NRC staff is performing review activities for possible licensing of new fuel cycle facilities. NRC accepted an application for construction of a mixed oxide fuel fabrication facility and is developing guidance on six policy issues related to gas centrifuge enrichment facilities. See the following pages for more information. See Fuel Cycle Facilities Licensing for an overview of the licensing process for fuel cycle facilities.
Organization |
Location |
Type of Facility |
Name of Facility |
Status |
Louisiana Energy Services (LES) |
Eunice, New Mexico |
Centrifuge enrichment |
National Enrichment Facility |
Application submitted to the NRC in December 2003. NRC license issued in June 2006. Facility began construction in August 2006. |
USEC Inc. |
Piketon, Ohio |
Centrifuge enrichment |
American Centrifuge Plant |
Application submitted to the NRC in August 2004. NRC license issued in April 2007. Facility began construction in May 2007. |
AREVA Enrichment Services
|
Bonneville County, Idaho |
Centrifuge enrichment |
Eagle Rock Enrichment Facility |
Application submitted to the NRC on December 30, 2008. |
General Electric - SILEX |
Wilmington, North Carolina | Laser enrichment |
Undetermined |
GE submitted a license amendment in June 2007 for a test loop, and planned to submit an application for a full-scale facility in early 2008. Location to be determined. |
Duke Cogema Stone & Webster |
Aiken, South Carolina | Mixed-oxide fuel fabrication facility |
N/A |
Application for construction authorization submitted in April 2001. Construction authorization issued by the NRC in March 2005. Application for operating license, submitted in November 2006, currently under NRC review. |