This is the accessible text file for GAO report number GAO-08-1141T 
entitled 'Secure Border Initiative: Observations on Deployment 
Challenges' which was released on September 10, 2008.

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Testimony: 

Before the Committee on Homeland Security, House of Representatives: 

United States Government Accountability Office: 
GAO: 

For Release on Delivery: 
Expected at 10:00 a.m. EDT: 
Wednesday, September 10, 2008: 

Secure Border Initiative: 

Observations on Deployment Challenges: 

Statement of Richard M. Stana, Director: Homeland Security and Justice 
Issues: 

GAO-08-1141T: 

GAO Highlights: 

Highlights of GAO-08-1141T, a testimony before the Committee on 
Homeland Security, House of Representatives. 

Why GAO Did This Study: 

In November 2005, the Department of Homeland Security (DHS) established 
the Secure Border Initiative (SBI), a multiyear, multibillion-dollar 
program to secure U.S. borders. One element of SBI is the U.S. Customs 
and Border Protection’s (CBP) SBI program, which is responsible for 
developing a comprehensive border protection system through a mix of 
surveillance and communication technologies known as SBInet (e.g., 
radars, sensors, cameras, and satellite phones), and tactical 
infrastructure (e.g., fencing). 

The House Committee on Homeland Security and its Subcommittee on 
Management, Investigations, and Oversight asked GAO to monitor DHS 
progress in implementing CBP’s SBI program. This testimony provides 
GAO’s observations on (1) technology deployment; (2) infrastructure 
deployment; and (3) how the CBP SBI program office has defined its 
human capital goals and the progress it has made to achieve these 
goals. GAO’s observations are based on prior and new work, including 
analysis of DHS documentation, such as program schedules, contracts, 
and status reports. GAO also conducted interviews with DHS and 
Department of the Interior officials and contractors, and visits to 
sites on the southwest border where SBI deployment is under way. GAO 
performed the work from March to September 2008. DHS generally agreed 
with GAO’s findings. 

What GAO Found: 

SBInet technology deployments continue to experience delays and, as a 
result, Border Patrol agents have to rely upon existing limited 
technological capabilities to help achieve control of the border. SBI 
program officials had originally planned to deploy SBInet technology 
across the southwest border by the end of 2008, but in February 2008 
this date had slipped to 2011. In July 2008, officials reported that 
two initial projects that had been scheduled to be completed by the end 
of calendar year 2008 would be finished sometime in 2009. SBInet 
program uncertainties, such as not fully defined program expectations, 
changes to timelines, and confusion over the need to obtain 
environmental permits contribute to ongoing delays of SBInet technology 
deployments. Due to the delays, Border Patrol agents continue to use 
existing technology that predates SBInet, and in the Tucson, Arizona, 
area they are using capabilities from SBInet’s prototype system despite 
previously reported performance shortfalls. Further delays of SBInet 
technology deployments may hinder the Border Patrol’s efforts to secure 
the border. 

The deployment of fencing is ongoing, but costs are increasing, the 
life-cycle cost is not yet known, and meeting DHS’s statutorily 
required goal to have 670 miles of fencing in place by December 31, 
2008, will be challenging. As of August 22, 2008, the SBI program 
office reported that it had constructed a total of 341 miles of 
fencing, and program officials stated that they plan to meet the 
December 2008 deadline. However, project costs are increasing and 
various factors pose challenges to meeting this deadline, such as a 
short supply of labor and land acquisition issues. According to program 
officials, as of August 2008, fencing costs averaged $7.5 million per 
mile for pedestrian fencing and $2.8 million per mile for vehicle 
fencing, up from estimates in February 2008 of $4 million and $2 
million per mile, respectively. Furthermore, the life-cycle cost is not 
yet known, in part because of increasing construction costs and because 
the program office has yet to determine maintenance costs and locations 
for fencing projects beyond December 2008. In addition, land 
acquisition issues present a challenge to completing fence 
construction. 

As of September 2008, the SBI program office was reevaluating its 
staffing goal and continued to take actions to implement its human 
capital plan. In February 2008, we reported that the SBI program office 
had established a staffing goal of 470 employees for fiscal year 2008. 
As of August 1, 2008, the SBI program office reported having 129 
government staff and 164 contractor support staff for a total of 293 
employees. Program officials stated that a reorganization of the SBI 
program office and SBInet project delays have resulted in fewer 
staffing needs and that they plan to continue to evaluate these needs. 
The SBI program office also continued to take steps to implement its 
human capital plan. For example, recruitment efforts are under way to 
fill open positions. However, the SBI program office is in the process 
of drafting or has drafted documents, such as the Succession Management 
Plan, that have yet to be approved or put into action. 

To view the full product, including the scope and methodology, click on 
[hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-1141T]. For more 
information, contact Richard M. Stana at (202) 512-8777 or 
stanar@gao.gov. 

[End of section] 

Chairman Thompson, Mr. King, and Members of the Committee: 

I am pleased to be here today to discuss observations on selected 
aspects of the Secure Border Initiative (SBI) program implementation. 
Securing the nation's borders from illegal entry of aliens and 
contraband, including terrorists and weapons of mass destruction, 
continues to be a major concern. Much of the United States' 6,000 miles 
of international borders with Canada and Mexico remains vulnerable to 
illegal entry. Although the Department of Homeland Security (DHS) 
apprehends hundreds of thousands of people entering the country 
illegally each year, several hundreds of thousands of individuals also 
enter the United States illegally and undetected. In November 2005, DHS 
announced the launch of the Secure Border Initiative (SBI), a 
multiyear, multibillion-dollar program aimed at securing U.S. borders 
and reducing illegal immigration. Elements of SBI will be carried out 
by several organizations within DHS. The U.S. Customs and Border 
Protection's (CBP) SBI program[Footnote 1] is responsible for 
developing a comprehensive border protection system using technology, 
known as SBInet, and tactical infrastructure--fencing, roads, and 
lighting. 

