Correspondence - CMRR Certification
- April 28, 2009, Department letter transmitting the CMRR Certification Plan. [HTML] [PDF] [DOC]
- April 22, 2009, Department letter transmitting the CMRR Preliminary Safety Validation Report in support of CMRR Board certification. [HTML] [PDF] [DOC]
- April 21, 2009, Department letter responding to Board staff letters dated March 4, 2009 and March 30, 2009, regarding CMRR Board Certification. [HTML] [PDF] [DOC]
- April 21, 2009, Department letter responding to Board staff letter dated March 16, 2009, regarding CMRR Board Certification. [HTML] [PDF] [DOC]
- March 30, 2009, Board staff letter providing findings regarding CMMR SDDs do not incorporate PDSA requirements adequately. [HTML] [PDF] [DOC]
- March 16, 2009, Board staff letter providing findings regarding CMRR Inadequate identificaton of safety-related controls, functional requirements and performance criteria. [HTML] [PDF] [DOC]
- March 11, 2009, Department letter responding to two Board staff letters dated January 16, 2009 regarding CMMR Board Certification. [HTML] [PDF] [DOC]
- March 4, 2009, Board staff letter identifying concerns regarding documenting and maintaining Preliminary Documented Safety Analysis safety-related functions and requirements related to CMRR Board certification. [HTML] [PDF] [DOC]
- January 16, 2009, Board staff letter identifying seismic design concerns related to CMRR Board certification. [HTML] [PDF] [DOC]
- January 16, 2009, Board staff letter identifying active confinement ventilation system seismic design concern related to CMRR Board certification. [HTML] [PDF] [DOC]
|
This Site Last Updated: Tuesday, May 12, 2009
|
|
|
|