Permitting Scenario |
Applicable Fee |
Existing Facilities with Existing Equipment Permits Applying for an Initial Title V Facility Permit |
Initial application fee shall be according to Rule 301(p)(3)(A) when the application is submitted. The final fee shall include staff time spent on the application according to Rule 301(p)(3)(B), Public Notice fee according to Rule 301(p)(9) and any applicable Public Hearing fee according to Rule 301(p)(10). |
Title V Facility Permit Revision Requests |
Revisions including permit terms or conditions, permit streamlining, alternative operating scenario, or a permit shield shall require applications with applicable fees according to Rule 301(p)(4) through (7), the sum of applicable fees shown in Rule 301(c) and (i), and any applicable Public Notice fee according to Rule 301(p)(9) and Public Hearing fee according to Rule 301(p)(10). |
Change of Operator with a valid Title V Permit |
Change of operator is handled as an Administrative Permit revision. The processing fees are those shown in Rule 301 (p)(6) plus the sum of applicable fees shown in Rule 301(c)(2). |
Administrative Title V Facility Permit Revision (definition) |
The processing fee shall be according to Rule 301(p)(6). |
Title V Facility Permit Revision (definition) |
For minor revision, de minimis significant revision, or significant permit revision, the fees are shown in Rule 301(p)(7), the sum of applicable fees shown in Rule 301(c) and (i), and any applicable Public Notice fee according to Rule 301(p)(9) and Public Hearing fee according to Rule 301(p)(10). |
Annual Renewal of Permit Units in the Title V Permit |
Applicable renewal fee for each active permit unit in the Title V is shown in Rule 301(d)(2). |
End of Term Renewal Fees |
Fees are specified in Rule 301(p)(8) at the end of term specified on the Title V Facility Permit. |
Public Notice for Title V Facility Permits |
Public notice fee shall include the costs incurred by the District per Rule 301(p)(9). |
Public Hearing For Title V Facility Permits |
Public hearing fee is specified in Rule 301 (p)(10). |
Title V Facility Permit Application Cancellation |
Final cancellation fee is specified in Rule 301(p)(11). |
Notice of Amount Due and Nonpayment Penalties |
Fee is specified in Rule 301(p)(12). |
Exemption from the Title V Program |
Plan application and applicable fees shall be calculated in accordance with Rule 306-Plan Fees.
Click here for other requirements. |
New Facilities Applying for an Initial Title V Facility Permit |
All initial processing fees [including Permits to Construct] shall be the sum of applicable fees shown in Rule 301(c) and (i) for all equipment at the facility, and the initial application fee according to Rule 301(p)(3)(A). The final fee shall also include staff time spent on the application according to 301(p)(3)(B) and any applicable Public Notice fee according to Rule 301(p)(9) and Public Hearing fee according to Rule 301(p)(10). |