You requested that we monitor CBP's SBI program and provide periodic 
updates on the status of the program. My testimony today is the third 
in a series of interim reports on SBI implementation[Footnote 2] and 
focuses on the following issues: 

* SBInet technology deployment, 

* SBI tactical infrastructure deployment, and: 

* how the SBI program office has defined its human capital goals and 
the progress it has made to achieve these goals. 

To address these issues, we analyzed DHS documents, including program 
schedules, status reports, and workforce data. We determined that the 
data were sufficiently reliable for purposes of this testimony. We 
interviewed DHS and CBP headquarters and field officials, including 
representatives of the SBI program office, Border Patrol, and Border 
Patrol's Office of Training and Development; U.S. Army Corps of 
Engineers (USACE) officials; Department of Interior (DOI) officials, 
including representatives of the Office of the Deputy Secretary and 
Office of Law Enforcement Security and Emergency Management; and 
representatives of the prime contractor, Boeing. We also visited the 
Border Patrol's Rio Grande Valley, Tucson, and El Paso sectors[Footnote 
3]--sites where SBInet technology, fencing deployment, or both, were 
under way at the time of our review. During the visit to the Rio Grande 
Valley, we also met with public officials and members of the community 
to discuss proposed SBI fencing projects and their effect on the 
communities. We conducted this performance audit from March 2008 
through September 2008 in accordance with generally accepted government 
auditing standards. Those standards require that we plan and perform 
the work to obtain sufficient, appropriate evidence to provide a 
reasonable basis for our findings and conclusions based on our 
objectives. We believe that the evidence obtained provides a reasonable 
basis for our findings and conclusions based on our objectives. 

We also have work underway and have completed work to review other 
components of the SBI program. Specifically, today we are also 
providing a statement for this committee that assesses DHS's efforts to 
define the scope, timing, and approach for developing SBInet 
capabilities, and how well DHS is managing related requirements 
development and management and testing activities.[Footnote 4] We also 
expect to issue a report covering these topics later this month. In 
addition, in April 2008, we completed a report on SBInet as part of a 
broader review of DHS's use of performance-based services acquisition, 
an acquisition method structured around the results to be achieved 
instead of the manner by which the service should be performed. 
[Footnote 5] Lastly, as mandated in the Consolidated Appropriations 
Act, 2008,[Footnote 6] we reviewed DHS's fiscal year 2008 expenditure 
plan for the SBI program and reported in June 2008.[Footnote 7] A list 
of SBI-related products appears at the end of this statement. 

Summary: 

SBInet technology deployments continue to experience delays and, as a 
result, Border Patrol agents have to rely upon existing limited 
technological capabilities to help secure the border. As of October 
2007, SBI program officials expected to complete all of the first 
planned deployment of technology projects across the Tucson, Yuma, and 
El Paso sectors by the end of calendar year 2008. But, by February 
2008, program office officials said that only a portion of the Tucson 
sector would be completed by the end of calendar year 2008 and other 
deployments would be complete by the end of calendar year 2011. In July 
2008, SBI program office officials reported that SBInet technology 
deployment to the Tucson, Yuma and El Paso sectors had been further 
delayed and that the two planned deployments in the Tucson sector would 
be completed sometime in 2009. SBInet program uncertainties, such as 
not fully defined program expectations, changes in deployment 
schedules, and confusion over the applicability of environmental 
regulations, continue to delay SBInet technology deployments. For 
example, the construction permit application for initial SBInet 
deployment sites on environmentally sensitive lands was submitted on 
July 10, 2008. According to DOI officials, the process normally takes 2 
to 3 months and the SBI program office had planned to begin 
construction on July 15, 2008. In the Tucson sector, Border Patrol 
agents are using capabilities provided by Project 28, the SBInet 
prototype, which we previously reported had encountered performance 
shortfalls and delays.[Footnote 8] In other sectors, agents are using 
technology that predates SBInet and does not have the capabilities that 
SBInet is to provide. Further delays of SBInet technology deployments 
may hinder the Border Patrol's efforts to secure the border. 

The deployment of tactical infrastructure projects along the southwest 
border is ongoing, but costs are increasing, the life-cycle 
cost[Footnote 9] is not yet known, and land acquisition issues pose a 
challenge to DHS meeting the goal it set, as required by law, to have 
670 miles of fencing--370 miles of pedestrian fence and 300 miles of 
vehicle fence--in place by December 31, 2008. As of August 22, 2008, 
the SBI program office reported that it had constructed a total of 341 
miles of fencing--187 miles of pedestrian fence and 154 miles of 
vehicle fence, and program officials stated that they plan to meet the 
December 2008 deadline. However, project costs are increasing and 
various factors pose challenges to meeting this deadline, such as a 
short supply of labor and land acquisition issues. According to program 
officials, as of August 2008, fencing costs averaged $7.5 million per 
mile for pedestrian fencing and $2.8 million per mile for vehicle 
fencing, up from estimates in February 2008 of $4 million and $2 
million per mile, respectively.[Footnote 10] Furthermore, SBI program 
office officials do not have a life-cycle cost estimate for fencing, in 
part because of increasing construction costs and also because the SBI 
program office has not yet determined the maintenance costs and 
locations for fencing construction projects beyond December 2008. 
Without a life-cycle cost estimate, the total cost to build and 
maintain fencing along the southwest border is not yet known. With 
respect to land acquisition issues, identifying landowners and 
negotiating land purchases present a challenge to completing fence 
construction by December 2008. For example, as of August 26, 2008, an 
estimated 320 properties remain to be acquired from landowners. Program 
officials noted that the fencing construction segments usually require 
90 to 120 days to complete, and completion of all tactical 
infrastructure projects by December 31, 2008, is in jeopardy if issues 
related to land acquisition are not resolved. 

As of September 2008, the SBI program office was reevaluating its 
staffing goal and office continues to take actions to implement its 
December 2007 human capital plan. In February 2008, we reported that 
the SBI program office had established a staffing goal of 470 employees 
for fiscal year 2008.[Footnote 11] As of August 1, 2008, the SBI 
program office reported having 129 government staff and 164 contractor 
support staff for a total of 293 employees. SBI program office 
officials said that a reorganization of the SBI program office and 
SBInet project delays have resulted in fewer staffing needs. The 
officials further noted they will continue to evaluate the expected 
staffing needs through the end of fiscal year 2009. In addition, the 
SBI program continues to implement its human capital plan. For example, 
the SBI program office has recruitment efforts underway to fill open 
positions. However, in other areas, the SBI program office is in the 
process of drafting or has drafted documents, such as the SBI 
Succession Management Plan, which have yet to be approved and acted 
upon. Until the SBI program office fully implements its plan, it will 
lack a baseline and metrics by which to judge its human capital 
efforts. 

In their oral comments on a draft of this statement, DHS generally 
agreed with our findings and provided clarifying information that we 
incorporated as appropriate. 

Background: 

CBP's SBI program is responsible for deploying SBInet (e.g., sensors, 
cameras, radars, communications systems, and mounted laptop computers 
for agent vehicles), and tactical infrastructure (e.g., pedestrian and 
vehicle fencing, roads, and lighting) that are intended to enable CBP 
agents and officers to gain effective control of U.S. borders.[Footnote 
12] SBInet technology is intended to include the development and 
deployment of a common operating picture (COP) that provides data 
through a command center to Border Patrol agents in the field and 
potentially to all DHS agencies and to be interoperable with 
stakeholders external to DHS, such as local law enforcement. The 
current focus of the SBI program is on the southwest border areas 
between the ports of entry[Footnote 13] that CBP has designated as 
having the highest need for enhanced border security because of serious 
vulnerabilities. The SBI program office and its offices of SBInet and 
tactical infrastructure are responsible for overall program 
implementation and oversight. 

Figure 1: Map of Border Patrol Sectors along the Southwest Border: 

[See PDF for image] 

This figure is a map of Border Patrol Sectors along the southwest 
border. Indicated on the map are state boundaries as well as the 
following Border Patrol Sectors: 
Rio Grande Valley; 
Laredo; 
Marfa; 
El Paso; 
Tucson; 
Yuma; 
El Centro; 
San Diego. 

Source: GAO analysis of CBP data. 

[End of figure] 

In September 2006, CBP awarded a prime contract to the Boeing Company 
for 3 years, with three additional 1-year options. As the prime 
contractor, Boeing is responsible for acquiring, deploying, and 
sustaining selected SBI technology and tactical infrastructure 
projects. In this way, Boeing has extensive involvement in the SBI 
program-requirements development, design, production, integration, 
testing, and maintenance and support of SBI projects. Moreover, Boeing 
is responsible for selecting and managing a team of subcontractors that 
provide individual components for Boeing to integrate into the SBInet 
system. The SBInet contract is largely performance-based--that is, CBP 
has set requirements for the project and Boeing and CBP coordinate and 
collaborate to develop solutions to meet these requirements--and 
designed to maximize the use of commercial off-the-shelf technology. 
[Footnote 14] CBP's SBI program office oversees and manages the Boeing-
led SBI contractor team. 

CBP is executing part of SBI activities through a series of task orders 
to Boeing for individual projects. As of September 5, 2008, CBP had 
awarded 11 task orders to Boeing for a total amount of $933.3 million. 
Table 1 is a summary of the task orders awarded to Boeing for SBI 
projects. 

Table 1: Task Orders Awarded to Boeing for SBI projects as of September 
5, 2008 (Dollars in millions): 

Task Order Description: 
Program Management: The mission engineering, facilities and 
infrastructure, systems engineering, test and evaluation, and program 
management services to develop and deploy the SBInet system; 
Date awarded: 09/21/2006; 
Task order obligation: $144.0. 

Task Order Description: 
Project 28: Boeing's pilot project and initial implementation of SBInet 
technology for 28 miles of the border in the Tucson sector; 
Date awarded: 10/20/2006; 
Task order obligation: $20.6. 

Task Order Description: 
Barry M. Goldwater Range (BMGR): The construction of 32 miles of 
vehicle and pedestrian barriers on the southern border of the BMGR in 
the Yuma sector; 
Date awarded: 01/12/2007; 
Task order obligation: $122.2. 

Task Order Description: 
Fence Lab: The testing of potential pedestrian and vehicle fence and 
barrier solutions; 
Date awarded: 02/16/2007;
Task order obligation: $0.7. 

Task Order Description: 
Design: SBInet deployment design solution including design, 
environmental-clearance support, and locations for the SBInet 
technology solution in the Yuma, Tucson, and El Paso sectors; 
Date awarded: 08/01/2007; 
Task order obligation: $84.0. 

Task Order Description: 
Project 28 Contractor Maintenance and Logistics Support: Provides 
Project 28 with the required maintenance and logistics support to 
operate the system; 
Date awarded: 12/07/2007; 
Task order obligation: $10.6. 

Task Order Description: 
Command, Control, Communications and Intelligence (C3I) and Common 
Operating Picture: The development of the next version of the SBInet 
operating software to design, develop, and demonstrate a functional 
SBInet C3I/COP system; 
Date awarded: 12/07/2007; 
Task order obligation: $64.5. 

Task Order Description: 
SBInet System: A follow-on to the program management task order, this 
task order specifies the program management and system-engineering 
activities required to achieve an integrated program across all task 
orders issued under the SBI contract; 
Date awarded: 04/15/2008; 
Task order obligation: $93.6. 

Task Order Description: 
Supply and Supply Chain Management: The development and implementation 
of a supply and supply chain management system solution to execute 
tactical infrastructure projects; 
Date awarded: 06/06/2008; 
Task order obligation: $313.3[A]. 

Task Order Description: 
Arizona Deployment Task Order: Boeing's deployment of the SBInet system 
along approximately 53 miles of the southwest border in the Tucson 
sector; 
Date awarded: 06/25/2008; 
Task order obligation: $70.5. 

Task Order Description: 
Integrated Logistics Support: Provides SBInet with the required 
maintenance and logistics support to operate the system; 
Date awarded: 08/16/2008; 
Task order obligation: $9.3. 

Total, Task order obligation: $933.3. 

Source: GAO Analysis of CBP data. 

[A] In January 2008, CBP issued a letter task order for the Supply and 
Supply Chain Management in the estimated amount of $733.3 million. On 
June 6, 2008, CBP finalized the task order in the amount of $313.3 
million. 

[End of table] 

In addition to deploying technology across the southwest border, the 
SBI program office plans to deploy 370 miles of single-layer pedestrian 
fencing and 300 miles of vehicle fencing by December 31, 2008. 
Pedestrian fencing is designed to prevent people on foot from crossing 
the border and vehicle fencing consists of physical barriers meant to 
stop the entry of vehicles. Figure 2 shows examples of SBI fencing 
styles along the southwest border. The SBI program office, through the 
tactical infrastructure program, is using USACE to contract for fencing 
and supporting infrastructure (such: 

as lights and roads), complete required environmental assessments, and 
acquire necessary real estate.[Footnote 15] In June 2008, CBP awarded 
Boeing a supply and supply chain management task order for the purchase 
of construction items, such as steel. 

Figure 2: Examples of SBI Fencing Styles along the Southwest Border: 

[See PDF for image] 

Four photographs: 

The Picket Fence (upper left), Bollard Fence (upper right) and Post & 
Rail with wire mesh (lower left) are examples of pedestrian fencing; 
the Normandy Vehicle Fence (lower right) is an example of vehicle 
fencing. 

Source: CBP. 

[End of figure] 

Since fiscal year 2006, Congress has appropriated more than $2.7 
billion for SBI. Table 2 shows SBI obligations from fiscal years 2006 
through 2008 for SBInet technology, tactical infrastructure, and 
program management. DHS has requested an additional $775 million for 
SBI for fiscal year 2009. 

Table 2: SBI Funding Fiscal Years 2006 to 2008, as of March 2008 
(Dollars in billions): 

Allocation of funds: SBInet Technology; 
Total funds: $0.74; 
Percent of total funds: 27. 

Allocation of funds: Tactical Infrastructure; 
Total funds: $1.84; 
Percent of total funds: 67. 

Allocation of funds: Program Management[A]; 
Total funds: $0.15; 
Percent of total funds: 6. 

Allocation of funds: Total; 
Total funds: $2.73; 
Percent of total funds: 100. 

Source: GAO Analysis of CBP data. 

[A] Includes personnel operations and support, and regulatory and 
environmental requirements. 

[End of table] 

SBInet Deployment Delays Are Ongoing and Border Patrol Agents Continue 
to Use Existing Technology to Secure Borders: 

SBInet technology deployments continue to experience delays and, as a 
result, Border Patrol agents have to rely upon existing limited 
technological capabilities to help achieve effective control of the 
border. We reported in October 2007, that SBI program office officials 
expected to complete all of the first planned deployment of technology 
projects in the Tucson, Yuma, and El Paso sectors by the end of 2008. 
[Footnote 16] In February 2008, we reported that the first planned 
deployment of technology would occur in two geographic areas within the 
Tucson sector--known as Tucson-1 and Ajo-1--by the end of calendar year 
2008, with the remainder of deployments to the Tucson, Yuma, and El 
Paso sectors scheduled to be completed by the end of calendar year 
2011.[Footnote 17] In July 2008, SBI program office officials reported 
that SBInet technology deployments to Tucson-1 and Ajo-1 would be 
completed sometime in 2009. These officials further noted that SBInet 
technology deployments in the Tucson, Yuma, and El Paso sectors had 
also been delayed. 

SBInet program uncertainties contribute to ongoing delays of SBInet 
technology deployments. These include: 

* SBInet technology will be deployed to fewer sites than originally 
planned by the end of 2008; is expected to have fewer capabilities than 
originally planned at that time; and as discussed above, the SBInet 
program office does not have specific deployment dates; 

* SBInet planning documents and mechanisms, such as the integrated 
master schedule, have not received executive approval and are 
constantly changing.[Footnote 18] For example, the current (unapproved) 
schedule is out of date and under revision; and: 

* The SBInet program office has not effectively defined and managed 
program expectations, including specific project requirements.[Footnote 
19] 

The need to obtain environmental permits is also contributing to the 
initial Tucson deployment delays. According to DOI officials, DHS 
officials initially stated that the DHS authority to waive all legal 
requirements as necessary to ensure expeditious construction covered 
both SBInet technology and tactical infrastructure projects.[Footnote 
20] However, DHS officials later determined that the Secretary's April 
1, 2008, waiver did not extend to the Tucson-1 and Ajo-1 SBInet 
projects. Without waiver coverage for these projects, DHS must conform 
to the National Environmental Policy Act,[Footnote 21] which requires 
federal agencies to evaluate the likely environmental effects of 
projects they are proposing using an environmental assessment or, if 
the projects likely would significantly affect the environment, a more 
detailed environmental impact statement. According to DOI officials, 
SBI program office officials had planned to submit the permit 
application for the Tucson-1 project area in February 2008, requesting 
access and permission to build on environmentally sensitive lands. SBI 
officials said that they had been working with DOI local land managers; 
however, due to confusion over the DHS waiver authority, the complete 
application for the tower construction sites was submitted on July 10, 
2008, while the SBI program office had planned to begin construction 
for Tucson-1 on July 15, 2008. According to DOI officials, the approval 
process normally takes 2 to 3 months, but they have expedited the DHS 
permit and plan to resolve the application in mid-September 2008. 

Given the delays with SBInet technology deployment, Border Patrol 
agents continue to rely upon existing technologies. The cameras and 
sensors in use predate SBInet technology and do not have the 
capabilities that SBInet technology is to provide.[Footnote 22] In 
addition, some of the equipment currently in use may be outdated. For 
example, in the Border Patrol's El Paso sector, aging cameras and 
sensors do not work in inclement weather and do not always function at 
night. In the Tucson sector, Border Patrol agents are using 
capabilities provided by Project 28, the SBInet prototype that was 
accepted by the government in February 2008. We previously reported 
that Project 28 encountered performance shortfalls and delays.[Footnote 
23] Despite these performance shortfalls, agents in the Tucson Sector 
continue to use Project 28 technology capabilities while waiting for 
the SBInet technology deployment. During our visit to the Tucson Sector 
in June 2008, Border Patrol agents told us that the system had improved 
their operational capabilities, but that they must work around ongoing 
problems, such as finding good signal strength for the wireless 
network, remotely controlling cameras, and modifying radar sensitivity. 
Moreover, during our visit we observed the agents' difficulties in 
logging on to the wireless network and maintaining the connection from 
the vehicle-mounted mobile data terminal.[Footnote 24] Project 28 is 
the only available technology in the Tucson-1 project area of the 
Tucson sector, compared to the Ajo-1 project area, which does not have 
any technology. Further delays of SBInet technology deployments may 
hinder the Border Patrol's efforts to secure the border. 

Tactical Infrastructure Deployment Continues, but Costs Are Increasing, 
the Life-Cycle Cost Is Not Yet Known, and Land Acquisition Issues Pose 
a Challenge to Completion of the Timeline: 

The deployment of tactical infrastructure projects along the southwest 
border is ongoing, but costs are increasing, the life-cycle cost is not 
yet known, and land acquisition issues pose challenges to DHS in 
meeting the goal it set, as required by law, to complete 670 miles of 
fencing--370 miles of pedestrian fence and 300 miles of vehicle fence, 
by December 31, 2008.[Footnote 25] We previously reported that as of 
February 21, 2008, the SBI program office had constructed 168 miles of 
pedestrian fence and 135 miles of vehicle fence.[Footnote 26] See 
figure 3 for photographs of SBI tactical infrastructure projects in 
Arizona and New Mexico. Approximately 6 months later, the SBI program 
office reports that 19 additional miles of pedestrian fence and 19 
additional miles of vehicle fence have been constructed as of August 
22, 2008 (see table 3). 

Figure 3: Examples of SBI Fence Construction: 

[See PDF for image] 

Three photographs: 

Construction of Post & Rail with wire mesh fence in Lukeville, Arizona, 
as of June 10, 2008 (left) and Santa Teresa, New Mexico, as of August 
26, 2008 (right). 

Completed Post & Rail with 4-gauge wire mesh (15 feet high) near Santa 
Teresa, Mexico. 

Source: GAO. 

[End of figure] 

Table 3: Tactical Infrastructure Deployment Progress as of August 22, 
2008: 

Infrastructure Type: Pedestrian fencing; 
Miles in place before SBI: 78; 
Miles deployed through SBI as of 08/22/08: 109; 
Total miles in place as of 08/22/08: 187; 
Target for 12/31/08: 370; 
Miles remaining to meet target: 183. 

Infrastructure Type: Vehicle fencing; 
Miles in place before SBI: 57; 
Miles deployed through SBI as of 08/22/08: 97; 
Total miles in place as of 08/22/08: 154; 
Target for 12/31/08: 300; 
Miles remaining to meet target: 146. 

Infrastructure Type: Total; 
Miles in place before SBI: 135; 
Miles deployed through SBI as of 08/22/08: 206; 
Total miles in place as of 08/22/08: 341; 
Target for 12/31/08: 670; 
Miles remaining to meet target: 329. 

Source: GAO analysis of SBI data. 

[End of table] 

Although SBI program office and USACE officials stated that they plan 
to meet the December deadline, factors such as a short supply of labor 
and materials, and the compressed timeline affect costs. SBI program 
office officials said that beginning in July 2008, as they were in the 
process of finalizing construction contracts, cost estimates for 
pedestrian fencing in Texas began to increase. According to USACE 
officials, as of August 28, 2008, fencing costs[Footnote 27] average 
$7.5 million per mile for pedestrian fencing and $2.8 million per mile 
for vehicle fencing, up from estimates in February 2008[Footnote 28] of 
$4 million and $2 million per mile, respectively. SBI program office 
officials attributed the cost increases to a short supply of both labor 
and materials as well as the compressed timeline. For example, they 
said that as a result of a construction boom in Texas, labor is in 
short supply and contractors report that they must provide premium pay 
and overtime to attract workers. In terms of materials, USACE officials 
stated the price of cement and steel have increased and in some areas 
within Texas obtaining cement near the construction site is difficult. 
For example, contractors are now procuring cement from Colorado, and 
aggregate, a cement mixing agent, from Houston, Texas. The SBI program 
office officials also said that increasing fuel costs for transporting 
steel and cement were contributing factors. Officials said they are 
working to mitigate the cost increases where possible, for example, 
through their bulk purchase of steel and their negotiations in one 
county where premium labor rates were higher than usual. The SBI 
program office officials said that the compressed construction timeline 
also contributes to the cost increase, particularly in terms of labor 
costs. 

The SBI program office does not yet have an estimated life-cycle cost 
for fencing because maintenance costs are unknown and the SBI program 
office has not identified locations for fencing construction projects 
beyond December 2008. The fiscal year 2008 Consolidated Appropriations 
Act required DHS to submit to the House and Senate Appropriations 
Committees an expenditure plan for the SBI program that included, among 
other things, a life-cycle cost estimate. However, the plan did not 
include the estimate. In a June 2008 response to an inquiry from the 
Chairman of the House Appropriations Subcommittee on Homeland Security 
regarding several deficiencies in the plan, the Secretary of Homeland 
Security stated that because Border Patrol agents have traditionally 
repaired damaged fencing themselves, DHS does not have historical cost 
data on fence repair by contractors on which to estimate life-cycle 
fence costs. However, according to the letter, DHS is currently 
collecting information on maintenance costs and by early calendar year 
2009 plans to have a life-cycle cost estimate. In the near term, the 
department requested $75 million for operations and maintenance of 
tactical infrastructure in fiscal year 2009, according to the letter. 
In addition, Border Patrol officials have identified additional 
segments of the southwest border for construction of pedestrian and 
vehicle fencing beyond December 2008 and SBI program office and Border 
Patrol stated that they are developing fencing project priorities for 
2009. However, they have not yet established a timeline for 
construction, and sources of funding have not been determined. 

Land acquisition issues such as identifying landowners and negotiating 
land purchases present a challenge to completing fence construction by 
December 31, 2008. According to SBI program office officials, in order 
to adhere to this timeline, all fencing construction projects must be 
underway by September 30, 2008. However, according to SBI program 
office officials, as of August 26, 2008, an estimated 320 properties 
remain to be acquired from landowners. USACE officials noted that 
completion of fencing construction projects usually take 90 to 120 days 
and the December 31, 2008 deadline, is in jeopardy if ongoing 
litigation related to land acquisition is not resolved by September 30, 
2008 (see table 4).[Footnote 29] 

Table 4: Land Acquisition Status for Pedestrian and Vehicle Fencing as 
of August 26, 2008: 

Landowner Status: Landowner has offered to sell; 
Number of Properties: 184. 

Landowner Status: Landowner has refused to sell; 
Number of Properties: 122. 

Landowner Status: Landowner is unknown; 
Number of Properties: 8. 

Landowner Status: Landowner negotiations are ongoing; 
Number of Properties: 6. 

Landowner Status: Total property acquisitions remaining[A]; 
Number of Properties: 320. 

Source: GAO analysis of USACE data. 

[A] Agency officials stated that 56 land acquisitions were resolved in 
addition to the 320 property acquisitions remaining. 

[End of table] 

Of the 122 landowners who have refused to sell, 97 are within the Rio 
Grande Valley sector. As of August 28, 2008, of these 97 landowners, 20 
are defendants in lawsuits filed by the Department of Justice at the 
request of the Secretary of Homeland Security for the condemnation and 
taking of their property. According to USACE officials, the 20 lawsuits 
were filed in July 2008 and are awaiting an order of possession ruling 
expected sometime in September 2008. Subsequent lawsuits were filed 
against the remaining 77 landowners, but court dates have not been set. 
[Footnote 30] 

The SBI Program Management Office Is Reevaluating Its Staffing Goal and 
Has Continued to Take Steps to Implement Its Human Capital Plan: 

As of September 2008, the SBI program office was reevaluating its 
staffing goal, and the SBI program office continued to take steps to 
implement the December 2007 Human Capital Plan. In February 2008, we 
reported that the SBI program office had established a staffing goal of 
470 employees for fiscal year 2008.[Footnote 31] As of August 1, 2008, 
the SBI program office reported having 129 government staff and 164 
contractor support staff for a total of 293 employees (see table 5). 
SBI program office officials stated that a reorganization of the SBI 
program office and project delays have resulted in a need for fewer 
staff during fiscal year 2008. The officials further noted they plan to 
continue to evaluate the expected staffing needs through the end of 
fiscal year 2009. 

Table 5: SBI Employees, as of August 1, 2008: 

SBInet; 
Government: 48; 
Contractors: 102; 
Total: 150. 

Tactical infrastructure; 
Government: 14; 
Contractors: 27; 
Total: 41. 

Other[A]; 
Government: 67; 
Contractors: 35; 
Total: 102. 

Total; 
Government: 129; 
Contractors: 164; 
Total: 293. 

Source: SBI program office. 

[A] Other includes employees in the Office of the Executive Director, 
the Office of Budget and Finance, the SBI Acquisition Office, the 
Transportation program office, and the Program Control Division. 

[End of table] 

The SBI program office published the first version of its Strategic 
Human Capital Management Plan in December 2007, and as of September 
2008, continued to implement the plan. The SBI program office's plan 
outlines seven main goals for the office and includes planned 
activities to accomplish those goals, which align with federal 
government best practices.[Footnote 32] As of September, 2008, the SBI 
program office had taken several steps to implement the plan. For 
example, the SBI program office held a meeting on September 2, 2008, to 
develop SBI's mission, visionary goals and objectives, and core values, 
and the office has recruitment efforts under way to fill open 
positions. However, in other areas, the SBI program office is in the 
process of drafting or has drafted documents, such as the SBI Value 
Statement, the SBI Awards and Recognition Plan, and the Succession 
Management Plan, which have yet to be approved and acted upon. Table 6 
summarizes the seven human capital goals, the SBI program office's 
planned activities, and steps taken to accomplish these activities. We 
have previously reported that a properly designed and implemented human 
capital program can contribute to achieving an agency's mission and 
strategic goals.[Footnote 33] Until the SBI program office fully 
implements its plan, it will lack a baseline and metrics by which to 
judge the human capital aspects of the program. 

Table 6: Human Capital Goals, Planned Activities, and Steps Taken: 

SBI human capital goals: (1) Develop a coherent framework of human 
capital policies, programs, and practices to achieve a shared vision 
integrated with SBI's strategic plan; 
Planned activities: Complete the SBI human capital plan; 
Steps taken as of February 2008: 
* Completed the first draft of the human capital plan; 
* Prepared the fiscal year 2008 staffing plan; 
Steps taken as of September 2008, as reported by the SBI program 
management office: 
* Human capital plan completed and to be updated on recurring basis; 
* Staffing plan drafted and pending approval. 

SBI human capital goals: (2) Prepare leaders to lead and manage the 
workforce; (3) Create and instill within the organization a value- 
driven organization; 
Planned activities: (1) Identify key leaders' skills and competencies, 
develop and deliver a leadership/management workshop focused on 
equipping SBI leaders with these skills; (2) Identify key organization 
values and create an SBI Value Statement; 
Steps taken as of February 2008: 
* Planning SBI leadership off-site meeting in early April, which will 
include discussions of leadership needs; 
* Planning to conduct 360° assessments for SBI leadership in late 
spring/early summer; 
Steps taken as of September 2008, as reported by the SBI program 
management office: 
* Leadership meeting held September 2, 2008 to develop SBI mission, 
visionary goals and objectives, and core values; 
* The 360° assessments for SBI leadership deferred to fiscal year 2009; 
* Project manager, contracting officer's technical representative, and 
contracting officer certification and training available; 
* SBI Value Statement is drafted; final approval is anticipated within 
30 days. 

SBI human capital goals: (4) Develop and implement a succession 
management plan; 
Planned activities: Develop a succession strategy for mission-critical 
positions; 
Steps taken as of February 2008: 
* Not yet started; 
Steps taken as of September 2008, as reported by the SBI program 
management office: 
* Succession Management Plan in progress; Currently identifying Mission 
Critical Positions. 

SBI human capital goals: (5) Define the performance culture (reward 
excellence); 
Planned activities: Based on the CBP Awards and Recognition Program, 
create an SBI policy and practice on rewards and recognition; 
Steps taken as of February 2008: 
* Designed but not yet implemented a program to recognize high 
performers; 
* Drafted a recognition program; 
Steps taken as of September 2008, as reported by the SBI program 
management office: 
* SBI Awards and Recognition Plan drafted; approval anticipated within 
30 to 60 days; 
* Awards recognition ceremonies conducted monthly. 

SBI human capital goals: (6) Hire, recruit, develop, and retain 
employees with the skills for mission accomplishment; 
Planned activities: Fill vacancies with qualified professionals and 
create a Supervisors' Onboarding Guide and retention interview process; 
Steps taken as of February 2008: 
* Developed an orientation course for new employees; 
* Drafted, but not yet finalized, the Supervisors' Onboarding Guide; 
* Recruitment efforts under way to fill open SBI positions in all 
programs; 
Steps taken as of September 2008, as reported by the SBI program 
management office: 
* SBI orientation approved and operational; 
* Approval of the Supervisors Onboarding Guide anticipated within 30 to 
60 days; 
* Recruitment efforts underway to fill open SBI positions; 
* SBI section of CBP's National Training Plan submitted. 

SBI human capital goals: (7) Establish leadership accountability for 
human capital management; 
Planned activities: Clarify key leadership responsibilities and metrics 
of success; 
Steps taken as of February 2008: 
* Not yet started; 
Steps taken as of September 2008, as reported by the SBI program 
management office: 
* Have started to link individual performance goals to DHS's strategic 
priorities. 

Source: GAO analysis of CBP data. 

[End of table] 

Concluding Observations: 

The SBI program continues to face challenges that include delays in 
project implementation and cost increases. The delays and cost 
uncertainties could affect DHS's ability to meet projected completion 
dates, expected costs, and performance goals. Border Patrol agents 
continue to rely upon existing limited technological capabilities as 
SBInet technology deployments delays persist, and this may hinder the 
Border Patrol's efforts to secure the border. In the tactical 
infrastructure area, meeting the Secretary's goal to build 670 miles of 
fencing by December 31, 2008, a goal that DHS was required by law to 
set for itself, continues to be challenging. Since our last report to 
you 6 months ago, 38 miles of fence have been built and 329 are to be 
constructed during the next 4 months - provided that land acquisition 
issues can be resolved. Furthermore, tactical infrastructure costs are 
increasing and the SBI program office has not yet determined a life- 
cycle cost for fencing because maintenance costs are unknown and the 
SBI program office has not identified the locations for fencing 
construction projects beyond December 31, 2008; therefore, the total 
cost for building and maintaining fences along the southwest border is 
not yet known. These issues underscore Congress's need to stay closely 
attuned to DHS's progress to ensure that schedule and cost estimates 
stabilize, and the program efficiently and effectively addresses the 
nation's border security needs. 

This concludes my prepared testimony. I would be pleased to respond to 
any questions that members of the committee may have. 

Contacts and Acknowledgments: 

For questions regarding this testimony, please call Richard M. Stana at 
(202) 512-8777 or stanar@gao.gov. Contact points for our offices of 
Congressional Relations and Public Affairs may be found on the last 
page of this statement. In addition to the contact named above, Susan 
Quinlan, Assistant Director, and Jeanette Espínola, Analyst-in-Charge, 
managed this assignment. Sylvia Bascopé, Burns Chamberlain, Katherine 
Davis, Jeremy Rothgerber, and Erin Smith made significant contributions 
to the work. 

[End of section] 

Related GAO Products: 

Secure Border Initiative: Fiscal Year 2008 Expenditure Plan Shows 
Improvement, but Deficiencies Limit Congressional Oversight and DHS 
Accountability. [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-
739R]. Washington, D.C.: June 26, 2008. 

Department of Homeland Security: Better Planning and Oversight Needed 
to Improve Complex Service Acquisition Outcomes. [hyperlink, 
http://www.gao.gov/cgi-bin/getrpt?GAO-08-765T]. Washington, D.C.: May 
8, 2008. 

Department of Homeland Security: Better Planning and Assessment Needed 
to Improve Outcomes for Complex Service Acquisitions. [hyperlink, 
http://www.gao.gov/cgi-bin/getrpt?GAO-08-263]. Washington, D.C.: April 
22, 2008. 

Secure Border Initiative: Observations on the Importance of Applying 
Lessons Learned to Future Projects. [hyperlink, http://www.gao.gov/cgi-
bin/getrpt?GAO-08-508T]. Washington, D.C.: February 27, 2008. 

Secure Border Initiative: Observations on Selected Aspects of SBInet 
Program Implementation. [hyperlink, http://www.gao.gov/cgi-
bin/getrpt?GAO-08-131T]. Washington, D.C.: October 24, 2007. 

Secure Border Initiative: SBInet Planning and Management Improvements 
Needed to Control Risks. [hyperlink, http://www.gao.gov/cgi-
bin/getrpt?GAO-07-504T]. Washington, D.C.: February 27, 2007. 

Secure Border Initiative: SBInet Expenditure Plan Needs to Better 
Support Oversight and Accountability. [hyperlink, 
http://www.gao.gov/cgi-bin/getrpt?GAO-07-309]. Washington, D.C.: 
February 15, 2007. 

[End of section] 

Footnotes: 

[1] The CBP SBI Program Executive Office, referred to in this testimony 
as the SBI program office, is responsible for overseeing all SBI 
activities for acquisition and implementation, including establishing 
and meeting program goals, objectives, and schedules; for overseeing 
contractor performance; and for coordinating among DHS agencies. 

[2] See GAO, Secure Border Initiative: Observations on the Importance 
of Applying Lessons Learned to Future Projects, [hyperlink, 
http://www.gao.gov/cgi-bin/getrpt?GAO-08-508T] (Washington, D.C.: Feb. 
27, 2008); and Secure Border Initiative: Observations on Selected 
Aspects of SBInet Program Implementation, [hyperlink, 
http://www.gao.gov/cgi-bin/getrpt?GAO-08-131T] (Washington, D.C.: Oct. 
24, 2007). 

[3] The U.S. Border Patrol has 20 sectors responsible for detecting, 
interdicting, and apprehending those who attempt illegal entry or 
smuggle people--including terrorists, contraband, and weapons of mass 
destruction--across U.S. borders between official ports of entry. 

[4] See GAO, Secure Border Initiative: DHS Needs to Address Significant 
Risks in Delivering Key Technology Investment, [hyperlink, 
http://www.gao.gov/cgi-bin/getrpt?GAO-08-1148T] (Washington, D.C.: 
Sept. 10, 2008). 

[5] See GAO, Department of Homeland Security: Better Planning and 
Assessment Needed to Improve Outcomes for Complex Service Acquisitions, 
[hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-263] (Washington, 
D.C.: Apr. 22, 2008) and Department of Homeland Security: Better 
Planning and Oversight Needed to Improve Complex Service Acquisition 
Outcomes, [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-765T] 
(Washington, D.C.: May 8, 2008). 

[6] Pub. L. No. 110-161, 121 Stat. 1844, 2047-2049. 

[7] See GAO, Secure Border Initiative Fiscal Year 2008 Expenditure Plan 
Shows Improvement, but Deficiencies Limit Congressional Oversight and 
DHS Accountability, GAO-08-739R (Washington, D.C.: June 26, 2008). 

[8] [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-508T]. 

[9] The estimated life cycle cost is the total cost to the government 
for a program over its full life, consisting of research and 
development, operations, maintenance, and disposal costs. Using a life- 
cycle cost estimate to determine the budget helps to ensure that all 
costs are fully accounted for so that resources are adequate to support 
the program. See GAO, Cost Assessment Guide: Best Practices for 
Estimating and Managing Program Costs--Exposure Draft, [hyperlink, 
http://www.gao.gov/cgi-bin/getrpt?GAO-07-1134SP] (Washington, D.C: July 
2007). 

[10] [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-508T]. 

[11] [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-508T]. 

[12] DHS defines effective control of U.S. borders as the ability to 
consistently: (1) detect illegal entries into the United States; (2) 
identify and classify these entries to determine the level of threat 
involved; (3) efficiently and effectively respond to these entries; and 
(4) bring events to a satisfactory law enforcement resolution. 

[13] At a port of entry location, CBP officers secure the flow of 
people and cargo into and out of the country, while facilitating 
legitimate travel and trade. 

[14] Commercial off-the-shelf is a term for software or hardware, 
generally technology or computer products, that are available for sale, 
lease, or license to the general public. 

[15] The SBI program office contracted with Boeing Company to construct 
32 miles of fencing in the BMGR. Deployment of this fencing has been 
completed, and the SBI program office plans to use USACE to contract 
for most remaining pedestrian fencing and vehicle barriers to be 
deployed through December 2008. 

[16] [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-131T]. 

[17] [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-508T]. 

[18] The integrated master schedule is a planning tool intended to 
integrate the disparate project schedules that officials use to manage 
SBInet program activities. 

[19] These issues are discussed in greater detail in GAO-08-1148T. 

[20] The REAL ID Act of 2005 allowed the Secretary of Homeland Security 
to waive all legal requirements he determines necessary to ensure 
expeditious construction of physical barriers and roads along the U.S. 
border to deter illegal crossings in areas of high illegal entry. 
Pub.L.No. 109-19, § 102, 119 Stat. 302, 306. 

[21] 42 U.S.C. §§ 4321-4347. 

[22] SBInet is to provide a system with the detection, identification, 
and classification capabilities required to maintain operational 
control of the border. To do so, Boeing is to provide, among other 
items, mobile towers equipped with radar, cameras, a COP that 
communicates comprehensive situational awareness, and secure-mounted 
laptop computers retrofitted in vehicles to provide agents in the field 
with COP information. 

[23] [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-508T]. 

[24] A mobile data terminal is a laptop computer mounted in select 
agent vehicles in the field. Mobile data terminals enable field agents 
to see information similar to that seen by command center operators. 

[25] The Consolidated Appropriations Act of 2008, requires DHS to 
complete construction by December 31, 2008, of 370 miles (or other 
mileage determined by the Secretary) of reinforced fencing along the 
southwest border wherever the Secretary determines it would be most 
practical and effective in deterring smugglers and aliens attempting 
illegal entry. 

[26] [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-508T]. 

[27] According to USACE officials, the cost includes program 
management, environmental assessments, design, real estate, 
construction management, and construction costs. 

[28] [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-508T]. 

[29] USACE officials stated they have the primary responsibility for 
negotiating land acquisition agreements for fence construction with 
private landowners. In cases where the property owner does not agree to 
right of entry or an offer to sell, the Department of Justice files a 
lawsuit against the landowner on behalf of the United States of America 
at the request of the Secretary of Homeland Security for the 
condemnation and taking of the property. 

[30] As of August 28, 2008, USACE officials reported that they continue 
to negotiate with these land owners and some of these lawsuits may be 
settled out of court. 

[31] [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-508T]. 

[32] These best practices are contained in the government-wide Human 
Capital Assessment and Accountability Framework which was developed by 
Office of Management and Budget, the Office of Personnel Management, 
and GAO. 

[33] See GAO, Human Capital: Key Principles for Effective Strategic 
Workforce Planning, [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-
04-39] (Washington, D.C.: Dec. 11, 2003). 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office: 
441 G Street NW, Room LM: 
Washington, D.C. 20548: 

To order by Phone: 
Voice: (202) 512-6000: 
TDD: (202) 512-2537: 
Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: