Fiscal Year: 2004
Total dollars: $243,437,111
This Congressional District is ranked 224 among districts for this year.
Total number of contractors: 191
Total number of transactions: 1,570
Get list of contractors
Get list of transactions
Extent of Competition
| Available for everyone for competition | $70,899,278 |
| Everyone could compete, but only one bid or offer was received | $35,085,215 |
| Competition within a limited pool | $74,386,601 |
| Actions necessary to continue existing competitive contracts for continuity (until the next one could be competed) | $1,625,916 |
| Available only for groups such as disabled persons, prisoners, and regulated utilities | $19,481,529 |
| Not competed for an allowable reason | $29,992,410 |
| Not identified, soon to be addressed | $11,966,160 |
Top 5 Known Congressional Districts where Work is Performed
Massachusetts 6 (John F. Tierney) | $4,122,701 |
California 44 (Ken Calvert) | $2,828,229 |
Mississippi 4 (Gene Taylor) | $2,033,320 |
Nebraska 1 (Doug Bereuter) | $1,308,314 |
Arizona 4 (Ed Pastor) | $1,289,400 |
| |
Top 5 Products or Services Sold
Engineering and Technical Services | $24,613,159 |
Other ADP and Telecommunications Services (includes data storage on tapes, compact disks, etc.) | $20,035,871 |
Construction of Structures and Facilities -- Other Non-Building Facilities | $15,637,413 |
Operation of Government-Owned Facilities -- Electronic and Communications Facilities | $14,000,000 |
Gas Generating and Dispensing Systems, Fixed or Mobile | $13,952,553 |
Top 5 Contracting Agencies Purchasing from Contractor(s)
NAVY, Department of the | $62,745,924 |
ARMY, Department of the (except Corps of Engineers Civil Program Financing) | $61,199,226 |
AIR FORCE, Department of the (Headquarters, USAF) | $52,456,576 |
Federal Technology Service | $22,240,189 |
STATE, Department of | $14,412,543 |
Top 10 Contractors
Stronghold Engineering Inc | $66,160,748 |
Computer Sciences Corporation | $61,162,302 |
Cherington Capital LLC | $15,217,480 |
Edsi | $12,843,853 |
Meggitt PLC | $7,619,688 |
Eclypse International Corp | $6,092,300 |
Hal Hays Construction, Inc. | $5,999,806 |
Environmental Assessment and Remediation Management, Inc. | $5,365,975 |
First Defense International | $5,284,529 |
Phoenix Construction Services, Inc. | $4,640,212 |
Trend
2000 | $0 |
2001 | $0 |
2002 | $0 |
2003 | $0 |
2004 | $243,437,111 |
2005 | $177,875,021 |
2006 | $230,559,722 |
2007 | $253,567,005 |
2008 | $304,746,145 |
2009 | $38,222,119 |
|