Works program. Specifically, the committee report 
accompanying the Corps' fiscal year 2005 appropriations expressed 
concern about the Corps' use of continuing contracts and noted that the 
purpose of continuing contracts was to enable the Corps, in awarding 
contracts for the components of large construction projects, to take 
advantage of economies of scale and efficiently manage these large 
components over several years. In enacting the Energy and Water 
Development Appropriations Act of 2006, Congress provided specific 
direction to the Corps regarding its use of continuing contracts. The 
law states, among other things, that with certain exceptions, none of 
the funds made available in the act may be used to award any continuing 
contract, or make modifications to any existing continuing contract, 
that commits an amount for a project in excess of the amount provided 
for the project. 

To help ensure that it met these new congressional requirements, the 
Corps issued guidance in fiscal year 2006 that, among other things: 
[Footnote 7] 

* directed that districts use fully funded contracts as their primary 
contracting option and that continuing contracts be used only as the 
contracting option of last resort; 

* summarized new information that the districts are required to provide 
in their requests to use continuing contracts, including an explanation 
of why using a continuing contract is in the best interest of the 
government; and: 

* directed districts to take measures to ensure that contractor costs 
do not exceed the amount provided for projects. 

Also, in response to these new congressional requirements, that same 
year, the Corps developed a new clause for continuing contracts that 
specifically required contractors to stop work once they had expended 
the funding set aside for the fiscal year. In addition, the Corps 
established certain criteria for the use of continuing contracts for 
operations and maintenance projects. The Assistant Secretary of the 
Army for Civil Works preapproved certain requests for operations and 
maintenance continuing contracts if the contracts met five conditions. 
In response, the Corps issued guidance to the divisions reiterating 
these conditions. These conditions included that (1) the contract was 
financed from the Corps' operations and maintenance account and (2) the 
work could not be broken down into smaller increments that could be 
fully funded within the current fiscal year.[Footnote 8] The following 
fiscal year, the Corps also established certain criteria for continuing 
contracts for construction projects. Specifically, using continuing 
contracts for construction activities was to be considered only if the 
contract was for more than $10 million and the work could not be 
completed in a single fiscal year. The Corps also required that 
requests for using continuing contracts, other than continuing 
contracts that had been preapproved, be approved at the Assistant 
Secretary level. 

While the Corps quarterly reports to Congress cannot be fully relied on 
for accurate information on the number and value of continuing 
contracts awarded with the new clause, they do provide a reasonable 
sense of the overall direction of the use of such contracts. In 2006, 
we reported that the Corps, on average, awarded about 500 continuing 
contracts per year for fiscal years 2003 through 2005. The 2007 and 
2008 quarterly reports to Congress indicate that the number of 
continuing contracts with the new clause has reduced considerably and 
may average only about 10 per year for fiscal years 2007 and 2008. 

The decreased use of continuing contracts, and the use of the new 
clause, does not appear to have significantly affected the Corps' Civil 
Works program. While the Corps has not established metrics to evaluate 
the impacts of this change, district officials we spoke with told us 
that they believe that the new continuing contracts clause has had 
little, if any, impact on their ability to accomplish the Civil Works 
mission of the agency. For example, several Corps district officials we 
interviewed said that while there were some temporary difficulties in 
executing their projects when the new clause was first implemented, 
their ability to conduct their work has not been adversely affected. 
Specifically, these officials told us that the combined effect of the 
requirement to fully fund contracts and the lack of sufficient funds in 
2007, when the new clause was first implemented, led them to award 
fewer contracts at that time, and some project starts were delayed 
until the following fiscal year. These officials did not provide any 
examples, however, of where work on a project was stopped because funds 
were not available. Since that time, however, they have adjusted to the 
changes and have resumed their normal level of contract activity. 

Corps officials also told us that, in general, the recent changes, 
including the new clause, have had some positive effects on contract 
management, including the following: 

* Contracts that are fully funded, as well as continuing contracts that 
use the new clause, provide officials more certainty in managing their 
funds. For example, the Corps no longer has to search for funds each 
year to meet the obligations created when contractors would work after 
the amount appropriated for a fiscal year was exhausted. 

* Contract management has become easier for Corps officials, whether 
they fully fund contracts or use continuing contracts with the new 
clause, because fewer contract modifications are likely, and the 
contractor is restricted to the work specified in the contract. 

Notwithstanding these positive effects, some district officials also 
told us that having the flexibility to use continuing contracts as they 
were previously used, as opposed to fully funding contracts, would be 
useful for some large, longer-term projects, such as lock and dam 
projects, which require millions of dollars and multiple fiscal years 
to complete. According to these officials, if such projects are fully 
funded, large amounts of unexpended appropriations would be carried 
over for several fiscal years. For example, a 5-year, $200 million 
contract that required only $75 million in its first year would require 
carrying over the remaining $125 million into subsequent fiscal years 
until the funds were expended. Since the $125 million would already 
have been obligated to the contract at award, it would not be available 
to be used on other contracts. If such projects were funded using 
continuing contracts as they were previously used, the Corps would 
allocate the entire contract amount at the time of award, but would 
obligate only the amount of funds that would be needed to cover the 
first year of the contract. The remaining funds not needed during the 
first year would be available to be used on other contracts. As a 
result, these officials told us that the restrictions placed on the use 
of continuing contracts in recent years may have made execution of some 
projects somewhat less efficient and more costly, although they could 
not provide us any specific examples of this having occurred. Corps 
headquarters officials generally disagreed with this position. 
According to these officials, over time, the Corps could complete the 
same number of projects even if they were fully funded, as opposed to 
using continuing contracts as they were previously used. 

Corp headquarters officials did tell us, however, that there is some 
value in having the ability to use continuing contracts as they were 
previously used for a few projects. Specifically, as previously used, 
continuing contracts obligated the Corps for the full amount of the 
contract at the date of the award. According to these officials, in 
practical terms, this means that the contractor does not have to wait 
for the Corps to provide the money in order to make large investments, 
such as ordering prefabricated materials and buying raw materials like 
steel. This flexibility on timing realized under the previous use of 
continuing contracts therefore provided contractors the ability to reap 
the benefits of economies of scale when purchasing materials in bulk. 

The Corps Did Not Comply with a Legal Requirement in Implementing the 
New Continuing Contracts Clause: 

In implementing the new continuing contracts clause, the Corps did not 
comply with a legal requirement and, as a result, some districts are 
reluctant to use it when awarding contracts. Specifically, the Corps 
has been using the new continuing contracts clause prior to its 
publication in the Federal Register for public comment, in violation of 
section 22 of the Office of Federal Procurement Policy Act (OFPP Act), 
41 U.S.C.§ 418b.[Footnote 9] This section of the act generally provides 
that no procurement regulation relating to the expenditure of 
appropriated funds that has a significant effect beyond the internal 
operating procedures of the agency or a significant cost or 
administrative impact on contractors or offerors may take effect until 
60 days after the procurement regulation is published for public 
comment in the Federal Register. This requirement for advance comment 
may be waived if urgent and compelling circumstances make compliance 
impracticable; in such cases, a procurement regulation shall be 
effective on a temporary basis if a notice of the regulation is 
published in the Federal Register stating that it is temporary and 
providing for a public comment period of 30 days. After considering the 
comments received, the agency may issue the final procurement 
regulation. Courts have held that the failure to comply with section 22 
renders the proposed procurement regulation without effect.[Footnote 
10] 

In spring 2006, the Corps waived the requirement to obtain advance 
comments on the new clause based on urgent and compelling circumstances 
and sent a request for publication of the clause to the Department of 
the Army. The Corps is required to obtain approval from the Department 
of the Army and DOD prior to publication of a change that has a 
significant effect beyond the internal operating procedures of the 
agency, such as the new continuing contracts clause.[Footnote 11] Over 
the intervening months and years, the Corps has submitted multiple 
iterations of the request for publication to the Army. These requests 
have moved among the Army, DOD, and the Office of Management and 
Budget, but the Corps has not yet received confirmation of approval 
from DOD, and the clause has never been published in the Federal 
Register. The Corps' use of the new clause for more than 3 years prior 
to its having been published in the Federal Register for public comment 
does not meet the requirements of section 22 of the OFPP Act. The 
Corps' argument that its use of the new clause complies with the 
statute because it has been pursuing publication through the Army and 
DOD as required is, in our view, unpersuasive. The relevant provision 
states that new procurement regulations may only take effect if a 
Federal Register notice "is published," not while publication is being 
pursued. The Corps' interpretation also ignores the requirement for a 
minimum public comment period of 30 days after the notice is published--
to date, no public comment period whatsoever has been provided. 

Corps officials from the districts and divisions with whom we spoke 
expressed concern about the Corps' use of the new clause without its 
having been published in the Federal Register. According to these 
officials, because this legal requirement has not been met, they are 
concerned that using the new clause could subject the Corps to legal 
challenges such as bid protests.[Footnote 12] Such potential legal 
challenges could prolong projects and increase their costs. 

We identified three solicitations for continuing contracts with the new 
clause issued from fiscal years 2006 through 2008 that did result in 
bid protests. These protests alleged, among other things, that the 
Corps' use of the new continuing contracts clause prior to providing an 
opportunity for public notice and comment violated the OFPP Act. These 
protests were withdrawn when the Corps reissued the solicitations 
without the new clause, using instead such options as fully funding the 
contracts and restructuring the work required by the contracts. (See 
app. II for details about the three bid protests.) Some district 
officials where the solicitations that were protested originated said 
that they are concerned that such legal challenges could resurface in 
the future--jeopardizing other contracts that use the new clause and 
delaying the award of these contracts. Moreover, officials in one 
district that has not used the new continuing contracts clause since it 
became available told us that the fact that the new clause has never 
been published for comment constituted their major reason for not using 
it. 

Conclusions: 

Although Congress and GAO have raised a number of concerns in recent 
years about the Corps' use of continuing contracts, of particular note 
has been the agency's lack of accurate information on the number and 
value of contracts that it has awarded. In 2006, we specifically 
recommended that the Corps establish a system to track its use of 
continuing contracts, and while the agency agreed with this 
recommendation, it has failed to implement it. As a result, the process 
and guidance it relies on to provide quarterly information to Congress 
are ineffective and continue to generate information that is neither 
complete nor accurate. 

Moreover, the Corps developed and implemented its new continuing 
contracts clause over 3 years ago, but its use of the clause does not 
comply with the publication requirements of the OFPP Act. The Corps' 
position that its use of the new continuing contracts clause while 
"pursuing publication" of the clause in the Federal Register satisfies 
the requirements of the act is unpersuasive. While we understand that 
the Corps has been seeking approval to publish the clause since 2006, 
and that it is unable to publish the clause without approval from the 
Army and DOD, the statute's publication requirement and its waiver 
provision clearly permit temporary use of such a clause only if it is 
actually published in the Federal Register for public comment. The 
Corps' use of the clause prior to publication does not comply with the 
statute's requirements and may leave the Corps susceptible to further 
legal challenges. 

Recommendations for Executive Action: 

To ensure that the Corps provides accurate and reliable reports to 
Congress on its use of continuing contracts and complies with federal 
procurement law, we recommend that the Secretary of Defense direct the 
Chief of Engineers and Commanding General of the U.S. Army Corps of 
Engineers to take the following three actions: 

* Establish adequate internal controls to ensure accurate and complete 
information is collected and reported to Congress on the use of 
continuing contracts. 

* Suspend the Corps' use of the new continuing contracts clause until 
it has been published in the Federal Register, in accordance with 41 
U.S.C. § 418b. 

* Provide regular updates to Congress on the progress of these actions. 

Agency Comments: 

We provided a draft of this report to the Department of Defense for 
official review and comment. The department concurred with two of our 
recommendations and did not concur with one. Specifically, the 
department concurred with our recommendations that the Corps establish 
adequate internal controls to ensure accurate and complete information 
is collected and reported to Congress on the use of continuing 
contracts; and provide regular updates to Congress. The department did 
not agree, however, with our recommendation that the Corps suspend use 
of the new continuing contracts clause until it has been published in 
the Federal Register in accordance with § 41 U.S.C. 418b. The 
department did not disagree with our conclusion that its use of the new 
clause prior to publication violates the law, and acknowledged that the 
unforeseen delay in publishing the clause is undesirable. The 
department also stated that it intends to publish the new clause in the 
Federal Register as expeditiously as possible and anticipates approval 
of the clause for publication within 60 days. While we agree with the 
department's efforts to expedite the publication of the new clause in 
the Federal Register, we continue to believe that suspending the use of 
the clause in the interim would be the appropriate course of action. 
This is because until the clause is published in the Federal Register 
for a minimum public comment period of 30 days, the department's use of 
the clause will violate section 22 of the OFPP Act. 

We are sending copies of this report to the appropriate congressional 
committees, the Secretary of Defense, and the Chief of Engineers and 
Commanding General of the U.S. Army Corps of Engineers. In addition, 
this report will be available at no charge on the GAO Web site at 
[hyperlink, http://www.gao.gov]. 

If you or your staffs have any questions regarding this report, please 
contact me at (202) 512-3841 or mittala@gao.gov. Contact points for our 
Offices of Congressional Relations and Public Affairs may be found on 
the last page of this report. Key contributors to this report are 
listed in appendix IV. 

Signed by: 

Anu K. Mittal: 
Director, Natural Resources and Environment: 

[End of section] 

Appendix I: Scope and Methodology: 

A joint explanatory statement accompanying the fiscal year 2008 
Consolidated Appropriations Act directed us to review the continuing 
contracts that the U.S. Army Corps of Engineers (Corps) has awarded 
using a new clause. More specifically, from 1922 to 2005, the Corps had 
the authority to award multiyear contracts (called continuing 
contracts) without having received appropriations to cover the full 
contract amount. These continuing contracts allowed contractors to 
continue working on a project after funds provided for that project had 
been expended. In 2006, as part of its changes associated with 
continuing contracts, the Corps created two new clauses--a "special" 
clause and an "incrementally funded" clause that require contractors to 
stop work on a project once they have expended the funding set aside 
for the fiscal year. According to Corps counsel, however, the agency 
considers only contracts with the special clause to be continuing 
contracts because the incrementally funded clause does not involve a 
future funding obligation. For the purpose of this review, we have 
referred to the special clause as the "new clause." 

To determine the accuracy of the information the Corps reported to 
Congress in fiscal years 2007 and 2008, we compared information from 
the Corps' quarterly reports on the number, type, and dollar value of 
continuing contracts that used the new clause with information obtained 
from a Corps database and results of interviews with Corps officials in 
selected divisions and districts.[Footnote 13] We identified the 
continuing contracts that the Corps listed as new awards on the basis 
of the information the Corps presented in its summary letters to 
Congress, as well as the information contained in the quarterly reports 
themselves.[Footnote 14] We then identified continuing contracts with 
the new clause that were awarded during the 2-year time frame but were 
missing from the Corps' quarterly reports by querying the Corps' 
Primavera database.[Footnote 15] We did not assess the reliability of 
the Primavera database, but we verified information from that database 
independently using both testimonial and documentary evidence provided 
by the Corps. In addition, we interviewed Corps officials in selected 
divisions and districts to corroborate the information on continuing 
contracts that we obtained from the quarterly reports and Primavera 
database. We selected a nonprobabilty sample of two of the eight 
divisions and 6 of the 38 districts that carry out the Corps' domestic 
civil works responsibilities. More specifically, we selected the one 
division that had used continuing contracts with the new clause the 
most and the other division that had used them the least. In addition, 
of the six districts, two had used continuing contracts with the new 
clause the most, two had used them the least, and the remaining two had 
been involved with bid protests associated with the new clause. We also 
ensured that those districts and divisions varied geographically and in 
program size. Specifically, we selected the Mississippi Valley and 
South Pacific Divisions, as well as the Los Angeles (South Pacific 
Division), Nashville (Great Lakes and Ohio River Division), 
Philadelphia and New York[Footnote 16] (North Atlantic Division), 
Vicksburg (Mississippi Valley Division), and Walla Walla (Northwestern 
Division) districts. We obtained pertinent supporting documentation 
from the divisions and districts to support the testimonial information 
obtained during the interviews. 

To obtain information about the extent to which the Corps' use of 
continuing contracts with the new clause may have affected its 
execution of the Civil Works program and the extent of the Corps' use 
of continuing contracts with the new clause, we interviewed Corps 
division and district officials at the locations identified above, as 
well as at Corps headquarters. In addition, we interviewed the Corps 
manager at headquarters responsible for the quarterly reports to obtain 
basic information for assessing the reliability of those data. Although 
there were inaccuracies, we found that the data were sufficiently 
reliable for the purposes of our report. During the interviews, we 
discussed, among other things, Corps guidance on continuing contracts, 
the process used to obtain approval to use continuing contracts, any 
impacts and challenges related to the Corps' use of continuing 
contracts, and monitoring the use of continuing contracts. 

To assess the Corps' process for implementing the new continuing 
contracts clause, we reviewed relevant federal procurement laws related 
to the Corps' issuance and use of the new continuing contract clause. 
[Footnote 17] In addition, we interviewed selected district and 
division officials to obtain their views on the issue. We also 
interviewed selected district and division officials to understand the 
process that the Corps used to develop and implement the new continuing 
contracts clause and obtain their views on the issue. We also contacted 
the Corps' Office of the Chief Counsel to obtain the Corps' legal 
position on the extent to which the Corps has met the requirements of 
federal procurement law, and reviewed its response and supporting 
documentation. Finally, we examined three bid protests, and the Corps' 
responses to these protests, concerning solicitations issued from 
fiscal years 2006 through 2008, that alleged, among other things, that 
the new clause was not published in the Federal Register as required by 
law. 

We conducted this performance audit from September 2008 to June 2009 in 
accordance with generally accepted government auditing standards. Those 
standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe that 
the evidence obtained provides a reasonable basis for our findings and 
conclusions based on our audit objectives. 

[End of section] 

Appendix II: Summary of Bid Protests Regarding the New Clause for 
Continuing Contracts: 

From fiscal years 2006 to 2008, the U.S. Army Corps of Engineers 
(Corps) received bid protests for three of its solicitations for 
continuing contracts with the new clause. A bid protest may be filed 
when a bidder or other interested party has reason to believe that a 
contract has been or is about to be awarded improperly or illegally, or 
that the bidder or interested party has been unfairly denied a contract 
or an opportunity to compete for a contract. One firm protested three 
solicitations that would have awarded contracts with the new clause. In 
each case, the firm withdrew its protest after the Corps restructured 
the statement of work, issued an amendment to remove the new clause 
from the solicitation, and proceeded to award the contract as a 
contract with a different funding mechanism, such as a fully funded 
contract, rather than as a continuing contract. 

Specifically, the firm filed initial protests with three districts that 
issued solicitations with the new clause--San Francisco, New York, and 
Philadelphia.[Footnote 18] The firm alleged several bases for its 
protests; however, the overarching issue in the protests, which 
generally used the same language, was the Corps' inclusion of the new 
clause in the solicitations. The firm alleged the following: 

* Inclusion of the new clause rendered the specifications defective 
because it made the project schedule and duration so vague and 
indefinite that potential bidders could not compete intelligently and 
on an equal basis. The firm argued that bidders would make different 
assumptions involving different contingencies and might not be bidding 
to perform the same scope of work and that, as a result, the Corps 
would be precluded from determining whether the lowest bid received 
represented the lowest cost to the government of performing the work 
required. 

* The Corps' attempt to use the new clause violated 41 U.S.C. § 418b 
and Federal Acquisition Regulation Subparts 1.3 and 1.5, which require 
the clause to be published in the Federal Register for public comment. 

When the Corps receives a bid protest, the respective division office 
responds on behalf of the district whose solicitation is being 
protested. Of the three districts that received bid protests, only the 
division for the San Francisco District formally denied the protest. 
The May 22, 2006, decision by the Assistant Chief Counsel/Division 
Counsel for the South Pacific Division, among other things: 

* denied the allegation that the clause rendered the specifications 
defective and stated that any assumptions a contractor may choose to 
make with regard to schedule, funding streams, delays, and so forth 
would necessarily be reflected in the bid prices. As a result, the 
Corps argued, as long as the bid was not unbalanced and was otherwise 
the lowest price, it would also be the lowest cost to the government. 

* asserted that the Corps used the new clause prior to publishing it in 
the Federal Register for public comment due to "urgent and compelling 
circumstances," and explained that the Corps was in the process of 
submitting the clause to the Federal Register for public comment 
through its internal procedures. 

After the Corps' South Pacific Division denied the agency-level 
protest, the protester filed a protest with GAO on May 31, 2006. 
Subsequently, the Corps' San Francisco District decided to remove the 
new clause from the solicitation, and the protester withdrew its 
protest on June 15, 2006. 

Similarly, the protests filed with the New York and Philadelphia 
Districts resulted in the districts' removing the new clause from the 
solicitations. The protester subsequently withdrew its protest in both 
cases. In all three protests, the Corps districts then used a different 
funding mechanism to complete the work. Table 1 describes the projects 
and shows relevant dates and estimated amounts. 

Table 1: Description of Projects Subject to Bid Protests because of the 
New Clause: 

Project name: Oakland Harbor; (San Francisco District); 
Type of work: Operations and maintenance; 
Protest date: March 27, 2006; 
Protest withdrawn date: June 15, 2006; 
New contract mechanism: Fully funded contract. 

Project name: New York and New Jersey Harbor; (New York District); 
Type of work: Operations and maintenance; 
Protest date: April 14, 2006; 
Protest withdrawn date: May 17, 2006; 
New contract mechanism: Fully funded contract. 

Project name: Inland Waterway Delaware River to Chesapeake Bay; 
(Philadelphia District); 
Type of work: Operations and maintenance; 
Protest date: August 20, 2007; 
Protest withdrawn date: August 30, 2007; 
New contract mechanism: Incrementally funded contract. 

Source: GAO analysis of Corps bid protests. 

[End of table] 

[End of section] 

Appendix III: Comments from the Department of Defense: 

Department Of The Army: 
Office Of The Assistant Secretary: 
Civil Works: 
108 Army Pentagon: 
Washington, DC 20310-0108: 

June 12, 2009: 

Ms. Anu Mittal: 
Director, Natural Resources and Environment: 
U.S. Government Accountability Office: 
441 G Street, N.W. 
Washington, DC 20548: 

Dear Ms. Mittal: 

This is the Department of Defense (DoD) response to the GAO Draft 
Report, GAO-09552. "Army Corps Of Engineers: Recent Changes Have 
Reduced the Use of Continuing Contracts, but Management Processes Need 
to be Improved," dated May 15, 2009 (GAO Code 360999) 

Thank you for the opportunity to review and comment on the draft 
report. Responses to the GAO recommendations are enclosed. 

We concur with recommendations one and three. We non-concur with 
recommendation two whereby GAO recommends suspending the use of the new 
continuing contracts clause until it has been published in the Federal 
Register in accordance with 41 U.S.C. 418b. We do however agree that 
the interim continuing contracts clause should be published in the 
Federal Register. The Corps has been working with the Army and DoD 
since 2006 in an effort to publish the clause. We anticipate DOD's 
approval within 60 days. 

Very truly yours, 

Signed by: 

Terrence C. Salt: 
Acting Assistant Secretary of the Army (Civil Works): 

Enclosure: 

[End of letter] 

GAO Draft Report - Dated May 15, 2009: 
GAO Code 360999/GAO-09-552: 

"Army Corps Of Engineers: Recent Changes Have Reduced The Use Of 
Continuing Contracts, But Management Processes Need To Be Improved" 

Department Of Defense Comments To The Recommendations: 

Recommendation 1: The GAO recommends that the Secretary of Defense 
direct the Commanding General and the Chief of Engineers of the U.S. 
Army Corps of Engineers to establish adequate internal controls to 
ensure accurate and complete information is collected and reported to 
Congress on the use of continuing contracts. 

DOD Response: Concur. 

Recommendation 2: The GAO recommends that the Secretary of Defense 
direct the Commanding General and the Chief of Engineers of the U S. 
Army Corps of Engineers to suspend the Corps' use of the new continuing 
contracts clause until it has been published in the Federal Register in 
accordance with 41 U.S.C. 418b. (p. 16/GAO Draft Report) 

DOD Response: Non-concur. Notwithstanding our non-concurrence. DOD 
acknowledges the unforeseen delay in publishing the interim continuing 
contract clause is undesirable. We intend to publish the interim clause 
in the Federal Register as expeditiously as possible. We anticipate 
approval of the clause for publication within 60 days. 

Recommendation 3: The GAO recommends that the Secretary of Defense 
direct the Commanding General and the Chief of Engineers of the U.S. 
Army Corps of Engineers to provide regular updates to Congress on the 
progress of these actions. 

DOD Response: Concur. 

[End of section] 

Appendix IV: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Anu K. Mittal, (202) 512-3841 or mittala@gao.gov: 

Staff Acknowledgments: 

In addition to the individual named above, Vondalee R. Hunt (Assistant 
Director), Tania L. Calhoun, Nancy L. Crothers, Diana C. Goody, Daniel 
J. Semick, and Delia P. Zee, made key contributions to this report. 
Also contributing to this report were Joel I. Grossman, Carol M. Henn, 
and William T. Woods. 

[End of section] 

Footnotes: 

[1] The Corps also has a military program that provides, among other 
things, engineering and construction services to other U.S. government 
agencies and foreign governments. This report discusses only the Civil 
Works program. 

[2] The Antideficiency Act prohibits agencies from entering into 
contracts that exceed currently available appropriations or that 
obligate appropriations not yet made. 

[3] The River and Harbor Act of 1922 gave the Corps the permanent 
authority it had sought to use continuing contracts to complete 
projects even when the agency did not have appropriations to cover the 
full contract amounts. 

[4] GAO, Army Corps of Engineers: Improved Monitoring and Clear 
Guidance Would Contribute to More Effective Use of Continuing 
Contracts, [hyperlink, http://www.gao.gov/products/GAO-06-966] 
(Washington, D.C.: Sept. 8, 2006). 

[5] The Corps typically receives contributed funds, particularly for 
construction projects, from nonfederal sponsors (state, tribal, county, 
and local agencies) that provide, among other things, financial 
contributions to complete the work. 

[6] The Federal Managers' Financial Integrity Act of 1982 required that 
GAO issue standards for "internal control" in government. The result 
was GAO, Standards for Internal Control in the Federal Government, 
[hyperlink, http://www.gao.gov/products/GAO/AIMD-00-21.3.1] 
(Washington, D.C.: November 1999). The term internal control is 
synonymous with the term "management control" in OMB Circular A-123, 
which covers all aspects of an agency's operations-- programmatic, 
financial, and compliance. 

[7] The Corps issued this guidance in its Engineering Circular 11-2- 
189. 

[8] The other three conditions follow: (1) the contract met all 
requirements established by the Corps, including that it be the most 
cost-effective acquisition mechanism; (2) no funds could be 
reprogrammed to or from the project in fiscal year 2006; and (3) the 
lowest amount specified in either the President's budget, the House 
report or the Senate report for fiscal year 2007, or the conference 
report for fiscal year 2007, if available, included funding for the 
remaining portion of the contract, along with funding for any other 
operation and maintenance of the affected project. 

[9] The act established the Office of Federal Procurement Policy in the 
Office of Management and Budget in 1974 to play a central role in 
shaping the policies and practices federal agencies use to acquire the 
goods and services they need to carry out their responsibilities. Among 
other things, the act provides overall direction for governmentwide 
procurement policies, regulations, and procedures to promote economy, 
efficiency, and effectiveness in acquisition processes. 

[10] Munitions Carriers Conference, Inc. v. United States, 932 F. Supp. 
334, 341 (D.D.C. 1996), rev'd on other grounds, 147 Fed. Cl. 200 (2003) 
("Because [the agency] did not comply with § 418b, either actually or 
constructively, the [procurement regulation] is without effect."). 

[11] See Defense Federal Acquisition Regulation Supplement (DFARS) 
§ 201.304; Army Federal Acquisition Regulation Supplement (AFARS) 
§ 5101.301. 

[12] Bidders and offerors seeking federal government contracts who 
believe that contracts have been, or are about to be, awarded in 
violation of the laws and regulations that govern contracting with the 
federal government may file bid protests with the contracting agency, 
GAO, or the U.S. Court of Federal Claims. 

[13] The quarterly reports list new continuing contracts awarded during 
fiscal years 2007 and 2008, as well as contracts already under way 
(that is, continuing contracts awarded prior to fiscal year 2007). 

[14] In fiscal year 2007, the Corps bolded newly awarded continuing 
contracts in the quarterly reports. In fiscal year 2008, the Corps 
changed its method for identifying new continuing contracts and added a 
"New" column in the quarterly report. The Corps placed an "X" in the 
"New" column to indicate that a contract was newly awarded in that 
quarter. 

[15] Primavera is used by project managers to develop and manage 
project schedules and resource requirements. Primavera has an optional 
field to track continuing contracts that was added to the database in 
early 2007. 

[16] The Philadelphia and New York districts dealt with bid protests 
related to their use of the new clause. 

[17] The Corps created two new clauses--a special clause and an 
incrementally funded clause--but according to Corps counsel, the agency 
only considers contracts with the special clause to be continuing 
contracts. Corps counsel stated that the incrementally funded clause 
does not include a future funding obligation and is, therefore, not 
considered a continuing contract. For the purposes of this review, we 
are referring to the special clause when we mention the "new clause." 

[18] A protest can be filed with the contracting agency, GAO, and the 
U.S. Court of Federal Claims. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: