Vallecitos Boiling Water Reactor1.0 Site Identification
2.0 Site Status SummaryThe VBWR was shutdown in 1963 and NRC issued a possession only license in 1965. The license was renewed in 1973 and the license has remained effective under the provisions of 10 CFR 50.51(b). The facility has been maintained in SAFSTOR condition. The licensee plans to maintain the facility in SAFSTOR until ongoing nuclear activities are terminated and the entire site can be decommissioned. GE has a self-guarantee instrument. The spent fuel has been removed from the site. NRC issued an Order on September 6, 2007, approving the direct transfer of GE's interest in License TR-1 to GE-Hitachi Nuclear Energy Americas, LLC. 3.0 Major Technical or Regulatory IssuesNone 4.0 Estimated Date For Closure01/20/2019 |